HomeMy WebLinkAbout07.a.1) CSOD Update, DP 8208Central Contra Costa Sanitary District
May 19, 2011
File: 8208.51.5.14
TO: HONORABLE BOARD OF DIRECTORS
VIA: JAMES M. KELLY, GENERAL MANAGER
ANN E. FARRELL, DIRECTOR OF ENGINE RI
ANDREW ANTKOWIAK, PROVISIONAL CAPITAL PRO CTS
DIVISION MANAGER
FROM: ALEX ROZUL, SENIOR ENGINEER
SUBJECT: CSOD ADMINISTRATION, CREW, AND WAREHOUSE FACILITY,
CONSTRUCTION PROGRESS, DISTRICT PROJECT 8208
Based on the construction schedule update through April, the Contractor remains
17 calendar days behind schedule. Staff continues to work with the Contractor to
track progress, adjust construction activities, and find ways to catch up on the
schedule. Construction activity is ongoing throughout the building, as well as in
the middle and lower yards concurrently. Key upcoming activities include
providing power,to the building, and installing the building elevator system.
Staff will keep the Board updated on the construction progress.
/cb
NAPESUP\CONSTUstrict Projects \8208 \131D memo CSOD Schedule 5- 19- 11.doc