April 14, 2011
File: 8208.51.5.14
TO: HONORABLE BOARD OF DIRECTORS
VIA: JAMES M. KELLY, GENERAL MANAGER
ANN E. FARRELL, DIRECTOR OF ENGINEERIN
TAD J. PILECKI, CAPITAL PROJECTS DIVISION M NAGE
FROM: ALEX ROZUL, SENIOR ENGINEER R.-�
SUBJECT: CSOD ADMINISTRATION, CREW, AND WAREHOUSE FACILITY,
CONSTRUCTION PROGRESS, DISTRICT PROJECT 8208
Weather last month was inclement with 16 of 23 working days considered rain
days. The schedule update for March was just received and is under review.
Per the last report, the Contractor is 35 calendar days behind schedule. Staff
continues to work with the contractor to track progress, adjust construction
activities and find ways to catch up on the schedule. Current construction
activities include installing HVAC ducting, electrical conduits, plumbing, building
insulation and drywall. In addition, construction in the middle and lower yards
has restarted with various concrete enclosures.
Staff will keep the Board updated on the construction progress.