HomeMy WebLinkAbout06.a. Award contract re Lafayette/Pleasant Hill Road Trunk Sewer, DP 5994Central Contra Costa Sanitary District
' BOARD OF DIRECTORS .
POSITION PAPER
Board Meeting Date: May 5, 2011
Subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE
GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO
SUBMITTAL REQUIREMENTS WITH MOUNTAIN CASCADE, INC. FOR THE
CONSTRUCTION OF THE LAFAYETTE /PLEASANT HILL ROAD TRUNK SEWER,
DISTRICT PROJECT NO. 5994
Submitted By: Initiating Dept. /Div.:
Wesley Adams, Assistant Engineer Engineering /Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
ISSUE: On April 12, 2011, eleven (11) sealed bids were received and opened for the
construction of the Lafayette /Pleasant Hill Road Trunk Sewer, District Project No. 5994.
The Board of Directors must award the contract or reject bids within 50 days of the bid
opening. Authorize the General Manager to execute the contract documents subject to
SUBMITTAL requirements.
RECOMMENDATION: Find that the project is exempt from the California
Environmental Quality Act (CEQA), award a construction contract, and authorize the
General Manager to execute the Contract Documents subject to favorable review of
insurance certificates, bond submittals, appropriate Contractor license, and any other
required submittals (SUBMITTALS).
FINANCIAL IMPACTS: Approximately $2,614,000, including design, bid price,
contingency, and construction management.
ALTERNATIVES /CONSIDERATIONS: Reject all bids, which is not recommended.
BACKGROUND: The Collection System Master Plan 2010 Update analyzed the
District's entire sewer system using an updated ArcSNAP hydraulic model. The existing
wet - weather flows for the Lafayette /Pleasant Hill Road corridor were calculated at 130%
to 270% of full pipe capacity. The capacity- deficient sewers are 10 -inch and 12 -inch
pipes that extend across Pleasant Hill Road at Springhill Road, through easements on
Acalanes High School, then through additional neighborhood easements and streets to
an 18 -inch sewer north of the Highway 24 sewer crossing (see Attachment 1). The
Lafayette /Pleasant Hill Road Trunk Sewer Project will install a relief sewer within
Pleasant Hill Road and Stanley Boulevard, then upsize the existing sewer through the
neighborhood easement and streets. In addition, deteriorating local mains will be
N: \PESUP \Cbradley \POSITION PAPERS\Adams \5994 PP Award Contract.doc Page 1 of 6
Air)
W. Adams
A. Rozul l'.,Pid 'cki
A. Farrell
. Kelly,
eneral Manager
ISSUE: On April 12, 2011, eleven (11) sealed bids were received and opened for the
construction of the Lafayette /Pleasant Hill Road Trunk Sewer, District Project No. 5994.
The Board of Directors must award the contract or reject bids within 50 days of the bid
opening. Authorize the General Manager to execute the contract documents subject to
SUBMITTAL requirements.
RECOMMENDATION: Find that the project is exempt from the California
Environmental Quality Act (CEQA), award a construction contract, and authorize the
General Manager to execute the Contract Documents subject to favorable review of
insurance certificates, bond submittals, appropriate Contractor license, and any other
required submittals (SUBMITTALS).
FINANCIAL IMPACTS: Approximately $2,614,000, including design, bid price,
contingency, and construction management.
ALTERNATIVES /CONSIDERATIONS: Reject all bids, which is not recommended.
BACKGROUND: The Collection System Master Plan 2010 Update analyzed the
District's entire sewer system using an updated ArcSNAP hydraulic model. The existing
wet - weather flows for the Lafayette /Pleasant Hill Road corridor were calculated at 130%
to 270% of full pipe capacity. The capacity- deficient sewers are 10 -inch and 12 -inch
pipes that extend across Pleasant Hill Road at Springhill Road, through easements on
Acalanes High School, then through additional neighborhood easements and streets to
an 18 -inch sewer north of the Highway 24 sewer crossing (see Attachment 1). The
Lafayette /Pleasant Hill Road Trunk Sewer Project will install a relief sewer within
Pleasant Hill Road and Stanley Boulevard, then upsize the existing sewer through the
neighborhood easement and streets. In addition, deteriorating local mains will be
N: \PESUP \Cbradley \POSITION PAPERS\Adams \5994 PP Award Contract.doc Page 1 of 6
POSITION PAPER
Board Meeting Date: May 5, 2011
subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE
GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO
SUBMITTAL REQUIREMENTS WITH MOUNTAIN CASCADE, INC. FOR THE
CONSTRUCTION OF THE LAFAYETTE /PLEASANT HILL ROAD TRUNK SEWER,
DISTRICT PROJECT NO. 5994
rehabilitated. The project will install approximately 5,600 linear feet of 6- to 18 -inch
sewer pipe.
District staff prepared the plans and specifications for the project. The Engineer's
estimate for construction of the Lafayette /Pleasant Hill Road Trunk Sewer is
$2,300,000. This project was advertised on March 22 and 29, 2011. Eleven (11)
sealed bids, ranging from $1,729,650 to $2,521,480, were received and publicly
opened on April 12, 2011. The Engineering Department conducted a technical and
commercial review of the bids and determined that Mountain Cascade, Inc. is the
lowest responsive bidder with a bid amount of $1,729,650. Despite cost increases in
fuel and oil products in the past few months, staff continues to receive favorable bids.
A summary of bids received is shown in Attachment 2.
The District will administer the construction contract and will provide contract
administration, inspection, survey, office engineering, and submittal review. The funds
required to complete this project, as shown in Attachment 3, are $2,269,000. The total
cost of the Lafayette /Pleasant Hill Road Trunk Sewer is anticipated to be $2,614,000.
This project is included in the fiscal year (FY) 2010 -11 Capital Improvement Budget
(CIB) on page CS -55. Staff has conducted a cash -flow analysis of the Collection
System Program budget and concluded that adequate funds are available for this
project.
Staff has concluded that this project is exempt from CEQA under District CEQA
Guidelines Section 15302, because it involves replacement of existing sewer facilities at
substantially the same locations and with the same purpose and level of activity as the
facilities being replaced. Any capacity increases are for non - growth inducing,
wet - weather purposes. This project also is exempt under District CEQA Guidelines
Section 15061(b)(3), since it can be seen with certainty that there is no possibility that
the activity in question may have a significant effect on the environment. This certainty
is based on the District's past experience with numerous sewer construction projects of
this nature, the relatively short distances involved, and the District's mitigating
construction specifications. These specifications are standardized general and special
conditions that are made part of the project bid documents to address environmental
considerations, such as protecting trees and riparian areas, as well as compliance with
applicable federal, state, county, district, municipal and local laws, ordinances, orders,
and regulations.
WPESUP\Cbradley \POSITION PAPERS\Adams \5994 PP Award Contract.doc Page 2 of 6
POSITION PAPER
Board Meeting Date: May 5, 2011
Subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE
GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO
SUBMITTAL REQUIREMENTS WITH MOUNTAIN CASCADE, INC. FOR THE
CONSTRUCTION OF THE LAFAYETTE /PLEASANT HILL ROAD TRUNK SEWER,
DISTRICT PROJECT NO. 5994
RECOMMENDED BOARD ACTION: Staff recommends the following:
1. Find that the project is exempt from CEQA,
2. Award a construction contract in the amount of $1,729,650 for the construction of
the Lafayette /Pleasant Hill Road Trunk Sewer, District Project No. 5994, to
Mountain Cascade, Inc., the lowest responsive bidder, and
3. Authorize the General Manager to execute the Contract Documents subject to
SUBMITTAL requirements.
N: \PESUP \Cbradley \POSITION PAPERS\Adams \5994 PP Award Contract.doc Page 3 of 6
ATTACHMENT 1
LAFAYETTE/PLEASANT HILL ROAD TRUNK SEWER
DISTRICT PROJECT NO. 5994
LOCATION MAP
Q to ! :• �C r;..� �_
Brio es
Re ional Pa
rk
V.
IF
Xx
AX
v+
Fp- V � �;.:t t }�. `.•t Y �' ,s I � `: .,fir, �'•>. —rte
N:\PESUP\Cbradley \POSITION PAPERS\Adams \5994 PP Award Contract.doc Page 4 of 6
ATTACHMENT 2
LAFAYETTE /PLEASANT HILL ROAD TRUNK SEWER
DISTRICT PROJECT 5994
SUMMARY OF BIDS'
PROJECT NO.: 5994 DATE: APRIL 12, 2011
PROJECT NAME: LAFAYETTE /PLEASANT HILL ROAD TRUNK SEWER
PROJECT LOCATION: LAFAYETTE, CA
NO. OF ADDENDA: 1 ENGINEER EST.: $2,300,000
NO.
BIDDER
1
Mountain Cascade, Inc.
Livermore, CA 94550
2
D'Arcy & Harty Construction, Inc.
San Francisco, CA 94124
3
Precision Engineering
San Francisco, CA 94105
4
California Trenchless
Hayward, CA 94545
5
K. J. Woods Construction
San Francisco, CA 94124
6
McNamara & Smallman Constructi
Livermore, CA 94550
7
Ghilotti Construction Company
Santa Rosa, CA 95407
8
J & M, Inc.
Livermore, CA 94550
9
Carone & Company, Inc.
Concord, CA 94520
10
Shaw Pipeline
San Francisco, CA 94134
11
Tidelands Construction Company
Brentwood, CA 94513
BIDS OPENED BY /s/ Elaine Boehme DATE April 12, 2011
N: \PESUP \Cbradley \POSITION PAPERS\Adams \5994 PP Award Contract.doc Page 5 of 6
ATTACHMENT 3
LAFAYETTE /PLEASANT HILL ROAD TRUNK SEWER
DISTRICT PROJECT NO. 5994
POST -BID / PRECONSTRUCTION ESTIMATE
No.
Item Description
Amounts
% Construction Cost
1.
CONSTRUCTION
a. Construction Contract
$1,729,650
b. Contingency at 15%
$259,350
c. Permit
50,000
SUBTOTAL - CONSTRUCTION COST
$2,039,000
100%
2.
CONSTRUCTION MANAGEMENT
a. District Forces
- Inspection
$200,000
- Construction Management
$60,000
- Public Relations
$15,000
b. Consultants
- Material Testing
$25,000
- Geotechnical and Arborist
$10,000
SUBTOTAL - CONSTRUCTION MANAGEMENT
$310,000
15%
3.
PREBID EXPENDITURES
a. Engineering
$259,000
13%
b. Right of Way
$6,000
0%
SUBTOTAL - PREBID EXPENDITURES
$265,00 0
13%
4.
TOTAL PROJECT COST
$2,614,000
5.
FUNDS AUTHORIZED TO DATE
$345,000
6.
ADDITIONAL ALLOCATION NEEDED TO
COMPLETE PROJECT (Line 4 - Line 5)
$2,269,000
N: \PESUP \Cbradley \POSITION PAPERS\Adams \5994 PP Award Contract.doc Page 6 of 6