HomeMy WebLinkAbout06.a. Award construction contract to Pacific Trenchless, Inc. re North Orinda Sewer Renovations, Phase 4, District Project 5973Board Meeting Date: May 17, 2012
subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE
GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO
SUBMITTAL REQUIREMENTS WITH PACIFIC TRENCHLESS, INC. FOR THE
CONSTRUCTION OF THE NORTH ORINDA SEWER RENOVATIONS, PHASE 4,
DISTRICT PROJECT NO. 5973
Submitted By: Initiating Dept. /Div.:
Mark Wenslawski, Associate Engineer Engineering /Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
M. Wenslawski S. Me s tsky A. Antkowiak Ann E. Farrell
General Manager
ISSUE: On May 2, 2012, six (6) sealed bids were received and opened for the
construction of the North Orinda Sewer Renovations, Phase 4, District Project
No. 5973. The Board of Directors must award the contract or reject bids within 50 days
of the bid opening. Authorize the General Manager to execute the contract documents
subject to SUBMITTAL requirements.
RECOMMENDATION: Find that the project is exempt from the California
Environmental Quality Act (CEQA), award a construction contract, and authorize the
General Manager to execute the Contract Documents subject to favorable review of
insurance certificates, bond submittals, appropriate Contractor license, and any other
required submittals (SUBMITTALS).
FINANCIAL IMPACTS: Approximately $2,589,000 including design, bid price,
contingency, and construction management.
ALTERNATIVES /CONSIDERATIONS: Reject all bids, which is not recommended.
BACKGROUND: North Orinda Sewer Renovations; Phase 4, is part of the ongoing
Collection System Renovation Program. The North Orinda Sewer Renovations,
Phase 4 project will renovate approximately 14,400 linear feet of 6- and 8 -inch sewer
lines in public streets and private easements in the City of Orinda. Construction of the
sewers in easements will involve close cooperation with customers for site access and
restoration.
District staff prepared the plans and specifications for the project. The Engineer's
estimate for construction of the North Orinda Sewer Renovations, Phase 4, is
$2,100,000. This project was advertised on April 1`2 and 19, 2012. Six (6) sealed bids,
ranging from $1,562,091 to $2,927,794, were received and publicly opened on May 2,
N: \PESUP \Cbradley \POSITION PAPERS \Wenslawski \5973 Award PRDOC Page 1 of 6
POSITION PAPER
Board Meeting Date: May 17, 2012
subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE
GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO
SUBMITTAL REQUIREMENTS WITH PACIFIC TRENCHLESS, INC. FOR THE
CONSTRUCTION OF THE NORTH ORINDA SEWER RENOVATIONS, PHASE 4,
DISTRICT PROJECT NO. 5973
2012. The Engineering Department conducted a technical and commercial review of
the bids and determined that Pacific Trenchless, Inc. is the lowest responsive bidder
with a bid amount of $1,562,091. A summary of bids received is shown in
Attachment 2.
The District will administer the construction contract and will provide contract
administration, inspection, survey, office engineering, and submittal review. The funds
required to complete this project, as shown in Attachment 3, are $2,139,000. The total
cost of the North Orinda Sewer Renovations, Phase 4, is anticipated to be $2,589,000.
This project is included in the fiscal year (FY) 2011 -12 Capital Improvement Budget
(CIB) on page CS -19. Staff has conducted a cash -flow analysis of the Collection
System Program budget and concluded that adequate funds are available for this
project.
Staff has concluded that this project is exempt from the California Environmental
Quality Act (CEQA) under District CEQA Guidelines, Section 15302, because it involves
replacement of sewers at substantially the same locations and with the same purpose
and level of activity of the facilities being replaced. Any capacity increases are for non -
growth inducing wet weather purposes. This project also is exempt under District
CEQA Guidelines Section 15061(b)( 3), since it can be seen with certainty that there is
no possibility that the activity in question may have a significant effect on the
environment. This certainty is based on the District's past experience with numerous
sewer construction projects of this nature, the relatively short distances involved, and
the District's mitigating construction specifications. These specifications are
standardized general and special conditions that are made part of the project bid
documents to address environmental considerations, such as protecting trees and
riparian areas, as well as compliance with applicable federal, state, county, district,
municipal and local laws, ordinances, orders, and regulations. Authorization of the
construction contract for this project will establish the Board of Directors' independent
finding that the project is exempt from CEQA.
RECOMMENDED BOARD ACTION: Staff recommends the following:
1. Find that the project is exempt from CEQA,
2. Award a construction contract in the amount of $1,562,091 for the construction of
the North Orinda Sewer Renovations, Phase 4, District Project No. 5973, to
Pacific Trenchless, Inc., the lowest responsive bidder, and
WPESUP\Cbradley \POSITION PAPERS \wenslawski \5973 Award PP.DOC Page 2 of 6
POSITION PAPER
Board Meeting Date: May 17, 2012
subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE
GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO
SUBMITTAL REQUIREMENTS WITH PACIFIC TRENCHLESS, INC. FOR THE
CONSTRUCTION OF THE NORTH ORINDA SEWER RENOVATIONS, PHASE 4,
DISTRICT PROJECT NO. 5973
3. Authorize the General Manager to execute the Contract Documents subject to
SUBMITTAL requirements.
N: \PESUP \Cbradley \POSITION PAPERS \Wenslawski \5973 Award PP.DOC Page 3 of 6
CREEK
V
-o
Vo
N
i
0 V2 1
MILE
24
Tf �ya
E
E
i
LEGEND:
v
I
11D
PROJECT LOCATION \ \
T
n
0
r Central Contra Costa Attachment
Sanitary District NORTH ORINDA SEWER RENOVATION
PHASE 4 PROJECT LOCATIONS
V DP 5973
f Page 4 of 6
ATTACHMENT 2
NORTH ORINDA SEWER RENOVATIONS, PHASE 4
DISTRICT PROJECT 5973
SUMMARY OF BIDS
PROJECT NO.: 5973 DATE: MAY 2, 2012
PROJECT NAME: NORTH ORINDA SEWER RENOVATIONS, PHASE 4
PROJECT LOCATION: ORINDA, CA.
NO. OF ADDENDA: 1 ENGINEER EST.: $2,100,000
NO.
BIDDER
BID PRICE
1
Pacific Trenchless, Inc.
$1,562,091
Oakland, CA 94607
2
K. J. Woods Construction
$1,738,000
San Francisco, CA 94124
3
Precision Engineering, Inc.
$1,787,930
San Francisco, CA 94124
4
California Trenchless, Inc.
$2,475,295
Dublin, CA 94568
5
McGuire and Hester
$2,683,405
Oakland, CA 94603
6
Ranger Pipelines
$2,927,794
San Francisco, CA 94124
BIDS OPENED BY /s /Elaine Boehme DATE May 2, 2012
N: IPESUMCbradleyTOSITION PAPERS\Wenslawski15973 Award PP.DOC Page 5 of 6
ATTACHMENT 3
NORTH ORINDA SEWER RENOVATIONS, PHASE 4
DISTRICT PROJECT NO. 5973
POST -BID / PRECONSTRUCTION ESTIMATE
No.
Item Description
Amounts
% Construction Cost
1.
CONSTRUCTION
a. Construction Contract
$1,562,091
b. Contingency at 15%
$234,909
c. Permits
$10,000
SUBTOTAL - CONSTRUCTION COST
$1,807,000
100%
2.
CONSTRUCTION MANAGEMENT
a. District Forces
- Inspection
$160,000
- Construction Management
$70,000
- Public Relations
$10,000
- Survey
$15,000
b. Consultants
- Material Testing
$10,000
- Geotechnical and Arborist
$15,000
SUBTOTAL - CONSTRUCTION MANAGEMENT
$280,000
15%
3.
PREBID EXPENDITURES
a. Engineering and Public Relations
$290,000
16%
b. Right of Way
$25,000
1%
c. Survey
$81,000
4%
d. Drafting
$106,000
6%
SUBTOTAL - PREBID EXPENDITURES
$502,00 0
28%
4.
TOTAL PROJECT COST
$2,589,000
5.
FUNDS AUTHORIZED TO DATE
$450,000
6.
ADDITIONAL ALLOCATION NEEDED TO COMPLETE
PROJECT Line 4 - Line 5
WPESUP\Cbradley \POSITION PAPERS \Wenslawski \5973 Award PP.DOC Page 6 of 6