HomeMy WebLinkAbout4/10/2008 AGENDA BACKUPAgenda Item 3)
Capital Projects Special Meeting of April 10, 2008
Announcements:
a) District Surplus Sale of Computers and Eguipment
On Saturday, April 12, 2008, Nationwide Auction Systems will conduct the
District's surplus sale of computers and equipment. The auction site is 1
Oak Road in Benicia. Gates open at 7 a.m. for an inspection period that
will end at 8:30 a.m., and the auction will begin at 9 a.m.
2008/09 Capital Improvements
Program
Board Workshop
April 10, 2008
2008/09 Capital Improvements Program Workshop
Agenda
• Review Board role in Capital planning and future challenges
• Review planned 2008/09 Capital Expenditures
• Review programs and selected 2008/09 projects
— Collection System Program
• A -line Phase 2A
• Renovation Program
— Treatment Plant Program
• Mercury Removal Project
• Green House Gas Reduction
— Recycled Water Program
• Industrial Recycled Water Planning
— General Improvements Program
• Collection System Operations Facility Improvements
• Information Technology Plan
• Revisit future planning challenges and review next steps in
Capital Budgeting process
Capital Improvement Budget Summary for
FY 2008/09
Board Role in Capital Program is Ongoing
• Authorize Program Budgets each fiscal year in June
• Re- authorize Program Budgets in August with
actual carryover amounts (new)
• Authorize Supplemental Program Funds if needed
• Create New Projects > $25,000
• Award Construction Projects > $15,000
• Authorize Construction Change Orders >$50,000
• Authorize Consultant Contracts > $50,000
• Authorize Revisions to Consultant Contracts > 15%
2
Estimated
Estimated
Estimated
Total
Program
FY 2008/09
Carry -over
Allocation
FY 2008/09
Program
from Prior
FY 2008/09
Proposed
Expenditures
Fiscal Year
Authorization
Treatment Plant
$12,680,000
$16,279,000
$10,660,000
$26,939,000
Collection System
$22,355,000
$13,688,000
$17,339,000
$31,027,000
General
Improvements
$3,418,000
$783,000
$3,071,000
$3,854,000
Recycled Water
$405,000
$30,000
$399,000
$429,000
To
Total
$38,858,000
$30,780,000
$31,469,000
$62,249,000
2008109
Board Role in Capital Program is Ongoing
• Authorize Program Budgets each fiscal year in June
• Re- authorize Program Budgets in August with
actual carryover amounts (new)
• Authorize Supplemental Program Funds if needed
• Create New Projects > $25,000
• Award Construction Projects > $15,000
• Authorize Construction Change Orders >$50,000
• Authorize Consultant Contracts > $50,000
• Authorize Revisions to Consultant Contracts > 15%
2
Next Steps in CIB /CIP Process
• April 17, 2008 set Public Hearing for CIB /CIP
• May 15, 2008 hold Public Hearing and Approve
CIB /CIP
• June 5, 2008 Board Adopts all Budgets, including
CIB /CIP, officially Authorizing the FY 2008/09 CIB
• June 5, 2008 Board Approves Closeout Position
Paper for completed CIB projects
• Hold Board briefing on closed out projects for any
interested Board members after June 5, 2008
• August 2008, ask Board to Reauthorize FY 2008/09
CIB with actual carryover amounts (new this year)
November 2008 will be critical decision
point for a number of issues....
• Is Ad Valorem Tax lost... if so, how is Capital Program
impacted?
• To Expand or Contract Renovation Program?
— Expand if master plan reduces capacity expenditure needs?
— Expand if peer agencies are outpacing us?
— Contract if AVT is lost?
• To Construct or Not To Construct Mercury Removal?
— Construct if funds available and air emissions are a concern?
— Defer, particularly if AVT lost?
• To Add Projects to Reduce Green House Gas
Emissions?
— Will regulations be taking shape?
— Should projects be budgeted or wait and see?
• To increase Treatment Plant Renovation based on
Asset Mgmt Plan?
Listen today and then stay tuned .............
3
FY 2008/09 Expenditure
Recommendations
EXPENDITURES (% Capital Program)
FY 2008/09
Collection System
$22,355,000 (57 %)
Treatment Plant
$12,680,000 (33 %)
General Improvements
$3,418,000 (9 %)
Recycled Water
$405,000 (1 %)
TOTAL EXPENDITURES
$38,858,000 (100°/x)
FY 2008 -09 Collection System Program
Expenditures by Subprogram
Program /Subprogram
FY 2008 -09 Expenditures
Total Collection System Program
$22.4 million (100 %)
Expansion /Capacity Improvements
(Driven by $8M A -line Phase 2A)
$12.5 million (56 %)
Renovation
$8.3 million (37 %)
Pumping Stations /Force Mains
$1.2 million (6 %)
Regulatory Compliance /Planning
$.3 million (1 %)
2008/09 Large Project Expenditures
Collection System Program
PROJECT
2008109
Expenditures
Total
Project Cost
A -Line Phase 2 -A Capacity Improvements
$8,125,000*
$20,000,000*
Camino Pablo Trunk Sewer /Flush Kleen FM
$1,850,000
$2,200,000
Walnut Creek Sewer Renovation — Phase 6
$1,800,000
$2,200,000
Lafayette Sewer Renovation — Phase 5
$1,500,000
$1,700,000
Martinez Sewer Renovation — Phase 2
$1,200,000
$1,400,000
South Orinda Sewer Renovation — Phase 3
$1,200,000
$1,400,000
2007/08 Development Sewerage
$1,180,000
NA
Alhambra Valley Assessment Districts
$1,000,000
$2,000,000
TV Inspection Program
$900,000
$5,600,000
Total Collection System Projects <$900,000
$3,600,000
NA
Total Collection System Program
$22,355,000
NA
*Discussion of A -line and Renovation Program to follow
A- Line /Concord Joint Project Overview
.00 ....
A -L= a .r1.IC.1O11
5
A- Line /Concord Joint Project Cost Update
Facility
Total Cost
Concord Portion
A -line
Phase 2A
$14.8 million
$4.4 million
Concord Intertie
$7.2 million
$7.2 million
Recycled Water
Line (deferred)
$0 million
$0 million
Total Cost
$22 million
$11.6 million
A- Line /Concord Joint Project
Updated Construction Schedule
• Award Construction
• Notice to Proceed
• Begin Tunneling
• Cross Walnut Creek
• Tie -in Concord Flows
• Complete Construction
October 2007
February 2008*
April 2008
June 2008
September 2008
February 2009*
* Six month delay primarily due to tunneling machine not available.
DRIVING 70 FOOT LONG SHORING
PILES FOR MAIN TUNNELING PIT
***BOARD TOUR WILL BE SCHEDULED WHEN
EPBM BORING MACHINE IS ON SITE... EST 4122 * **
7
EXCAVATING SOIL FROM MAIN
TUNNELING PIT
TUNNEL PIT SOIL DISPOSAL NEAR
FILTER PLANT SITE
PLACING CONCRETE FLOOR IN MAIN
TUNNELING PIT
INSPECTING PIPE AT THE AMERON
PLANT
LOAD TESTING OF 96 INCH PIPE
I
INSPECTING PIPE AT THE AMERON
PLANT
INSPECTING FINISHED PRODUCT
Ten Year Collection System Capital
Improvement Program Budgets
approximately 50% of $178 million in
Planned Collection System Expenditures for
TV Program and Renovation Projects
10
Investment in Sewer Renovation
Continues.....
*Based on Total Project Cost in 2007 -08 of approximately
$1.75 million per mile renovated /replaced. This cost may
decrease in 2008 -09 favorable bid climate.
Definition of Future Needs Continues...
• Extrapolation of TV results indicates that
about 100 miles of 6,8 and 10 -inch sewer
mains still need to be renovated
• Plan next 10 years — 46 miles renovated
• 54 miles will remain after next ten years
unless rate of renovation expenditures are
increased or cost per mile decreases
• Sewers will continue to deteriorate
11
FY 90/91 — 99/00
4 Miles/Year = 40 Miles
10 Yr Cost = $40 M
Renovation
FY 00/01 — 07/08
5.3 Miles/Year = 42.1 Miles
Program
8 Yr Cost = $49 M
FY 08/09 —17/18
4.6 Miles/Year = 46 Miles
10 Yr Cost = $81 M*
TV Program
900 Miles of 1500 Miles of District Sewers
Inspected to Date
*Based on Total Project Cost in 2007 -08 of approximately
$1.75 million per mile renovated /replaced. This cost may
decrease in 2008 -09 favorable bid climate.
Definition of Future Needs Continues...
• Extrapolation of TV results indicates that
about 100 miles of 6,8 and 10 -inch sewer
mains still need to be renovated
• Plan next 10 years — 46 miles renovated
• 54 miles will remain after next ten years
unless rate of renovation expenditures are
increased or cost per mile decreases
• Sewers will continue to deteriorate
11
How to "right size" sewer renovation
program?
• Complete TV program / validate extrapolation figures
• Research renovation programs of peers to determine
how CCCSD compares in renovation investment
• Complete Collection System Master Plan to validate
and revisit cost/timing of needed capacity projects
• Review /optimize right of way /design /construction
process to minimize project costs
• Develop report to Board for November 2008 CIB
Workshop on "Right Sizing" renovation program
FY 2008 -09 Treatment Plant Program
Expenditures by Subprogram
Program /Subprogram
FY 2008 -09 Expenditures
Total Treatment Plant Program
$12.7 million (100 %)
One -Time Renovation
$4.9 million (39 %)
Recurring Renovation
$4.8 million (38 %)
Regulatory Compliance /Planning
$2.2 million (17 %)
Expansion /Capacity Improvements
$.3 million (3 %)
Other Miscellaneous Projects
$.4 million (3 %)
12
2008 -09 Large Project Expenditures
Treatment Plant Program
PROJECT
2008109
Expenditures
Total Project Cost
Piping Renovations & Replacement- Phase4
$1,800,000
$1,800,000
Plant Site Improvements
$1,500,000
$2,500,000
Standby Power Facility Improvements
$1,200,000
$6,800,000
Primary Structures Demolition
$1,100,000
$1,400,000
Solids Handling Improvements
$1,054,000
$6,500,000
Aeration Air Renovations
$1,000,000
$2,100,000
Scrubber Water Mercury/Metals Removal*
$1,000,000
$20,300,000
Treatment Plant Asset Management
$1,000,000
$1,200,000
Total Treatment Plant Projects< $1,000,000*
$3,046,000
NA
Total Treatment Plant Program
$12,700,000
NA
*Discussion of Mercury Removal and Green House Gas Emissions to follow
Mercury was Greatest Regulatory Challenge
Effluent Limits Now Achievable for Short Term
• Interim Limit* 87 ppt Superceded by TMDL/Watershed P.
• Final Limit* 18 ppt Superceded by TMDL/Watershed P.
• Watershed Permit Limit* 66 ppt Effective March 1, 2008
• CCCSD Actual 24 ppt 2007 Max Monthly Ave
• Watershed Calc Limit ** 41 ppt Based on 2.23 kg /yr **
• CCCSD Actual 19 ppt 2007 Annual Ave
*Monthly average effluent limit
* *Watershed Permit Allowable Mass
2.23 kg /yr 2008
1.8 kg /yr 2018
1.3 kg /yr 2028
13
0.5
0.45
0.4
0.35
0.3
0.25
777 0.2
0.15
0.1
0.05
0
Effluent Mercury Concentration
991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007
Year
-- - AV9iAGE1�lNhA) • - "AVH3AGE(�tr0) -r -D LY M4XM.1M
14
Influent Mercury Concentration
,a
-- --------------------------------------------
a--
---------------------------------------------------
9
-- -------------------------------------------------
7
-- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
J 8
- - - -- - - - - - - - -- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
7 5
-- --- --------------------------------------------------
q__
_ -__ ._---_.-__.______-- _--- __- ____._.__- .__-- _. -_____
3
__.__ __-___-.__-______ _______- ___- ._-- _________ - -_ - -.
2
__ -_- _- _.-- __- .___ -_ ___ ___.__- ._- _- _.________
_ .__
1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007
Year
- �AVIRAOE(MMOL) __.A__- AyCRAO!(I,p�O) �DALYIMNM/A
0.5
0.45
0.4
0.35
0.3
0.25
777 0.2
0.15
0.1
0.05
0
Effluent Mercury Concentration
991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007
Year
-- - AV9iAGE1�lNhA) • - "AVH3AGE(�tr0) -r -D LY M4XM.1M
14
Where does Hg come from and
where does it go?
(2003 analysis based on historical data)
INTO PLANT
• 34.7 Ib /yr plant influent
RECYLE WIN PLANT
• 19.3 Ib /yr recycled scrubber water
• 33.2 Ib /yr to aeration basins
OUT OF PLANT
• 29.1 Ib /yr air emissions
• 4.8 Ib /yr plant effluent
• 0.8 Ib /yr grit/ash
Total 34.7 Ib /yr
Where does Hg come from and
where does it go?
2007 UPDATE
INTO PLANT
• 14.5 Ib /yr plant influent
Mercury air emissions are
still a potential
concern....... as is effluent
mass reduction to
1.3 kg /yr in 2028
OUT OF PLANT
• 11.8 Ib /yr air emissions
• 2.3 Ib /yr (1.03 kg /yr)
plant effluent
• 0.4 Ib /yr grit/ash
Total 14.5 Ib /yr
15
Long Term Mercury Removal Solutions
Cost Comnarisnn
Approach
Capital Cost
PW Annual
Total PW
O&M Cost
Cost
(20 yrs)
(20 yrs)
Haul Dewatered Sludge —
$4 million
$133 million
$137 million
Facility being constructed
for reliability... would allow
shutdown of incinerators
Scrubber Water
$40 million
$90 million
$130 million
Treatment — Does not
adequately address air
emissions... on hold
Dry Scrubber Air
$21 million
$87 million
$108 million
Treatment — Most cost
effective method to
address air and effluent
mercury emissions
Currently being piloted...
MEIROU .Y Removal Pilot
16
MERCURY PILOT PLANT OVERVIEW
MERCURY PILOT PLANT
COMPONENTS
PRIMARY HEAT EXCHANGER & CARBON FEEDER
WATER INJECTION
17
Ten Year Treatment Plant Capital
Improvement Program does NOT Budget
for Projects to Respond to Climate Change
and Green House Gas Regulations.
Regulations being developed for Green
House Gas (GHG) reductions could have
significant impacts....
• AB 32 (2006 Global Warming Solutions Act)
— Reduce statewide GHG emissions to 1990 levels
by 2020 (approx. 25% reduction)
— Requires Air Resources Board to develop
regulations on:
1.GHG reporting by 2008
2. Specific GHG emission reduction requirements by 2012
(Implementation Plan)
• Governors Executive Order
— Reduce statewide GHG emissions by an
additional 80% by 2050
20
-Aer" Illi* ..,. ;
. rnia's
a h
i
eons re
• ers
41 (8%
Transportation
00(41%)
Electric Power
109(22%)
* *All value
in MMT CO
all
Equivalent
Agriculture &
al
Forestry
41(8%)
MmMmy ofCaVornia Ownhou a Gas &WmA nr and Sinks.- 19910 to 1004
Status of Regulatory Development
• ARB adopted mandatory GHG reporting regulations
January 2008
• CCCSD must begin reporting April 2009 for 2008
calendar year
• ARB is holding scoping meetings to develop draft
emission reduction regulations
• Will take several years to develop and finalize
specific emission reduction regulations and market
mechanisms... legally enforceable January 1, 2012
• Reductions in place by December 31, 2020
21
District GHG Inventory Summary
• 1990 emissions were 52,612 metric tons of CO2eq
• Cogen facility operational in 1995
• Cogen footprint 21,741 metric tons of CO2eq is larger
than replaced PG &E footprint of 6,000 metric tons of
CO2eq because of PG &E renewable power
• 2006 emissions were 69,296 metric tons of CO2eq
Therefore, would have to reduce emissions by
16,684 metric tons of CO2eq or 24% to return to
1990 levels.
How much will CCCSD actually have to
reduce?
• We don't know yet how much CCCSD will have to
reduce! (could be more than 24 %)
• Why? Mobile sources (the largest emissions sector)
are difficult and controversial to regulate
• Large stationary sources are easier to regulate and it
is sometimes assumed that it is easier for large
utilities to raise money for control measures
• For now, CCCSD should plan to reduce to 1990
levels by 2020 while we await development of the
regulations
22
What can CCCSD do to reduce GHG
emissions?
• Reduce energy use through conservation and
changes in operation
• Use alternative forms of energy
• Purchase carbon credits on the open market
Energy Efficiency and GHG's
• Energy use is directly related to GHG emissions
...generally the more power we use, the bigger our
carbon footprint
• Two prior energy conservation studies have been
conducted (1990 & 1996)
• The District has already implemented recommended
energy savings strategies (VFDs; peak shaving of
influent flows; high efficiency motors, lighting and HVAC)
• No more "low hanging fruit"
• However, some energy savings may be still possible and
energy study should be updated
23
Alternative Energy and GHG's
• District Staff completed study February 2008
• Evaluated 15 different alternative energy
technologies
• Recommended four options for additional study
— Solar at plant (large scale - sell power for "credits ")
— Solar at remote sites
— Bio Diesel
— Purchase of Green Power
• Most technologies are not cost - effective due to low
cost power available from cogeneration
— Cogeneration is greatest source of GHG emissions added since
1990
— Cogeneration provides essential redundancy through onsite
power generation
• Consultant peer review of staff work is next....
Next Steps to Comply with AB32
• Proactively monitor AB 32 regulatory development
• Submit 2008 GHG inventory to ARB in April 2009 per
regulations
• Complete update of energy conservation study
• Complete peer review of alternative energy study
• Develop potential scenarios for meeting 24% ++
reduction... consider including in next years CIB /CIP
• Analyze GHG impacts of future projects in CIB, as
necessary
• Follow development of carbon trading markets
24
2008/09 Expenditures
Recycled Water Program
*Discussion of potential Industrial Recycled Concepts to follow
Potential Industrial Recycling Concepts
Being Evaluated
• CCCSD Serve Power Plant in East County through
abandoned pipeline
• CCWD Serve Power Plant in East County from raw
water canal and CCCSD Serve Local Refineries
• CCCSD Serve Power Plant on District Site
• CCWD Transfer Water to Other User and CCCSD
Serve Local Refineries
25
2008109
Total
PROJECT
Expenditures
Project Cost
Recycled Water — Pleasant Hill Phase
$340,000
NA
16
Total Remaining Recycled Water
Projects including Industrial Concepts
$65,000
NA
Planning*
Total Recycled Water Program
$405,000
NA
*Discussion of potential Industrial Recycled Concepts to follow
Potential Industrial Recycling Concepts
Being Evaluated
• CCCSD Serve Power Plant in East County through
abandoned pipeline
• CCWD Serve Power Plant in East County from raw
water canal and CCCSD Serve Local Refineries
• CCCSD Serve Power Plant on District Site
• CCWD Transfer Water to Other User and CCCSD
Serve Local Refineries
25
28
CSO PROJECT APPROVAL PROCESS
ADMINISTRATIVE DRAFT MND REVIEW BY THE
SEPTEMBER 13, 2007
�I
CITY OF WALNUT CREEK
FEBRUARY 2009
DRAFT MND AVAILABLE FOR PUBLIC REVIEW
NOVEMBER 9, 2007
END OF PUBLIC REVIEW PERIOD
DECEMBER 10, 2007
CCCSD BOARD APPROVES MND, MMRP, AND
DECEMBER 20, 2007
PROPOSED PROJECT
JULY - AUGUST 2009
CCCSD SUBMITS CONDITIONAL USE PERMIT
JANUARY 14, 2008
(CUP) APPLICATION CITY OF WALNUT CREEK
SEPTEMBER. 2009 —
CITY REVIEW OF CUP APPLICATION
JANUARY - APRIL
(130 detailed comments reed Feb 14 1resubmital
2008
with comments incorporated April 9)
DECEMBER 2010
CITY STAFF DEEMS APPLICATION COMPLETE
MAY 2008
CITY DESIGN REVEW COMMISSION HEARING
MAY - JUNE 2008
CITY PLANNING COMMISSION HEARING
JULY 2008
CUP APROVAL
AUGUST 2008
PRELIMINARY CSO FACILITY
DESIGN /CONSTRUCTION SCHEDULE
PREPARE DETAILED DESIGN PLANS AND
AUGUST 2008 -
SPECIFICATIONS FOR BIDDING
FEBRUARY 2009
CITY PLAN CHECK (FOR BUILDING PERMIT)
AND
MARCH - JUNE 2009
SITE DEVELOPMENT PERMIT
BIDDING /AWARD OF CONSTRUCTION
JULY - AUGUST 2009
CONTRACT
CONSTRUCTION OF NEW
SEPTEMBER. 2009 —
ADMINISTRATION /CREW/ WAREHOUSE
NOVEMBER 2010
BUILDING
OCCUPANCY OF NEW BUILDING
DECEMBER 2010
DEMOLITION AND LANDSCAPING OF
DECEMBER 2010 -
EXISTING ADMINISTRATION /CREW BUILDING
MARCH 2011
29
Capital Program Impacts from Potential
Loss of Ad Valorem Taxes
• Loss of Ad Valorem Taxes (AVT) not known till State
budget adopted (estimated September /October 2008)
• Sewer Construction Fund Balance is adequate to
fund program for several years if AVT is lost
• Bid climate is excellent at current time and many
needed projects are /will be ready for bidding in next
six months
• Staff recommends proceeding with planned capital
program at this time
• Review AVT impacts and ongoing capital program at
November 2008 Capital Budget and Plan Workshop
FY 2008/09 Capital Cash Flow Estimate
w/o Ad Valorem Tax
Capital Program Cash Flow
2008/09
Total Budgeted Revenue
w/o Ad Valorem Tax
$29,628,000
Total Budgeted Expenditures
$38,858,000
Negative Variance
- $9,230,000
Projected SCF Balance June 30, 2009
$38.6 M*
*Assumes beginning SCF Balance $47.8 M (7/1/2008)
32
November 2008 will be critical decision
point for a number of issues....
• Is Ad Valorem Tax lost... if so, how is Capital Program
impacted?
• To Expand or Contract Renovation Program?
— Expand if master plan reduces capacity expenditure needs?
— Expand if peer agencies are outpacing us?
— Contract if AVT is lost?
• To Construct or Not To Construct Mercury Removal?
— Construct if funds available and air emissions are a concern?
— Defer, particularly if AVT lost?
• To Add Projects to Reduce Green House Gas
Emissions?
— Will regulations be taking shape?
— Should projects be budgeted or wait and see?
• To increase Treatment Plant Renovation based on
Asset Mgmt Plan?
Stay tuned .............
Capital Improvement Budget Summary for
FY 2008/09
33
Estimated
Estimated
Estimated
Total
Program
FY 2008/09
Carry -over
Allocation
FY 2008/09
Program
from Prior
FY 2008/09
Proposed
Expenditures
Fiscal Year
Authorization
Treatment Plant
$12,680,000
$16,279,000
$10,660,000
$26,939,000
Collection System
$22,355,000
$13,688,000
$17,339,000
$31,027,000
General Improvements
$3,418,000
$783,000
$3,071,000
$3,854,000
Recycled Water
$405,000
$30,000
$399,000
$429,000
Total
o
$38,858,000
$30,780,000
$31,469,000
$62,249,000
2008109
33
Next Steps in CIB /CIP Process
• April 17, 2008 set Public Hearing for CIB /CIP
• May 15, 2008 hold Public Hearing and Approve
CIB /CIP
• June 5, 2008 Board Adopts all Budgets, including
CIB /CIP, officially Authorizing the FY 2008/09 CIB
• June 5, 2008 Board Approves Closeout Position
Paper for completed CIB projects
• Hold Board briefing on closed out projects for any
interested Board members after June 5, 2008
• August 2008, ask Board to Reauthorize FY 2008/09
CIB with actual carryover amounts (new this year)
Questions?
Staff is available to stay after meeting for any detailed
technical question.
34
*- 0 1 r - I I 1 0 ji 0 , , , -
•
Public Health and the Environment
I A
Alk
Public Health and the Environment
I A
Central Contra Costa Sanitary District
Capital Improvement Program
Executive Summary
Central Contra Costa Sanitary District
funds an extensive Capital Program
designed to preserve, maintain and
enhance the District's assets,
accommodate the community's needs,
and protect the environment.
Capital improvements /capital projects
are major construction, acquisition or
renovation activities which add value to
the District's fixed assets (buildings,
pipelines, facilities, equipment) or
significantly increase their useful life.
The District's Fiscal Year 2008 -09
Capital Improvement Budget details
expenditures of approximately $39
million for the planning, design and
construction of capital projects. By
adopting the Capital Improvement
Budget, the Board of Directors
authorizes staff to pursue this work.
In addition to the Capital Improvement
Budget for the upcoming year, the Board
approves a Ten -Year Capital Improve-
ment Plan that forecasts needed
expenditures for ten years into the future.
This plan focuses on renovation, expan-
sion and regulatory requirements. Its
estimated expenditures for the next ten
years are $340 million (in 2008 dollars),
an average of $34 million per year.
The Capital Improvement Budget and
Ten -Year Capital Improvement Plan also
include projected revenues and cash -
flow analyses to demonstrate how
planned expenditures will be funded. The
projections assume revenue potential
and make up deficits through a
combination of drawing on reserves and
raising the capital component of the
annual sewer service charge paid by
each new connection to the sewer
system.
Each planned project addresses one or
more of these District goals:
• Protect public health and the
environment
• Maintain existing assets
• Respond to regulatory and
community concerns
• Accommodate planned growth
This summary describes the major
projects for fiscal year 2008 -09, the
major projects included in the Ten -Year
Capital Improvement Plan, and the
revenue streams that will support the
planned expenditures.
FY 2008 -09 Capital Improvement Budget
The FY 2008 -09 Capital Improvement Budget shows expenditures of approximately $39
million ($38,858,000) for the planning, design and construction of capital projects
categorized into four programs:
• Treatment Plant
• Collection System
• General Improvements
• Recycled Water
Each of those programs is subdivided into subprograms.
Most of the money will be spent on renovation or preservation of capital assets, as
shown in the following table:
Capital Program/
Subprogram
Planned
Expenditure
For FY 2008 -09
Treatment Plant Program
$12.7 million 33%
Regulatory Compliance/Planning
$
2.2 million
One -Time Renovation
$
4.9 million
Recurring Renovation
$
4.8 million
Expansion/Capacity Improvements
$
0.3 million
Other Miscellaneous Projects
$
0.4 million
Collection System Program
$22.4 million 57%
Renovation
$
8.3 million
Regulatory Compliance/Planning Compliance/Planning
$
0.3 million
Expansion/Capacity Improvements
$12.5 million
Pumping Stations /Force Mains
$
1.2 million
General Improvements Program
$
3.4 million 9%
Vehicles and Equipment
$
0.9 million
Management Information Systems
$
0.8 million
CSO Facility Improvements
$
0.7 million
All Other
$
1.0 million
Recycled Water Program
$
0.4 million 1
Total
MMMOR
Wo _
ind
In FY 2008 -09, 75 percent of the budgeted $39 million will be for the following 18
large projects.
Treatment Plant
Plant Site Improvements: As in any
industrial facility, heavy use, time and
weather deteriorate pavement. This
project will restore and preserve areas of
paving throughout the plant site, add
new paving as appropriate, correct
drainage deficiencies, replace
deteriorated fences and gates, and
enhance visual appearance through
landscaping. In addition, handicap
accessibility will be improved, and a new
conduit for fiber optic communications
will be installed. ($1,500,000 FY 08 -09;
$2,500,000 estimated total project
cost)
Among other things, the Plant Site Improvements Project will remove the old railroad
tracks and repair paving throughout the site.
Aeration Air Renovations: The existing
aeration tanks were installed in the mid
1970s. Since then, numerous cracks and
air leaks have developed. This air loss, if
allowed to continue, could undermine the
structural integrity of the aeration tanks
and represents a significant energy cost.
The cracks will be repaired using a
technology (pressure grouting) that both
fills the voids beneath the tanks and fills
the cracks. A future phase may require
replacement of the air delivery system of
the secondary aeration system.
($1,000,000 FY 08 -09; $2,100,000
estimated total project cost)
Piping Renovations and Replacement,
Phase 4: Since the inception of the
treatment plant facilities in 1948,
numerous piping systems have been
installed that carry processed waste-
water, sludge, steam, air, and other
constituents. Over time, these pipes fail
due to corrosion and erosion. This multi-
phase program replaces piping that has
reached the end of its useful life. Phase
4 will focus on ash piping, furnace gas
piping, diesel piping, return activated
sludge piping, and chemical piping.
($1,800,000 FY 08 -09; $1,800,000
estimated total project cost)
Primary Structures Demolition: This
project will demolish the abandoned
primary sedimentation tanks constructed
in 1948 and 1957 and backfill the area. It
will also demolish the unused lime
storage silos, building, and associated
piping systems.
Pipes at risk of failure due to corrosion and
erosion will be replaced
Additional obsolete facilities may be
included based on further evaluations.
This work will increase safety around the
abandoned tanks and allow for future
expansion of related adjacent facilities.
($1,100,000 FY 08 -09; $1,400,000
estimated total project cost)
The abandoned primary sedimentation tanks will be demolished.
4
Treatment Plant Asset Management
Plan: Replacement value of the current
treatment plant facilities is conservatively
estimated at $600 million. This includes
all mechanical and electrical equipment,
piping systems, concrete structures and
buildings, access roads, etc. All of these
components have a finite useful life. The
purpose of the Asset Management Plan
is to develop a systematic approach to
identifying, prioritizing and funding
replacement projects. The first step
documents completed projects and
institutional knowledge within the various
processes of the treatment plant, and will
be continued. The second step, to be
initiated in FY 08/09, will assess the
conditions of treatment plant processes,
systems, equipment, and structures.
($1,000,000 FY 08 -09; $1,200,000
estimated total project cost)
Standby Power Facility Improve-
ments: This project will replace the
standby power units with generators that
meet new air quality regulations,
increase runtime to meet operational
requirements, and improve overall
reliability. The standby power generator
building will also be brought into
compliance with the latest Uniform
Building Code. ($1,200,000 FY 08 -09;
$6,800,000 estimated total project
cost)
Standby
power units
will be
replaced
Solids Handling Improvements: A
major recommendation of the 2005
Solids Handling Facilities Plan was to
upgrade the equipment for handling
biosolids (sludge) during emergencies
(furnace failure) or non - routine
operations (e.g., spikes in solids
productions) that exceed the furnace
capacity. This project will design and
construct a sludge truck loading facility
with a sludge cake hopper and odor
control facilities to store sludge
generated during overnight and weekend
hours when hauling to landfills is not
possible. Contracts with local landfills will
be executed for disposal of biosolids on
an intermittent basis. ($1,054,000 FY 08-
09; $6,500,000 total estimated project
cost)
Scrubber Water Mercury/Metals
Removal: This project will modify the
multiple - hearth furnace air pollution
control train to decrease emissions of
mercury, other heavy metals, and
cyanide. A pilot study is being performed
to determine the effectiveness of various
air pollution control methods.
($1,000,000 FY 08 -09; $20,300,000
estimated total project cost)
Collection System
TV Inspection Program: This is a large -
scale multi -year effort to inspect the
entire collection system using closed -
circuit TV cameras, digital imaging and
database software. A publicly bid
inspection contract using digital imaging
and database software is awarded each
year. The new contractor's data is being
integrated with existing inspection and
sewer information databases, which is
then used to identify and prioritize sewer
replacement and renovation needs.
Currently sewers in Danville /Diablo are
being televised with sewers in Alamo
and Moraga to follow. ($900,000 FY 08-
09; $5,600,000 estimated total project
cost)
Walnut Creek Sewer Renovation
Project, Phase 6: This ongoing project
(which may include up to 15 phases) will
replace or renovate deteriorating or
deficient sewers in Walnut Creek. Phase
6 will renovate approximately 10,000 feet
of deficient sewers at 10 sites using
open cut and various trenchless
technologies. Construction of this phase
is expected to start in June 2008 and be
finished by February 2009. ($1,800,000
FY 08 -09; $2,200,000 estimate total
project cost)
Lafayette Sewer Renovation Project,
Phase 5: This ongoing project will
replace or renovate deteriorating or
deficient sewers in Lafayette. Phase 5
will renovate approximately 11,000 feet
of sewers at 10 sites using open cut and
various trenchless technologies.
Construction of this phase is expected to
start in June 2008 and finish by February
2009. ($1,500,000 FY 08 -09; $1,700,000
estimated total project cost)
Open -cut digging (as shown above) and trenchless technologies will be used for construction
projects in Walnut Creek and Lafayette.
Martinez Sewer Renovation Project,
Phase 2: This ongoing project will install,
replace or renovate deteriorating or
deficient sewers in Martinez. Phase 2 will
renovate approximately 5,000 feet of
sewers using open cut and various
trenchless technologies. Construction of
this phase is expected to start in June
2008 and finish by January 2009.
($1,200,000 FY 08-09; $1,400,000
estimated total project cost)
South Orinda Sewer Renovation
Project, Phase 3: This ongoing project
will renovate deteriorating sewers in
South Orinda. Phase 3 will renovate
approximately 10,000 feet of sewers at
10 sites south of Highway 24 using
trenchless technologies. Construction of
this phase is expected to start in July
2008 and finish by February 2009.
($1,200,000 FY 08-09; $1,400,000
estimated total project cost)
A -Line Relief Interceptor, Phase 2A:
This project will increase capacity and
reduce the potential for wet - weather
overflows in the A -Line Relief
Interceptor. It entails building 3,000 feet
of 96 -inch pipe from Buchanan Fields
Golf Course to the intersection of
Meridian Park Boulevard and Galaxy
Way. An additional 1,300 feet of 48 -inch
through 72 -inch pipe will be installed
along Galaxy Way, then across Walnut
Creek to the City of Concord Pumping
Station. The project will also eliminate
the need for the pumping station. To
minimize construction impacts, 4,000
feet of pipe will be installed by tunneling.
Construction is expected to begin in
March 2008 and finish in January 2009.
($8,125,000 FY 08-09; $20,000,000
estimated total project cost)
Camino Pablo Trunk Sewer and Flush
Kleen Force Main Improvements: This
project will replace gravity sewers and
two pumping station force mains within
Camino Pablo and the Camino Pablo
frontage road, from Miner Road north to
the Flush Kleen pumping station, using
open -cut and pipebursting methods.
Construction and traffic control details
will be closely coordinated with the City
of Orinda. Construction is expected to
start in June 2008 and finish by
December 2008. ($1,850,000 FY 08 -09;
$2,200,000 estimated total project
cost)
Approximately 1,500 feet of trunk sewer
and two force mains in Camino Pablo will
be replaced
Alhambra Valley Assessment District
Program: This project will assist
Alhambra Valley property owners
currently using septic tanks by financing
the cost of extending and connecting to
the public sewer. It will also help to avoid
future use of septic systems and sewage
pumping systems in Alhambra Valley;
and facilitate direct and indirect
connections to the Alhambra Valley trunk
sewer so the District's expenditures
associated with the trunk sewer
extension can be reimbursed more
quickly. ($1,000,000 FY 08 -09;
$2,000,000 estimated total project
cost)
2008 -09 Development Sewerage: This
project will provide capitalization of
District force account labor and other
expenses for planning, designing, and
constructing developer - installed and
contributed main sewer facilities.
($1,180,000 estimated total project
cost)
General Improvements
Collection System Operations
Department Facility Improvements:
This project will design and construct a
new administration, crew and warehouse
building, and provide new paving and
landscaping at the Collection System
Operations facility in Walnut Creek. The
District will obtain permits from the City
of Walnut Creek and address any City
requirements prior to construction.
($700,000 FY 08-09; $14,100,000
estimated total project cost)
This illustration shows the south elevation of the new CSO facility that will be built at the
District's Walnut Creek property.
Ten -Year Capital Improvement Plan
The District develops a Ten -Year Capital Improvement Plan each year which provides
the information needed to formulate long -range policy regarding:
• Identifying, prioritizing, and scheduling capital projects for the ten -year period.
• Providing financial resources for completing those capital projects.
The plan covers FY 2008 -09 through FY 2017 -18 and includes total expenditures of
approximately $340 million (in 2008 dollars), or an average of $34 million per year, as
described in the following table:
Capital Pt9grarn Expenditure Category
Dollars
Percent
Renovation One time and recurring)
$180 million
53%
Expansion (Capacity increases /sewers for new
customers
$110 million
32%
Regulation Driven
$ 38 million
11%
Miscellaneous
$ 16 million
4%
Total 10 -Year Capital Program Expenditures
$340 million
100%
The plan is divided into the same four programs as the budget. While a large portion of
the plan is devoted to ongoing renovation, several projects address capacity and
regulatory issues. The following table lists total ten -year expenditures by program and
subprogram. A brief description of the major projects /programs not described under the
FY 2008 -09 Capital Improvement Budget section follows the table.
C►t ram/Subprogram
Planned 10 Year
Expenditure
Treatment Plant Program
$121.6 million
(36%)
Regulatory Compliance
$
31.9 million
One -Time Renovation
$
24.3 million
Recurring Renovation
$
36.2 million
Expansion
$
28.4 million
Other Miscellaneous Projects
$
0.9 million
Collection System Program
$1708.2 million
(53%)
Renovation
$
91.3 million
Regulatory Compliance/Planning Compliance/Planning
$
1.9 million
Expansion/Capacity Improvements
$
72.8 million
Pumping Stations /Force Mains
$
12.2 million
General Improvements Program
$ 35.2 million 10%
Vehicles and Equipment
$
9.9 million
Management Information Systems
$
5.8 million
CSO Facility Improvements
$13.1 million
All Other
$
6.4 million
Recycled Water Program
$
4.3 million 1
Major Treatment Plant Projects /Programs
Electric Blower Renovations: The
electric blower serves as a backup to the
plant's two steam powered turbine
blowers. Its capacity is adequate during
winter months, but not during summer
months, when the plant's demand for air
increases. This project will design and
install a new, higher capacity blower.
(Construction FY 12 -14; $3,825,000
estimated total project cost)
Centrifuge and Cake Pumps
Upgrades: This project will upgrade the
treatment plant's centrifuges and cake
pumps, which will have been in service
for more than 20 years by 2010. The
design life of rotating equipment is
generally around 20 years. While routine
rotation of the operational and stand -by
centrifuge helps increase the operating
lifespan, as the equipment continues to
age the operation and maintenance
requirements become extensive.
(Construction FY 12 -13; $4,150,000
estimated total project cost)
Primary Expansion: This project will
add two primary sedimentation tanks to
increase the plant's wet - weather
capacity to roughly 270 million gallons
per day (62.5 mgd dry weather capacity
with one tank out of service). The new
tanks will provide additional operational
flexibility, reduce the amount of raw
wastewater bypassed to holding basins
during heavy rain storms, and decrease
the potential for associated odor issues.
This project will also upgrade the existing
primary sedimentation tanks, pre -
aeration tanks and grit - handling system.
(Construction FY 16 -18; $26,210,000
estimated total project cost)
Recurring Renovation: Replacement
value of the current treatment plant
facilities is conservatively estimated at
$600 million. This includes all
mechanical and electrical equipment,
piping systems, concrete structures and
buildings as well as access roads, etc.
All of these components have a finite
useful life. In order to maintain the
facilities in top operational condition, the
Ten -Year Capital Improvement Plan sets
aside funds for recurring renovation
(Ten -year plan; $36,154,000)
10
Recurring
renovation
work is vital to
maintaining
the plant's
assets.
Major Collection System Projects /Programs
Sewer Renovation: In 2002, the District
initiated a long -term program to televise
all 1,447 miles of its gravity sewers. To
date the program has televised approxi-
mately 578 miles of main sewers. The
results indicate approximately 4.6
percent, or almost 29 miles of pipes, are
in poor condition. Extrapolating the data
to the entire collection system shows 72
miles of sewer mains in poor condition,
with a replacement cost of $123.5
million. The current ten -year plan targets
approximately 44 miles of pipe for
renovation /replacement. (Ten -year
plan; $91,284,000 estimated total
project cost — includes TV program,
large diameter pipe renovation and
cathodic protection)
Sewer Capacity: Periodically the
District updates the Collection System
Master Plan to identify capacity
deficiencies, which are prioritized and
scheduled for replacement in the Capital
Plan. Presently, the Collection System
Master Plan is being updated to reflect
recently approved land use and new flow
monitoring data. The current figures are
based on the 2000 Master Plan. The
Capital Plan will be updated to reflect the
new results when available. (Ten -year
plan; $61,000,000 estimated total
project cost)
Ongoing TV inspection of the collection system reveals problems like this broken pipe.
11
Potential Future Projects Not Included in Ten -Year Capital Improvement Plan
The Ten -Year Capital Improvement Plan budgets $38 million (11 percent of the planned
ten -year expenditures) for regulatory- driven projects. However, this does not tell the
entire story. There are a number of potential projects that may be required to meet
regulations that are under consideration but have not yet been enacted into law. The
following table shows these potential projects and the estimated probability (low, medium
or high) of their being necessary. If these expenditures become necessary, additional
revenues not currently identified in the ten -year plan will need to be generated, or other
needed projects will need to be deferred.
Description
Time
Estimated
Total "�
Estimated
Frame
cost
Probability
Treatment Plant: Hydraulic/ Process Capacity
Filter Plant Expansion - Provide facilities to
filter secondary effluent during dry and wet
$135 -150
weather to meet new regulations such as metals
3 -15 yrs
million
Medium
reduction or provide additional effluent for water
recycling.
Nutrient Removal — Provide facility for nutrient
10 -20
removal (nitrogen and phosphorus).
yrs
$50 million
Low
Nitrification — Provide facilities for nitrification
(convert ammonia to nitrate). This project is
5-10 yrs
$50 million
Medium
partially funded in the latter years of the Plan.
Treatment Plant: Solids Handling
Sludge Treatment Replacement - Implement
anaerobic digestion or thermal drying if future
3 -15 yrs
$30 -50 million
Low
regulations prohibit incineration.
Incinerator Emissions - The EPA is currently
considering stricter regulation of air emission
3 -10 yrs
$30 million
Medium
from sewage sludge incinerators.
Treatment Plant: Other Projects
Air Emissions Projects — Provide processes to
control air toxics and odors and construct tank
5 -10 yrs
$25 -30 million
Low
covers (primary and /or secondary processes to
capture air emissions ).
Greenhouse Gas Reduction — Construct
alternative energy projects to reduce or provide
5 yrs
$25 -50 million
High
offsetting credits for greenhouse gas emissions.
Collection System: Regulatory Response
Sewer System Management Plan Projects —
The SF Bay Regional Water Quality Control
Board and State Water Resources Control Board
1 -5 yrs
$5 - $10 million
Medium
require a Sewer Maintenance Management Plan.
per year
The requirements may necessitate an escalated
capital program to televise and renovate sewers.
12
Capital Revenue /Cash Flow /Sewer Construction Fund
Balance
The Capital Program is funded by a number of different fees and charges as described
below. Figures 1 & 2 depict the relative magnitude of these revenue sources from the
Capital Improvement Budget and Ten -Year Capital Improvement Plan perspectives.
Facility Capacity Fees: A facility capacity
fee is paid by each new connector to the
District's collection system. This fee is
recalculated each year and represents the
cost of buying into the existing assets of the
District. The revenue from these fees is
highly dependent on the housing market and
the rate of new connections.
Pumped Zone Fees: For new connections
located in an area where pumping is
necessary, an additional facility capacity fee
is charged to buy into the existing pumping
station assets of the District. The revenue
from the pumped zone fees is also highly
dependent on the housing market and the
rate of new connections.
Property Taxes: Historically, some
enterprise districts have levied a property tax
rate to cover part of their costs. In 1978,
when Proposition 13 reduced the taxation
rate on property, the State Legislature urged
enterprise special districts to shift to user fee
financing. In FY 1992 -93, the State of
California began diverting portions of the
property tax revenue. The District still
receives a significant amount of property
taxes which are allocated entirely to debt
service and the Capital Program. If those
taxes were to be permanently diverted, a
significant increase in other forms of
revenue, particularly the sewer service
charge, would be necessary.
Sewer Service Charges: The sewer
service charge is an annual charge placed
on the property tax rolls which funds
13
operation and maintenance costs as well as
a portion of the Capital Program. Each year
the capital revenue from all other sources is
estimated, and the additional revenue
needed to fund the planned expenditures is
generated by increasing the capital
component of the sewer service charge.
Reimbursements from Others: The
District receives reimbursements from others
for capital expenditures which benefit others.
For example, the City of Concord is served
by a contract which requires them to pay a
flow - proportional share of capital projects
which benefit Concord (such as projects to
improve wastewater treatment facilities and
large interceptors). The District also has
formed Assessment Districts to promote the
installation of sewers in un- sewered areas
and has set up loaned money from the
Sewer Construction Fund, along with
reimbursement accounts to return these
revenues, with interest, to that fund.
Interest: Interest is earned on the balance
of the Sewer Construction Fund, the money
held in reserve to fund future capital
projects. The interest earned is returned to
the fund.
Bond Proceeds: While the District
generally follows a pay -as- you -go
philosophy, sewer service charge rate
increases can be mitigated when large, one-
time projects are required by utilizing bond
funding to spread the payments over time.
Figure 1: FY 08 -09 Capital Budget Revenue
($1,000)
Facilities
Sewer Service Capacity & Pump
Charge Zone Fees
$8,510 (22.2 %) $7,375 (19.3%)
All Other
Interest ' $979 (2.6 %)
$1,500 (3.9 %)
Taxes Concord*
$8,636 (22.6)% $11,264 (29.4 %)
*Concord revenue unusually high due to reimbursements for Concord project
executed by the District.
Figure 2: Ten -Year Capital Plan Revenue
($1,000)
Bond Proceeds
$27,500 (7.3 %)
Facilities
Capacity & Pump
Zone Fees
$63,900 (17 %)
Sewer Service
Charge '
$85,000 (22.6 %)
Interest '
$19,600 (5.2 %)
Taxes
$120,700 (32)%
14
All Other
$15,445 (4.1%)
Concord
$44,604 (11.9 %)
As part of the Ten -Year Capital Improve-
ment Plan, estimates of expenditures
and revenues are made and a cash flow
projection developed to show the
interrelationship of revenues and the
Sewer Construction Fund balance.
Each year a policy decision is made by
the Board of Directors, based on staff
analysis and recommendations,
regarding the rate at -which the capital
component of the sewer service charge
should be set to fund the planned Capital
Program while maintaining an adequate
Sewer Construction Fund balance. The
Sewer Construction Fund balance is
needed for future capital projects. It also
acts as the bank to meet the District's
cash flow needs. To provide sufficient
funds for cash flow needs, a balance of
approximately $30 million is
recommended for the Sewer
Construction Fund.
The following table shows cash flow
projections for the next ten years,
including planned expenditures,
revenues needed to fund the
expenditures, and the utilization of the
Sewer Construction Fund. This table
includes an inflation factor of 3 percent
per year and therefore the expenditure
numbers will be slightly higher than
those included in the Ten -Year Capital
Improvement Plan section of this
document.
Sewer Construction Fund Cash Flow Projection
($1,000)
FY
Revenue
Ex
enditures
Net
Increase
Fund
Balance'
Treatment
Collection
General
Recycled
Subtotal
08
$38,264
Plant
$12,680
S stem
$22,355
Imp.
$3,418
Water
$405
$38,858
Decrease)
$594
(Projected)
$47,173
09
$33,299
$14,042
$17,884
$10,028
$417
$42,371
$9,072
$38,101
10
$36,812
$23,730
$18,410
$7,695
$430
$50,264
$13,452
$24,649
11
$32,987
$8,595
$18,906
$2,430
$443
$30,375
$2,612
$27,261
12
$33,600
$7,710
$19,471
$2,879
$445
$30,505
$3,095
$30,356
13
$34,413
$7,608
$20,055
$2,312
$458
$30,433
$3,980
$34,336
14
$35,825
$7,878
$20,657
$2,350
$472
$31,357
$4,468
$38,804
15
$35,812
$8,624
$21,277
$2,420
$537
$32,859
$2,953
$41,758
16
$37,871
$20,914
$21,915
$2,340
$547
$45,716
$7,845
$33,912
17
$57,637
$20,092
$22,573
$2,871
$770
$54,305
$3,332
$37,244
' Ending fund balance on June 30, 2008 is estimated at $47,767.
2 $27,500 from bond proceeds.
As shown, the Sewer Construction Fund
balance acts in concert with the various
revenue sources to fund the Ten -Year
Capital Improvement Plan. This cash
flow projection assumes the sewer
15
service charge capital component is
increased each year as necessary to
fund the planned expenditures and
maintain the Sewer Construction Fund
balance at appropriate levels.
Questions?
For additional information about the District's Capital Improvement Budget and Ten -Year
Plan, please contact Director of Engineering Ann Farrell at (925) 229 -7302 or Capital
Projects Division Manager Tad Pilecki at (925) 229 -7273.
' Central Contra Costa
Sanitary District
16
i
0
too=
>4
o+
0
0
C
U
N
H
C
0
E
a
0
m
d
0
C
O
L
a
m
V
0
m
O
O
N
00
0
O
N
SEEN
0
..
O E M
4W
4W
c
c
c
2
O
■ EEN
Co
■
CO
V
V
O
O
00
IA
'
O
V
O
O
N
.�
p
N
i
4W
a
_
O
a�
W
i
C
�
o
4W
V
a
LL
..
O E M
c
c
c
2
O
■ EEN
■ _
■
V
V
V
c/i
c�
cn
4w
4)
as
1
N
i
L
L
V
Go
O
01
O
m
C
V
fl.
ce
L
V
CL
.
'Q
L
a
z
0
a
CL
.
'a
L
Ch
CL
0
V
•
'a
L
cn
CL
L
V
Y
L
0
3
a�
z
.
'a
L
p1
CL
L
0
Z
m
0
L
Q
cn
m
L
O
L
cn
O.
V
O
0
L
�V
V
0 p
O
L
a
0o
0
O
O
N
c
c
m
E
r
a.+
CL
O
D
w
4w
A
r.�
O
L
4W
m
.
N
C
0
D1
C
►�
L
O
■ _
LL
3
z
z
L
V
V
V
a.+
O
0
ce
.
L
01
O
mm
O
._
4W
V
IMMEME
O
L
4w
O
V
4�
V
L
O
.
cm
O
V
m
01
m
m
E
m
C
3
V
O
D
W
4W
E
L
0
CL
Ll
rmwl
a�
m
s
a
m
L
cm
CL
m
mv
L
0
.
m
L
c1
■_
O
O
OC
O
L
O
m
m
mi
iqm�
0
1
00
O
N
L
ow
Y V �
O M �
ce Am
O1
o � _
L
CL CL
V =
a Lu
C
N �
� V
a a
ce
� L
L �
CL �
Lm
�a
0 �
Z
E
�+ O
= V
4� 4�
E
4�
w ow F•.
V =
E
4� O
� V
m
�
Z
! ce cn
O L =
C (D • _
O ?1
Q �
1-1 Q V i
J Vi Vi Q