Central Contra Costa Sanitary District
October 12, 2011
File: 8208.51.5.14
TO: HONORABLE BOARD OF DIRECTORS
VIA: JAMES M. KELLY, GENERAL MANAGER
ANN E. FARRELL, DIRECTOR OF ENGINE ING
TAD J. PILECKI, CAPITAL PROJECTS DIVI ION MANAGE • l
FROM: ALEX V. ROZUL, SENIOR ENGINEER
SUBJECT: CSOD ADMINISTRATION, CREW, AND WAREHOUSE FACILITY,
CONSTRUCTION PROGRESS, DISTRICT PROJECT 8208
The contractor's latest schedule update shows project completion on
November 10, 2011. The current contractual end date is October 14, 2011.
This represents a 27 day schedule slippage from the contractual end date.
Staff is in the process of negotiating various construction change orders of which
a number will result in adding days to the contract schedule. It is anticipated that
these negotiations will result in a contract end date that approximately matches
the contractor's scheduled completion date.
Construction work is proceeding on schedule for the planned ribbon cutting
ceremony on November 16 and staff move in on November 18. Ongoing key
construction activities include completing the interior trim and finish, starting and
testing the HVAC and elevator, repairing the permeable concrete and finishing
the site work landscaping.
Staff will continue to keep the Board updated on the construction progress.