Central Contra Costa Sanitary District
May 25, 2011
File: 8208.51.5.14
TO: HONORABLE BOARD OF DIRECTORS
VIA: JAMES M. KELLY, GENERAL MANAGER
ANN E. FARRELL, DIRECTOR OF ENGINEERING
NDREW ANTKOWIAK, PROVISIONAL CAPITAL VROJECTS
DIVISION MANAGER
FROM: ALEX ROZUL, SENIOR ENGINEER
SUBJECT: CSOD ADMINISTRATION, CREW, AND WAREHOUSE FACILITY,
CONSTRUCTION PROGRESS, DISTRICT PROJECT 8208
No changes to the schedule were made since the last report. Based on the last
construction schedule update through April, the Contractor remains 17 calendar
days behind schedule. The schedule update for May is expected next week.
Staff continues to work with the Contractor to track progress, adjust construction
activities, and find ways to catch up on the schedule. Construction activity is
ongoing throughout the building, as well as in the middle and lower yards
concurrently. Key upcoming activities include providing power to the building,
and installing the building elevator system.
Staff will keep the Board updated on the construction progress.
/cb