Central Contra Costa Sanitary District
July 27, 2011
File: 8208.51.5.14
TO: HONORABLE BOARD OF DIRECTORS
VIA: JAMES M. KELLY, GENERAL MANAGER
ANN E. FARRELL, DIRECTOR OF ENGIN RING R14- FROM: ALEX ROZUL, PROVISIONAL CAPITAL PROJECTS DIVISION
MANAGER:
SUBJECT: CSOD ADMINISTRATION, CREW, AND WAREHOUSE FACILITY,
CONSTRUCTION PROGRESS, DISTRICT PROJECT 8208
Based on the last construction schedule update through June, the Contractor is
50 calendar days behind schedule. The additional lost time was due to delays in
completing the drywall installation and finishing. The Contractor has added
another subcontractor to the project to catch up on the drywall work. Staff
continues to work with the Contractor to track progress, adjust construction
activities, and find ways to catch up on the schedule. Construction activity is
ongoing throughout the building, as well as in the middle and lower yards
concurrently. Key construction activities include completing the drywall
installation and finishing, interior painting, installing "T" bar ceiling, and installing
the building elevator system.
Staff will keep the Board updated on the construction progress.
/jf
NAINFRA \8208 - CSOD Facility \Construction Phase \55.0 Schedules, Reports \Presentations \BD Memos \BD memo CSOD