HomeMy WebLinkAbout08.a.1) CSOD Update, DP 8208Central Contra Costa Sanitary District
August 25, 2011
File: 8208.51.5.14
TO: HONORABLE BOARD OF DIRECTORS
VIA: JAMES M. KELLY, GENERAL MANAGER
ANN E. FARRELL, DIRECTOR OF ENGINEERING
FROM: ALEX ROZUL, ROVISIONAL CAPITAL PROJECTS DIVISION
�"
MANAGER
SUBJECT: CSOD ADMINISTRATION, CREW, AND WAREHOUSE FACILITY,
CONSTRUCTION PROGRESS, DISTRICT PROJECT 8208
Based on the last construction schedule update through June, the Contractor is
50 calendar days behind schedule. Construction activity is ongoing throughout
the building, as well as in the middle and lower yards concurrently. The drywall
installation /finishing and interior wall paint are 90% complete. Other ongoing key
construction activities include concrete floor polishing, building elevator
installation, and site work landscaping and paving. Staff continues to work with
the Contractor to track progress, adjust construction activities, and find ways to
catch up on the schedule.
Staff will continue to keep the Board updated on the construction progress.