HomeMy WebLinkAbout07.a.1) CSOD UpdateCentral Contra Costa Sanitary District
December 28, 2010
File: 8208.51.5.14
TO: HONORABLE BOARD OF DIRECTORS
VIA: JAMES M. KELLY, GENERAL MANAGER '�
ANN E. FARRELL, DIRECTOR OF ENGINE ING
�Cr -TAD J. PILECKI, CAPITAL PROJECTS DIVISION MANAGE
FROM: ALEX ROZUL, SENIOR ENGINEER6�
SUBJECT: CSOD ADMINISTRATION, CREW, AND WAREHOUSE FACILITY,
CONSTRUCTION PROGRESS, DISTRICT PROJECT 8208
The contractor's construction schedule update for the month of November
indicates that, as of November 30, construction is 42 calendar days behind
schedule with 243 calendar days remaining on the contract. Staff is working with
the contractor to develop a recovery schedule that more closely represents the
sequence of ongoing construction. Current construction activities are focused on
completing work necessary to erect the exterior walls, and manage the site
conditions during the wet weather season.
Staff will keep the Board updated on the construction progress.