March 17, 2011
File: 8208.51.5.14
TO: HONORABLE BOARD OF DIRECTORS
VIA: JAMES M. KELLY, GENERAL MANAGER
ANN E. FARRELL, DIRECTOR OF ENGINEERING -
TAD J. PILECKI, CAPITAL PROJECTS DIVISION MANAGE1
FROM: ALEX ROZUL, SENIOR ENGINEER
SUBJECT: CSOD ADMINISTRATION, CREW, AND WAREHOUSE FACILITY,
CONSTRUCTION PROGRESS, DISTRICT PROJECT 8208
Due to the inclement weather, seven calendar days were added to the
construction schedule in February. The contractor continues to work on the
construction schedule revisions, and the update for February has not been
received yet. The contractor remains 27 calendar days behind schedule. Staff
continues to work with the contractor to track and adjust construction activities,
Current .construction activities remain focused on building construction with an
emphasis on completing the roof and erecting the exterior walls.
Staff will keep the Board updated on the construction progress.