Loading...
HomeMy WebLinkAbout11/29/2007 AGENDA BACKUPCentral Contra Costa Sanitary District November 20, 2007 TO: BOARD OF DIRECTORS VIA: JAMES M. KELLY, GENERAL MANAGER FROM: ANN E. FARRELL, DIRECTOR OF ENGINEERING SUBJECT: FY 2008 -09 INITIAL CAPITAL PLANNING WORKSHOP Attached is the memo reviewed with the Capital Projects Committee on November 14, 2007. After detailed discussion, the Committee made no changes to the memo. Since preparation of the memo, additional discussions have occurred with the Contra Costa Water District (CCWD) regarding the recycled water line extension to the Diamond /Meridian Park Boulevard area of Concord as part of the A -line Phase 2A project. CCWD has expressed no interest in contributing to this project to make it more financially feasible, and therefore staff has recommended and the Board has concurred, that this recycled line extension be deferred. In lieu of the recycle water project, Staff recommends that several needed projects that would have been done in future years be constructed in 2008 -09 to utilize the $2 million previously earmarked for the recycled water line extension. This would also help keep expenditures more in line with projections and revenues. These projects include the demolition of the abandoned primaries and additional pipeline renovation work. This change will change the relative expenditure amounts for the individual wastewater treatment, collection system and recycled water programs, but will not change the overall recommended expenditures for fiscal year 2008 -09, as presented in the attached memo. Central Contra Costa Sanitary District November 9, 2007 TO: BOARD CAPITAL PROJECTS COMMITTEE /BOARD OF DIRECTORS VIA: JAMES M. KELLY, GENERAL MANAGER n • l FROM: ANN E. FARRELL, DIRECTOR OF ENGINEERING fi� SUBJECT: FY 2008 -09 INITIAL CAPITAL PLANNING WORKSHOP INTRODUCTION In preparation for the Board Capital Projects Committee meeting on November 14, 2007 and the Capital Planning Workshop on November 29, 2007, 1 have summarized the material we will be covering in this memo. This information, with additional detail, will be reviewed in the committee meeting and workshop. We routinely hold a Capital Planning Workshop in the fall to set an estimated dollar amount for our capital program for the following ten years. We have found this approach to be very helpful in narrowing the scenarios and considerations for the January Financial Planning Workshop in which the Board this year will be asked to either confirm or modify the rate that was set last year for fiscal year 2008 -09. By fixing the level of capital expenditures, approximately 40 -45 percent of District overall spending, the possible budgeting scenarios become more limited and understandable. If the scenarios in January lead to some concerns about capital revenue and expenditures, adjustments can be made at that time and incorporated into the draft Capital Improvement Budget and Plan, which is brought to the Board in a second FY 2008 -09 Capital Planning Workshop in April. BASELINE RENEWAL AND REPLACEMENT PROGRAM As our District assets age, renovation and replacement is necessary to keep them functioning properly. For budgeting purposes, the amount of annual investment in renovation and replacement must be estimated. In January 2000, without a formal condition assessment and asset management plan, staff developed and recommended a baseline for investment in our capital facilities which assumed replacement of all assets every one hundred years. This equates to a reinvestment of 1 % of the estimated replacement value. At that time the total replacement value of our facilities was estimated at $2.1 billion and therefore the annual investment was set at $21 million. This amount has been increased for inflation at 3% per year. This is a modest increase as building costs have increased significantly more than 3% per year since January 2000. For example, the Engineering News Record construction cost index, a commonly used index for construction cost estimating, has increased approximately 3.8% per year over this same time period. This 3% annual increase brings the recommended reinvestment for renewal and replacement of existing assets to $27 million for the next fiscal year, year 2008 -09. While this approach continues to provide a reasonable benchmark for planned expenditures, a more detailed and systematic approach is needed. Staff has made significant progress in developing a detailed Asset Management Inventory and Plan for the Collection System. The value of the collection system is estimated to be approximately 65% of the total District asset value. Our District -wide collection system closed circuit TV inspection program has been underway for 5 years and 60 % of the District's sewers have been televised and the condition assessed. We estimate that it will take another 2 to 3 years to complete this work. As the work has progressed, the lines with the highest defect scores have been grouped into renovation projects which we construct each year. Staff is currently developing a reference document with maps to delineate the progress of the TV program and the renovation projects that are being developed as a result. This document will serve as our Collection System Asset Management Plan and will be updated as projects are completed and additional line segments are televised and the condition assessed. Our next initiative is to develop a more formalized approach to condition assessment and asset management in the treatment plant and at the pumping stations. We have begun an inventory of the treatment plant to document ages and conditions of major assets and renovation and replacement work done to date. We will then be developing an approach to condition assessment and asset management for our treatment plant assets looking to the future. We are currently developing scopes of work to hire technical assistance with systematic condition assessments of remaining work needed on treatment plant concrete structures, piping, coating and electrical systems. Significant renovation work has been done on our pumping stations over the last ten years and this is being documented in a pumping station inventory which will serve as the basis for determining what additional condition assessment work is needed on the pumping stations to develop an overall asset management plan. Finally, expenditures for significant projects to increase capacity or address changing regulations are in addition to the budget for renovation and replacement. For the last several years, budgeted expenditures for needed capacity and regulatory projects have been increased to take advantage of increased revenues from a number of sources, principle among them being capacity fees for new connections. Thus, expenditures have in some years significantly exceeded those estimated for baseline renewal and replacement. HISTORICAL PERSPECTIVE A series of two tables and two figures detailing expenditures and revenues for the last eight years are attached in the appendix and summarized as follows. Since fiscal year 1999 -00, District capital spending has ranged from a low of $19.8 million in 2002 -03 to a high of $39.7 million for fiscal year 2006 -07. This wide variation has been due in large part to the conscious effort to defer needed projects in fiscal years 2001 -02 through 2003 -04, when the permanent loss of ad valorem tax was feared. Subsequently, when there were large revenue increases due to the pace of new home construction in the Dougherty Valley and related capacity fees, expenditures were increased. On average, capital revenues have closely matched capital expenditures. Over the eight years shown on the figures, the average annual revenue was $25,100,000 and the average annual expenditures were $25,700,000, a 2% difference. Average budgeted revenue over the eight -year period was $23,700,000 compared to average actual revenue of $25,100;000. Actual revenue exceeded budgeted revenue for a number of years due to the unanticipated rapid build out of the Dougherty Valley and because ad valorem taxes were not lost to the extent budgeted. Thus, the Sewer Construction Fund Balance increased for the three year period from fiscal years 2002 -03 to 2004 -05. This increase has been offset in recent years by increased spending, leading to a net draw down of the Sewer Construction Fund Balance of approximately $5 million over the eight year period. The one capital revenue source controlled by the District is the capital component of the sewer service charge. This charge is adjusted each year as needed to match planned expenditures or to draw down the Sewer Construction Fund Balance or place additional revenue in the fund, depending on the goals and strategies of the Capital Budget and Plan in any given year. PROJECTED FISCAL YEAR 2007 -08 EXPENDITURES /REVENUES As noted under the historical data discussion, for several years revenues from Dougherty Valley connections were coming in to District coffers faster than expected, resulting in a significant increase in the Sewer Construction Fund balance. Over several prior years, there had been a conscious effort to defer needed projects due to the uncertainty associated with the ad valorem tax revenue. This also contributed to the increase in the fund balance. Therefore, two years ago staff recommended increasing capital program expenditures to levels greater than revenues for several years and funding needed deferred projects as well as some needed regulatory and capacity driven projects partially from the Sewer Construction Fund balance. These needed capacity and regulatory driven projects included the expansion of the ultraviolet disinfection facilities, a wet weather discharge point to increase the wet weather discharge capacity, a study and implementation of improvements to increase furnace capacity and reduce mercury in the effluent, the extension of the A -line from Buchanan Fields Golf Course to the intersection of Meridian Park Boulevard and Galaxy Way, and the expansion of the Primary Sedimentation Tanks. Since that time, the pace of building has slowed and the Dougherty Valley connections are expected to take place over a longer period of time. Revenue projections have been adjusted downward, but there is still a significant balance in the Sewer Construction Fund that will support running a deficit in the capital program in order to stay on course with the completion of needed projects. For the current fiscal year 2007 -08, both expenditures and revenues are now projected to be about 4% less than budgeted, resulting in no net change to the Sewer Construction Fund balance as budgeted at the end of the current fiscal year. 2007 -08 Capital Program Budgeted Activity Projected Activity Total expenditures $43.1 million $41.6 million Total revenue $40.5 million $39.0 million Variance -$2.6 million -$2.6 million SCF balance 7/1/08 $50.2 million $50.2 million As discussed in previous years, the Sewer Construction Fund balance acts as the bank to fund all District operations. This is necessary because SSC revenue and property tax revenue are collected by the County on the tax rolls twice per year. For the intervening six months, the District draws on these reserves to fund its operation and maintenance functions as well as the capital program. The cash flow needs for this self funding dictate that the Sewer Construction Fund balance be maintained in the neighborhood of $30 million. RECOMMENDED 2008 CAPITAL IMPROVEMENT PLAN FY 2008 -09 TO FY 2017 -18 Staff has developed a ten -year capital expenditure plan which budgets for a baseline of $27 million per year to fund renovation, renewal and replacement projects for a ten -year total of $270 million in June 2008 dollars. Staff has supplemented this baseline with approximately $45 million in needed capacity and regulatory expenditures between fiscal years 2008 -09 and 2010 -11 and an additional expenditure of approximately $22 million in the outlying years to fund the primary expansion. While the timing of the remainder of the Dougherty Valley capacity fee revenues is difficult to predict given the existing housing climate, it is expected these revenues will come in within the early part of the ten year plan and will offset a large portion of the supplementary $45 million in needed projects recommended for the near term. If the housing slump is prolonged, some adjustments in expenditures or funds from another source may be necessary to fund the supplementary projects. It is likely that large expenditures in outlying years, such as the $22 million primary expansion, may need to be bond financed unless another large development, such as the Concord Naval Weapons Station, is approved and begins generating significant capacity fee revenue. This year projects to meet known near term regulatory requirements are budgeted to the best of our ability. Our understanding of our potential new permit limits has improved over the last several months in numerous discussions with the Regional Water Quality Control Board (RWQCB). It appears less likely that a project to remove mercury from the incinerator air scrubber water will be required to allow compliance with effluent limits for mercury. However, staff is continuing to evaluate possible treatment options and has included a budget of $1 million in the treatment plant program expenditures for fiscal year 2008 -09 to complete pilot testing and preliminary planning and design. An additional $15 million has been budgeted over the subsequent three years to fund possible needed improvements to remove mercury. Should these expenditures for mercury control in outlying years not be needed, these funds can be allocated to other needed projects in a future capital plan. Projects for possible long -term regulatory requirements, such as nutrient removal, are not budgeted. There is more and more discussion at the Federal level about implementing nutrient standards for all dischargers. Currently the District does not remove nutrients and it would require an expensive retrofit to do so. Staff will be including a planning project in the 2008 -09 budget to examine possible long -term regulatory requirements, such as nutrient removal, and develop alternative compliance strategies and budgets. It is anticipated that some pilot work will be desirable to evaluate different technologies and compliance strategies. In conclusion, the District is in a very sound financial position with respect to its ten year capital plan, and should be able to fund needed baseline renewal and replacement as well as known needed capacity and regulatory projects minimum rate impacts. District staff will be working on two important planning initiatives in 2008 -09: one, to better document our condition assessment and asset management strategies for the collection system, treatment plant and pumping stations, and two, to examine long term regulatory trends and identify studies that should be done to develop compliance alternatives and budgets. RECOMMENDED FISCAL YEAR 2008 -09 CAPITAL IMPROVEMENT BUDGET The recommended fiscal year 2008 -09 Capital Improvement Budget includes $27 million for baseline renewal and replacement projects and an additional $11.2 million for needed capacity and regulatory projects for a total recommended expenditure of $38.2 million. The allocation of the recommended $38.2 million among the four programs is as follows: FY 2008 -09 Capital Improvement Budget Baseline Capacity /Regulatory Total Treatment Plant $7,500,000 $4,000,000 $11,500,000 Collection System $17,000,000 $4,300,000 $21,300,000 General Improvements $2,200,000 $800,000 $3,000,000 Recycled Water $300,000 $2,100,000 $2,400,000 Total $27,000,000 $11,200,000 $38,200,000 Staff will be working to develop the detailed budget document using the above preliminary figures as modified by the November 2007 and January 2008 Board Workshops. Many of the projects have already been defined. Others will evolve and emerge as we prepare the budget document over the next six months in anticipation of the second Board Capital Workshop in April 2008, when the detailed draft Capital Improvement Budget is reviewed with the Board. A review of the preliminary 2008 -09 Capital Improvement Budget for major projects and areas of emphasis follows. Treatment Plant Program Preliminary estimates of expenditures for the fiscal year 2008 -09 Treatment Plant Program can be grouped into three major categories: renovation, reliability and regulatory. The major projects are as follows: Category Project Annual Ex ense Renovation Piping Renovation $1,000,000 Plant Site Improvements $1,500,000 Aeration Air Renovation $1,000,000 Reliability Sludge Loading Facility $1,500,000 Standby Power Im rovements $1,200,000 Wet Weather Bypass $1,200,000 Regulatory Scrubber Water Mercury Pilot Testing/Prelim i na Design $1,000,000 All Other $3,100,000 Total $11,500,000 The projects listed under renovation have been identified and developed with input from plant operations staff. They address urgent needs. For example, the piping renovation project will begin the process of replacing ash piping which has been eroded down to paper thin walls due to the abrasive nature of the ash. The site improvements will replace failing paving and will incorporate the improvements needed to meet ADA requirements in the various parking areas. Going forward, staff will be developing a more formal asset management approach to developing renovation projects for the treatment plant, in addition to addressing urgent needs identified by plant operations staff. The aeration air renovation project is one that was discussed with the Board several years ago. The aeration tanks, due to the way they were originally designed and constructed, have developed leakage that has gotten progressively worse over the years. A similar facility in Australia solved this problem by filling in the air plenums at the bottom of the aeration tanks with concrete and adding a complete new diffused air system. The District could do the same thing for an estimated cost of $8 to $10 million. Staff has been investigating other options for several years in the hopes of avoiding this large expenditure. In the summer, when flows are lower and tanks can be taken out of service, pilot studies have been conducted on different methods for sealing the leaks in place and retaining the existing air plenum and diffuser design. Staff has identified at least two and possibly three systems that can effectively seal the leaks. These systems can be bid against each other and it is estimated that a complete fix will cost in the neighborhood of $1 - $2 million. This is a fraction of the cost of filling in the leaking plenums and adding a new aeration system. Staff will present some photos and details of this study at the workshop on November 29, 2007. The other large category of projects budgeted for 2008 -09 is reliability. There are three critical projects budgeted. The first has to do with the sludge handling system. Currently, if the operating incinerator or ash handling system goes down for any reason, the District has no reliable means of sludge disposal until the other incinerator can be brought on line or the ash handling problem corrected. Bringing the second incinerator on line takes weeks, and there is not enough storage for this period of time. There is an old and very rudimentary system available for dewatered sludge hauling, but it has no storage or odor control and is considered to be unreliable. The Sludge Loading project will construct a reliable sludge loading facility that can load trucks with dewatered sludge and hold enough sludge to get through a long weekend so that sludge can be taken to landfill if the incinerators cannot process sludge for any reason. Second, the standby power improvements will replace the two existing engine - generator sets, which have had significant reliability problems, with two new engine - generator sets. And third, the wet weather bypass project will provide a more effective means of overflowing to Walnut Creek if the capacity of the plant and the wet weather storage ponds are exceeded than the current limited capacity flow over the adjacent Conco property. All three of these projects have been discussed with the Board at previous workshops and meetings. Finally, the major regulatory project addresses controlling mercury in the plant effluent and potentially in the air emissions from the incinerator as well. District staff is conducting two different pilot studies and working with an expert in incineration to develop an innovative approach to control mercury in both the plant effluent and the incinerator emissions. Collection System Program The major 2008 -09 projects planned for the proposed $21,300,000 collection system program can be grouped into four categories, renovations to existing sewers, developer related services, the A -line phase 2A capacity project and the Alhambra Valley main line extensions, which are being funded by the District through an assessment district process. Estimated expenditures are shown as follows. Category Annual expense % Collection System Program Renovation program $7,500,000 35% Developer services $1,200,000 6% A -line Phase 2A $8,100,000 38% Alhambra Valley Main Lines $1,000,000 5% All others $3,500,000 16% Total $21,300,000 100% As you can see, the major drivers of the Collection System Program for 2008 -09 will be the renovation program and the A -line Phase 2A. The A -line project is a joint project with the City of Concord. Approximately 30% of the approximate $22 million project cost is for an intertie to the Concord pumping station, which will allow the abandonment of the station. This portion of the project will be funded 100% by the City of Concord. Of the remainder of the project, after the Concord flows enter the A -line, approximately 30% of the flows will be from Concord and therefore they will fund 30% of the remaining 70% of the project cost. Of the total $8,100,000 A -line Phase 2A cost to be expended in fiscal year 2008 -09, $7,000,000 is estimated to be reimbursed by Concord during fiscal year 2008 -09 because it is assumed that the majority of the work being constructed next fiscal year will be the Concord intertie. The Concord intertie costs will be reimbursed monthly due to the large impact on our cash flow. The typical Concord capital reimbursements occur once per year, at the close of the fiscal year. The ongoing renovation program will take us to South Orinda, Walnut Creek, Lafayette and Martinez in 2008 -09. The renovation projects continue to be challenging, with many backyard easements and difficult field conditions. Impacts to the community are sometimes difficult to mitigate. Staff is doing an excellent job implementing these difficult projects. We are beginning to see some positive impacts. Sewer system overflows are trending downward. Staff believes this is due both to improved cleaning and to the renewal of problem sewers through the renovation program. One concern we are just beginning to track and document is the increasing time and cost required to obtain and perfect easements and rights of entry needed for renovation projects on private property. These costs are now being tracked separately and listed as a line item when renovation construction projects are awarded. Initial data suggests that the cost can range from 2 to 4 percent of total project cost for perfection of property rights to as much as 17 percent for sites that require new easements. For the recent North Orinda Phase 2.1 project, which consisted of 3700 feet of pipe almost entirely in back yard easements, the right of way costs totaled approximately $432,000 or 17.3 percent of the $2.5 million total project cost. Staff will continue to monitor and control these costs as much as practical, but they must be recognized as the cost of doing business on private property. General Improvements Program General improvements in fiscal year 2008 -09 are proposed at a modest $3,000,000 and will include the traditional equipment budget, information technology budget and items associated with miscellaneous District facilities. In addition, expenditures will continue on the permitting, environmental review and design of the proposed new Collection System Operations Building. Due to the lengthy plan review process, construction of the new Collection Systems Operations Building is not budgeted until fiscal years 2009 -10 and 2010 -2011. Recycled Water Program The recycled water program may see a larger than usual expenditure in 2008 -09 associated with the A -line Phase 2A extension. As part of this project, a recycled water distribution line may be extended to serve 18 new customers in the Diamond Boulevard and Meridian Park Boulevard area of Concord. The estimated expenditures for this extension are $2,000,000, of which Concord will reimburse the District approximately 30% or $600,000. District staff is engaged in ongoing discussions with the Contra Costa Water District staff in an effort to make this project a reality. If the project is not constructed, the budgeted $2,000,000 will not be spent and will be available for other projects or will remain in the Sewer Construction Fund. Also in 2008 -09, staff will be updating previous master planning efforts for recycled water to identify any new opportunities and ensure that we are focusing our energy on the projects that recycle the greatest amount of water. Chief among these are industrial recycling projects, such as taking recycled waters to nearby existing refineries or to proposed new power plants. The potential for Concord Naval Weapons Station development to use recycled water also needs to be integrated into our recycled water master planning effort. SUMMARY The proposed 2008 Ten Year Capital Improvement Plan includes baseline renewal and replacement projects of $270 million ($27 million per year) as well as $45 million in capacity and regulatory projects funded directly by rates and a potential $22 million bond funded project in outlying years. A preliminary financial analysis indicates, with the spending of the accumulated balance in the Sewer Construction Fund to a minimum balance of $30 million and the use of bond funding for large projects in outlying years, the proposed Ten Year Capital Plan can be funded with a minimal impact on rates. Therefore, staff recommends incorporating the recommended preliminary budgetary figures for the 2008 -09 fiscal year Capital Improvement Budget and 2008 Capital Improvement Plan contained in this memo into the ten year planning document that will be considered at the January 2008 Financial Planning Workshop. APPENDIX Historical Perspective Capital Revenue Discussion CATEGORY 1999100 2000101 2001102 2002103 2003104 2004105 2005106 2006107 Total $54 $76 $46 $76 SEWER SERVICE CHARGE $3,100,000 $6,300,000 $8,400,000 budgeted $26.7 M $24.4 M $25.1 M $28.2 M $25.9 M $26.6 M $27.7 M $34.7 M expenditures CAPACITY FEES $4,400,000 $6,100,000 $7,600,000 $12,700,000 $10,400,000 $8,784,000 ALL OTHER Total actual expenditures $21.3 M $28 M $20.5 M $22.4 M $19.8 M $26.5 M $27.7 M $39.7 M Total actual revenue $21.6 M $18.9 M $17 M $23.5 M $28.2 M $30.0 M $24.8 M $36.6 M Variance + $.3 M - $9.1 M - $3.5 M + $1.1 M + $8.4 M + $3.5 M - $2.9 M - $3.1 M SCF Balance - June 30 $55.9 M $52.8 M Capital Revenue Discussion CATEGORY 2001102 2002103 2003104 2004105 2005106 2006107 SSC CAPITAL COMPONENT $20 $41 $54 $76 $46 $76 SEWER SERVICE CHARGE $3,100,000 $6,300,000 $8,400,000 $12,100,000 $7,400,000 $12,510,00 AD VALOREM TAX $6,400,000 $7,700,000 $7,900,000 $200,000 $1,100,000 $8,111,000 CAPACITY FEES $4,400,000 $6,100,000 $7,600,000 $12,700,000 $10,400,000 $8,784,000 ALL OTHER $3,100,000 $3,400,000 $4,300,000 $5,000,000 $5,900,000 $6,895,000 TOTAL ACTUAL CAPITAL REVENUE $17,000,000 $23,500,000 $28,200,000 $30,000,000 $24,800,000 $36,300,000 10 CCCSD Actual Capital Revenue vs. Actual Capital Expenditures $40,000,000 39.7 $35,000,000 __ - -- -- - 36.3 $30,000,000 -- - -- - Actual Expense $25,000,000 -- - - -- Actual $20,000,000 Revenue $15,000,000 - - -- $10,000,000 Average Actual Revenue $25.1 million Average Actual Expenditures $25.7 million $5,000,000 Difference= $5 million more expended than revenue over 8 year period. Sewer Construction Fund Balance drawn down 1999/00 2000/01 2001/02 2002/03 2003/04 2004/05 2005/06 2006/07 1-4W- Total Actual Capital Revenue t Total Actual Capital Expenditures CCCSD Actual capital Revenue vs. Budgeted Capital Revenue $40,000,000 38.8 $35,000,000 -- -- __ 16.3 $30,000,000 - - $25,000,000 - -- Revenue $20,000,000 - -- -- Actual $15,000,000 - $10,000,000 - - -- Average Actual Revenue $25.1 million - - -- Average Budgeted Revenue $23.7 million $5,000,000 Difference: $11 million more revenue than budgeted -- - over 8 year period. 1999/00 2000/01 2001/02 2002/03 2003/04 2004/05 2005/06 2006/07 Total Actual Capital Revenue -* -Total Budgeted Capital Revenue 11 2008/09 Capital Improvements Program Board Workshop November 29, 2007 2008 -09 Capital Improvements Program Workshop Agenda • Strategic Areas of Emphasis Drive Projects — Establish recommended expenditure levels for 2008 -09 — Review renovation/ reliability/ capacity/ regulatory areas of emphasis — Review programs and selected 2008 -09 projects • Collection System Program • Treatment Plant Program • Recycled Water Program • General Improvements Program • CIB /10 Yr CIP Must Respond to Changes in Need and Revenue — Review recommended expenditure levels for 2008 -09 — Establish projected revenue levels for 2008 -09 and cash flow — Evaluate recommended 10 -year expenditures and revenue projections and ability to fund needed projects 1 FY 2008 -09 Expenditure Recnmmpnclatinnc FY 2008 -09 Capital Renovation/ Reliability Capacity/ Total Improvement Budget Baseline Regulatory Treatment Plant $7.5 M $5.1 M $12.6 M Collection System $17 M $5.3 M $22.3 M General Improvements $2.2 M $0.8 M $3 M Recycled Water $0.3 M $0.0 M $.3 M TOTAL EXPENDITURES $27 M $11.2 M $38.2 M 2 FY 2008 -09 Treatment Plant Program Highlights Category Project Annual Expense % Program Renovation Piping Renovation $1.8 M 14% Plant Site Improvements $1.5 M 12% Aeration Air Renovation * $1 M 8% Reliability Sludge Truck Loading Facility * $1.5 M 12% Standby Power Improvements $1.2 M 10% Capacity Abandoned Primary Structures & Lime Storage Silos Demolition $1.1 M 9% Regulatory Scrubber Water Mercury Pilot Testing/ Preliminary Design $1 M 8% All Other Protective Coatings, DAF Polymer Improvements, Primary Expansion Design, Plant Equipment, Wet Weather Bypass $3.5 M 27% Total $12.6 M 100% Aeration Air Renovation Overview of A/N Tanks y}Y} T �yd �M� q YAK 3 Aeration Air Renovation 24" Air Supply and Air Plenum Boxes Aeration Air Renovation Air is Leaking from Cracks in Plenum Aeration Air Header Dilluters c�'_� � Comer Air Plenum Box — F- D. i . in Concrete Aeration Air Renovation Air Leakage from Plenums is Causing Serious Problems • Increasing aeration air loss is taxing capacity of steam turbines and electric blower • Air Leakage into subgrade and migrating to surface around structures is blowing out soil fines. • Loss of soil fines is resulting in settlement and potential loss of stability of structures. 5 Aeration Air Renovation Summer 2007 Repair Demonstration Projects • Three contractors tested innovative repair techniques • One used an expanding grout injection technique to seal cracks • Two applied coatings under positive air pressure to counteract under slab air pressure Aeration Air Renovation Air Plenum Box Floor Slab Aeration Air Renovation Air Plenum Box Floor Slab Repaired by Grout Injection Show Video Clip Aeration Air Renovation Potential Repair Methods • Repair Air Plenum Cracks Using one of Three Approved Technologies. (Estimated 10 Year Life) — Approx. Cost $1 M - $2 M • Pour New Floor and Install New Fine Bubble Diffuser System (Estimated 50 Year Life) — Approx. Cost $8 M - $10 M Sludge Truck Loading Facility Incinerator down time could be weeks... where will the sludge go ? ? ?? s ._... .w."ruft AND ...,.... ..�,,.m.. .a..,. . . M,,,IC sLow amaeft s Existing Sludge Loading Facility Sludge Truck Loading Facility Landfill Availability Drives Need for Sludge Storage • Avg Production: 20 truck loads /day • Peak Production: 30 truck loads /day • Land Fill Availability: 8 - 11 hrs /day /No Sundays and Holidays SOLUTION • Storage Hopper: 400 cy to hold cake generated overnight • Additional Liquid Storage to hold Sludge on Sundays or Holidays Sludge Truck Loading Facility Needed Project Components • Cake Hopper for Overnight Storage • Retrofit of Existing Tank for Liquid Sludge Storage • Enclosed Structure with Odor Control Facilities for Loading • Operator Observation Platform /Control Station • Wash Down Facilities 10 Location of New Sludge Truck Loading Facility n �J: 000 � Sludge Truck Loading Facility Estimated Costs are Significant but Necessary for Reliable Sludge Disposal - Construction - $4,000,000 - Design /CM - $1,000,000 - Total Project - $5,000,000 11 Demolition of Abandoned Primary Structures makes room for future Primaries 12 Treatment Plant Program Innovations • Developed innovative approach to sealing leaks in aeration basins • Pilot testing processes for mercury removal from incinerator air emissions and scrubber water • Completing state of the art upgrade to plant control system and seem -less switchover • Conducting Green House Gas inventory and developing plan for reducing carbon footprint • Beginning project to investigate innovative ways to comply with future regulations e.g.) nutrient removal • Five papers accepted for 2008 technical conferences 13 FY 2008 -09 Collection System Program Highlights Category Projects Annual Expense % Program Renovation & TV Program* Walnut Creek VI, Lafayette V, South Orinda III, Martinez II = 25,900 ft. $8.5 M 38% Pumping Stations & Force Mains Renovation/ Reliability Flush Kleen FM & small stations $1.1 M 5% Capacity Developer Services $1.2 M 5% A -Line Phase 2A $8.1 M 36% Camino Pablo Trunk* $1.3 M 6% Alhambra Valley Mains $1 M 5% All others $1.1 M 5% Total $22.3 M 100% Camino Pablo Trunk Sewer Improvement 50% in Frontage Road from Flush Kleen Pumping Station to short of Miner Road 14 Camino Pablo Trunk Sewer Improvement in Camino Pablo from Miner Road to Orinda Way Note: Miner Road Trunk Sewer Improvements have been deferred for one fiscal year. Sewer Renovation T.V. Program • 1447 miles of public gravity lines • 1275 miles of 6, 8 & 10 inch lines for potential renovation • Program to televise all lines started in 2002 • TV'd 900 miles to date (- 60 %) • Complete initial TV program in 2 to 3 years 15 4 ti 4 o COO 0 m a i ak 9 ®t Geogmphl oda 6degrm,w BxB -,WW, LMk- BeiCxrnnlew�..en!I dY111G � aooda 1 ❑= 2X6 0-H., ..... ❑o LI0070D50 -0. ly i ❑= Bdread M— 1 Elgreel S-.Dl H= Semi MAR DebiW - . -.:. .. - -1 - - ...1 •' 'r _ ..: •. ..1 E C.9.d Rdocnm Syd Q= Mode Ju 8m 1 1 4 �^ PeWfien 1 !0 Ted Sfalera Seen FeeNe[ ; 12 No NAe Mk Bc� I 1 1 ❑= Clcak Go[mq[ 1 ..... .. .......� 1 _. . DnbCgrroeEOm 1 1 1 Segment ID: 1793 M-ID: 7501 R10 7981 M9 £= iunryaletim Fedues :..1... SfeatV w RQS] 67 c F— ❑ Rabed, _ 1 B = Maprfloeh end Fn 1 E7 H1dvapN Fea Geabgr FeeWn %.^ Fed Tlem M Eadh,,*k Fal Z, 1 .. . - . -..... 1 ... 1 ..... .... I... 1 @ iopopepF,Fealue[ Gnd Pend Featue[ ❑� nwe[u Pecs B., c Gies 1------- i------- �_._____ �@ MAD Gads 1 ..- I -.:.. .. 1 ... .. -...I ....... ....... ®c S—Mao Gnd I r. -... ... ---1 ] a Nh.Rdo Gnd W.c Shaded R.W 750 7WIM9 16 Sample Defect Scores Score Description 75 break- inrunnecri -with grease, NCI 110 debris grease light NC2 110 encrastelion light #C2 110 scale/mineral deposits light OC2 115 gasket exposed 120 Infiltration Dripping at joint AC1 130 sceldminerel deposits at joint #C2 light 130 Corrosion light 130 encrustation at joint, NC2 light I30 roots light 150 separatedjoint slight 150 mortar missing light PC2 150 Infiltration Reaming NC 150 offsetjoint, slight 160 too en- ection with roots light, #Cl 160 serviee wnnection with grease, WCI 160 break- inconnection with roots light, WCI 160 wn- U- defective, kCI a • , a MMM Hism 17 Sewer Renovation T.V. Proqram Results to Date Extrapolation of T.V. Results (Miles of 6, 8 & 10 inch Pipe Scoring 7,000 or Greater) 1275 miles X (4.6% > 7000 score) = 59 miles 1275 miles X (2% obstructed) X (50% needing renovation) = 13 miles Total 6, 8 and 10 inch pipe needing renovation = 72 miles 18 SCORE (High score is poor condition) PIPE SIZE 1 -5,000 5,000- 7,000 7,000- 10,1000 >10,000 6" 136 miles 14 miles 12 miles 12 miles 8" 418 miles 5 miles 2.5 miles 2.0 miles 10" 25 miles 1 miles 0.2 miles 0.1 miles TOTAL MILES TV ID 578 miles 20 miles 14.7 miles 14.1 miles % 92.2% 3.2% 2.4% 2.2% Extrapolation of T.V. Results (Miles of 6, 8 & 10 inch Pipe Scoring 7,000 or Greater) 1275 miles X (4.6% > 7000 score) = 59 miles 1275 miles X (2% obstructed) X (50% needing renovation) = 13 miles Total 6, 8 and 10 inch pipe needing renovation = 72 miles 18 10 Year Proposed Sewer Renovation Program FISCAL YEAR FOOTAGE RENOVATED IN MILES TOTAL PROJECT COST (MILLIONS)" 2007/08 3.8 $6.6 2008/09 4.9 $7.4 2009/10 4.9 $8.4 2010/11 3.9 $6.7 2011/12 3.3 $5.7 2012/13 4.8 $8.3 2013/14 5.1 $8.8 2014/15 4.7 $8.1 2015/16 3.8 $6.5 2016/17 4.9 $8.5 TOTAL 44.1 $75.0 * Estimated at $325 per foot Comparison of Current 10 -Year Sewer Renovation Program vs. Extrapolated Needs 19 RENOVATION PROJECTED PROGRAM TOTAL COST Current 10 -Year 44.1 miles $75 Million Program Extrapolated 72.0 miles $123.5 Million Needs Difference 27.9 miles $48.5 Million 19 Comparison of Current 10 -Year Sewer Renovation Program vs. Projected Needs • At current production rates it would take 16.5 years to renovate all pipes with a rating greater than 7,000 • At current production rates it would take an additional 9.5 years to renovate all pipes with a rating of 5,000 to 7,000 • Total of 26 years to renovate all 6, 8 and 10 inch pipes with rating greater than 5,000 at current production rates How to maximize dollars for sewer renovation ?? • Finish TV Program /Assessment to validate extrapolation figures • Complete Collection System Master Plan to identify remaining capacity issues and adjust Capital Plan • Look at right of way /design /construction process improvements to reduce project costs • Next budget cycle, adjust funding, if possible, to maximize dollars for Renovation Program 20 Collection System Program Innovations • Leaders in use of trenchless technology — Guided Horizontal Drilling — Directional Drilling — Microtunneling — Pipe bursting, CIPP, Slip lining, Rib Lok, Reaming • Developed state of the art geographical data integration platform for collection system • Developed TV program linked with renovation program and integrated with CSO • Using in -house right of way, survey, design and construction management to minimize cost of renovation project delivery • Three papers accepted 2008 technical FY 2008 -09 & Future General Improvements Program Highlights • Maintain basic programs — Equipment Budget — Information Technology Plan — HOB /HHW /POD Miscellaneous Building Improvements • Fund future building needs — Collection System Operations Building and Improvements — Others as needed but none currently budgeted 21 FY 2008 -09 & Future Recycled Water Program Highlights • Maintain basic landscape program and publicize success — Continue to add cost - effective connections to existing backbone — Continue to make needed capital improvements to existing system • Develop strategic approach to maximize year round recycling for industrial /other purposes — Consider water transfers — Consider legislation re: duplication of services — Hire expertise to facilitate thinking "out of the box" FY 2008 -09 Expenditure Rpcnmmpnrlatinnc FY 2008 -09 Capital Renovation/ Reliability Capacity/ Total Improvement Budget Baseline Regulatory Treatment Plant $7.5 M $5.1 M $12.6 M Collection System $17 M $5.3 M $22.3 M General Improvements $2.2 M $0.8 M $3 M Recycled Water $0.3 M $0.0 M $.3 M TOTAL EXPENDITURES $27 M $11.2 M 1 $38.2 M 22 FY 2008 -09 Preliminary Estimate Budqeted Revenue Revenue Source Budgeted Amount Facility Capacity Fees $6.2 M Pumped Zone Fees $1.1 M Interest $2.5 M Ad Valorem Taxes $8.4 M City of Concord $11.2 M Sewer Service Charges (Preliminary $52 /RUE) $8.7 M Other Fees & Charges $1.7 M Total Revenue 1 $39.8 M FY 2008 -09 Preliminary Capital Cash Flow Estimate Capital Program Cash 2008/09 Flow Total Budgeted Revenue $39.8 M Total Budgeted $38.2 M Expenditures Variance * + $1.6 M Projected SCF Balance $51.8 M June 30, 2009 " Positive due to revenue from Concord reimbursement 23 SCF Balance Baseline Determined from Projected 2007 -08 Capital Program Activity 2007 -08 Capital Program Budgeted Activity Projected Activity Treatment Plant $12.3 M $10.9 M Collection System $26.5 M $26.7 M General Improvements $3.2 M $E6M Recycled Water $1.1 M $ Total Expenditures $43.1 M $41.6 M Total Revenue $40.5 M $39.0 M Variance -$2.6 M -$2.6 M SCF Balance Beginning FY 2008 -09 $50.2 M $50.2 M Preliminary Ten Year Projected Revenue /Expense and Impact on Sewer Construction Fund Balance Fiscal Year 08 -09 09 -10 10 -11 11 -12 12 -13 13 -14 14-15 15.16 16 -17 17 -18 SSC ($): 0 &M (Prelim) 259 269 288 300 312 324 338 350 370 388 Capital (Prelim) 52 54 47 47 48 49 48 49 42 37 Total SSC (Prelim) 311 323 335 347 360 373 386 399 412 425 SCC Inc. (Prelim) 11 12 12 12 13 13 13 13 13 13 Capital ($M): Total Revenue 39.8 34.5 36.4 31.9 32.5 33.6 35.3 35.8 31.9 39.2 Debt for Primaries 25.0 Total Expenditures 38.2 41.9 49.7 30.0 29.6 30.0 31.1 32.7 45.0 52.9 Mercury Rem $15M x x x CSO Bldg $13M x x x Variance ($M) 1.6 -7.4 -13.3 1.9 2.9 3.5 4.2 3.0 11.9 -13.7 Projected SCF Balance ($M)* 51.8 44.3 31.0 32.9 35.7 39.2 43.4 46.5 58.4 44.7 *($50.2 M July 1, 2008) 24 Projected Sewer Construction Fund Balance Fiscal Year 08.09 09.10 10.11 11.12 12.13 1 13.14 14.15 15.16 16.17 17.18 Expenditures ($M): Treatment Plant 12.6 13.9 23.7 8.6 7.5 7.6 7.9 8.6 20.9 28.1 Mercury Removal $15 M x x x Primary Sedmntn $25 M x x x Coll. System 22.3 17.9 18.3 18.9 19.5 20.1 20.7 21.3 21.9 22.6 Gen'Ilmprvmts 3.0 9.7 7.3 2.1 2.3 1.9 2.1 2.3 1.6 1.7 CSOD Impmnts $13M x x x Recycled Water 0.4 1 0.4 0.4 0.4 0.4 0.4 0.4 0.5 0.5 0.5 Capital ($M): Total Capital Revenues 39.8 34.5 36.4 31.9 32.5 33.6 35.3 35.8 31.9* 39.2 Debt Issuance 25.0 Total Capital Expenditures 38.2 41.9 49.7 30.0 29.6 30.0 31.1 32.7 45.0 52.9 Variance ($M) 1.6 (7.4) (13.3) 1.9 2.9 3.5 4.2 3.0 11.9 (13.7) Projected SCF Balance ($M) 51.8 44.3 31.0 32.9 35.7 39.2 43.4 46.5 58.4 44.7 ($50.2 M July 1, 2008) o ss 5O ao 35 30 - CF Balance Board Role in Capital Program is Ongoing • Set Initial Capital Funding Levels in November • Authorize Program Budgets in April - June • Authorize Supplemental Program Funds if needed • Award Construction Projects > $15,000 • Authorize Construction Change Orders >$50,000 • Authorize Consultant Contracts > $50,000 • Authorize Revisions to Consultant Contracts > 15% 25 What do we need from the Board today? • Concurrence that proposed preliminary expenditure figures for FY 2008 -09 and the subsequent 9 years are acceptable for inclusion in financial planning documents to be reviewed by Board in January 2008 • Concurrence that relative emphasis and allocation of expenditures between the four programs is acceptable for financial planning and development of the detailed FY 2008 -09 Capital Improvement Budget and Ten -Year Capital Plan Board Input / Questions? Staff is available to stay after meeting for any detailed technical questions. 26