HomeMy WebLinkAbout06.a.1) CSOD Construction Progress Update, DP 8208Central Contra Costa Sanitary District
April 7, 2011
File: 8208.51.5.14
TO: HONORABLE BOARD OF DIRECTORS
VIA: JAMES M. KELLY, GENERAL MANAGER
ANN E. FARRELL, DIRECTOR OF ENGINE RING 1 (v,4.ft"Tr
TAD J. PILECKI, CAPITAL PROJECTS DIVISION MA A ER IV
FROM: ALEX ROZUL, SENIOR ENGINEER
SUBJECT: CSOD ADMINISTRATION, CREW, AND WAREHOUSE FACILITY,
CONSTRUCTION PROGRESS, DISTRICT PROJECT 8208
Based on the construction schedule update through February, the Contractor is
35 calendar days behind schedule. The additional delay was due to the framing
subcontractor taking longer than scheduled to complete the interior metal
framing. Staff continues to work with the contractor to track progress, adjust
construction activities, and find ways to catch up on the schedule. Current
construction activities remain focused on building construction with an emphasis
on completing the roof and exterior walls.
Staff will keep the Board updated on the construction progress.
NAPESUPICONSTUstrict Projects182081BD memo CSOD Schedule 4- 7- 11.doc