Staff continues to work with the contractor to develop a revised construction
schedule. Based on the last schedule update the contractor was 42 calendar
days behind schedule, with 243 calendar days remaining. Current construction
activities remain focused on building construction with an emphasis on
completing the roof and erecting the exterior walls. In addition, with the recent
fair weather, site work for permeable pavement has resumed with finish grading
in the middle yard and construction of cutoff wails. a
Staff will keep the Board updated on the construction progress.
Icb