HomeMy WebLinkAbout06.a.1) CSOD update, District Project 8208Central C March 17, 2011 File: 8208.51.5.14 TO: HONORABLE BOARD OF DIRECTORS VIA: JAMES M. KELLY, GENERAL MANAGER ANN E. FARRELL, DIRECTOR OF ENGINEERING - TAD J. PILECKI, CAPITAL PROJECTS DIVISION MANAGE1 FROM: ALEX ROZUL, SENIOR ENGINEER SUBJECT: CSOD ADMINISTRATION, CREW, AND WAREHOUSE FACILITY, CONSTRUCTION PROGRESS, DISTRICT PROJECT 8208 Due to the inclement weather, seven calendar days were added to the construction schedule in February. The contractor continues to work on the construction schedule revisions, and the update for February has not been received yet. The contractor remains 27 calendar days behind schedule. Staff continues to work with the contractor to track and adjust construction activities, Current .construction activities remain focused on building construction with an emphasis on completing the roof and erecting the exterior walls. Staff will keep the Board updated on the construction progress. Icb NAPESUPICONSTUstrict Projects182081BD memo CSOD Schedule 3- 17- 11.doc