Central Contra Costa Sanitary District
June 9, 2011
File: 8208.51.5.14
TO: HONORABLE BOARD OF DIRECTORS
VIA: JAMES M. KELLY, GENERAL MANAGER
,MANN E. FARRELL, DIRECTOR OF ENGINE NG
ANDREW ANTKOWIAK, PROVISIONAL CAPITAL PROJECTS
DIVISION MANAGER
4
FROM: ALEX ROZUL, SENIOR ENGINEER
SUBJECT: CSOD ADMINISTRATION, CREW, AND WAREHOUSE FACILITY,
CONSTRUCTION PROGRESS, DISTRICT PROJECT 8208
The contractor is working on the May schedule update. Based on the last
construction schedule update through April, the Contractor is 17 calendar days
behind schedule. Staff continues to work with the Contractor to track progress,
adjust construction activities, and find ways to catch up on the schedule.
Construction activity is ongoing throughout the building, as well as in the middle
and lower yards concurrently. Key upcoming activities include placing permeable
concrete pavement in the middle yard, providing power to the building, and
installing the building elevator system.
Staff will keep the Board updated on the construction progress.