HomeMy WebLinkAbout07.a.1) CSOD UpdateCentral Contra Costa Sanitary District December 28, 2010 File: 8208.51.5.14 TO: HONORABLE BOARD OF DIRECTORS VIA: JAMES M. KELLY, GENERAL MANAGER '� ANN E. FARRELL, DIRECTOR OF ENGINE ING �Cr -TAD J. PILECKI, CAPITAL PROJECTS DIVISION MANAGE FROM: ALEX ROZUL, SENIOR ENGINEER6� SUBJECT: CSOD ADMINISTRATION, CREW, AND WAREHOUSE FACILITY, CONSTRUCTION PROGRESS, DISTRICT PROJECT 8208 The contractor's construction schedule update for the month of November indicates that, as of November 30, construction is 42 calendar days behind schedule with 243 calendar days remaining on the contract. Staff is working with the contractor to develop a recovery schedule that more closely represents the sequence of ongoing construction. Current construction activities are focused on completing work necessary to erect the exterior walls, and manage the site conditions during the wet weather season. Staff will keep the Board updated on the construction progress. Icb NAPESUPICONSTUstrict Projects182081BD memo CSOD Schedule 12 -28 -1 o.doc