HomeMy WebLinkAbout06.a.1) Update on Collection Operations Facility (DP 8208)Central Contra Costa Sanita istrict January 12, 2011 File: 8208.51.5.14 SUBJECT: CSOD ADMINISTRATION, CREW, AND WAREHOUSE FACILITY, CONSTRUCTION PROGRESS, DISTRICT PROJECT 8208 No schedule update for December Was received. As reported in the previous memo to the Board, the contractor is developing a revised construction schedule that more closely represents the sequence of ongoing construction, and accurately identifies the activities and their durations necessary to complete the project Within the contract time. Based on the last schedule update, the contractor Was 42 calendar days behind schedule With 243 calendar days remaining. Current construction activities remain focused on building construction With an emphasis on completing the Work necessary to erect the exterior Walls. Staff will keep the Board updated on the construction progress. Ic b NAPESUPICONSTOistrict Projects182081BD memo CSOD Schedule 1- 12- 11.doc