Based on the last construction schedule update through May, the Contractor is
27 calendar days behind schedule. Interior drywall taping and finishing is taking
longer than expected. The Contractor's drywall subcontractor is working on
Saturdays to catch up on their work. Staff continues to work with the Contractor
to track progress, adjust construction activities, and find ways to catch up on the
schedule. Construction activity is ongoing throughout the building, as well as in
the middle and lower yards concurrently. Key upcoming activities include
providing power to the building, and installing the building elevator system.
Staff will keep the Board updated on the construction progress.