Central Contra Costa Sanitary District
July 13, 2011
File: 8208.51.5.14
TO: HONORABLE BOARD OF DIRECTORS
VIA: JAMES M. KELLY, GENERAL MANAGER
NN E. FAR DIRECTOR OF ENGINEERING �1
FROM: V ALEX ROZUL, OVISIONAL CAPITAL PROJECTS DIVISION
MANAGER
SUBJECT: CSOD ADMINISTRATION, CREW, AND WAREHOUSE FACILITY,
CONSTRUCTION PROGRESS, DISTRICT PROJECT 8208
No changes to the schedule were received since the last report. Based on the
last construction schedule update through May, the Contractor remains 27
calendar days behind schedule. The schedule update for June is expected next
week. Interior drywall taping and finishing is taking longer than expected, and
the Contractor has added additional drywall finishers to the project to catch up.
Staff continues to work with the Contractor to track progress, adjust construction
activities, and find ways to catch up on the schedule. Construction activity is
ongoing throughout the building, as well as in the middle and lower yards
concurrently. Key upcoming activities include painting and tiling the locker rooms
and bathrooms, and installing the building elevator system.
Staff will keep the Board updated on the construction progress.