HomeMy WebLinkAbout12/14/2006 AGENDA BACKUPCentral Contra Costa Sanitary District
' BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: December 14, 2006 No. • 3.a. CONSENT CALENDAR
Type of Action: AUTHORIZE SUBSTITUTION
subject: AUTHORIZE THE SUBSTITUTION OF B &B PAVING AND GRADING, INC.,
THE LISTED SUBCONTRACTOR, WITH FREMONT PAVING, FOR THE GRADING
AND PAVING WORK ON THE CSOD LEASE AREA AND SITE IMPROVEMENT
PROJECT, DISTRICT PROJECT 8215
Submitted By: Initiating Dept /Div.:
Paul Seitz, Associate Engineer Engineering / Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
P. Seitz A. Rozul <i A. Farrell ames M. Kelly,
general Manager
ISSUE: William P. Young Construction, Inc., general contractor, has requested
substitution of a subcontractor listed on its bid and contract for the Collection System
Operations Department (CSOD) Lease Area and Site Improvement Project, District
Project 8215. Board of Directors' authorization is required for the substitution.
RECOMMENDATION: Authorize substitution of the grading and paving subcontractor
on the CSOD Lease Area and Site Improvement Project, DP 8215.
FINANCIAL IMPACTS: The proposed substitution will not result in any additional cost
to the District.
ALTERNATIVES /CONSIDERATIONS: William P. Young Construction, Inc. has
informed the District that its listed subcontractor has failed to perform its subcontract
work and is in breach of the Subcontractor Agreement. Under California Public
Contract Code, Section 4107, substitution of a listed subcontractor is permitted when
the subcontractor fails to perform its subcontract. The awarding authority must consent
to the subcontractor substitution to effect the change.
BACKGROUND: William P. Young Construction, Inc. listed B &B Grading and Paving,
Inc. as their subcontractor for the grading and paving work on its bid proposal to the
District for the CSOD Lease Area and Site Improvement Project, DP 8215.
Incorporated into B &B Grading and Paving, Inc.'s Subcontract Agreement is a clause
that requires B &B Grading and Paving, Inc. to abide by William P. Young Construction,
Inc.'s Collective Bargaining Agreement with the Operating Engineers Local 3. B &B
Grading and Paving, Inc. does not want to sign a Project Agreement with Local 3 and,
therefore, will not be able to fulfill the requirements of the Collective Bargaining
Agreement clause contained in their Subcontract Agreement. The value of B &B
Grading and Paving, Inc.'s work was $111,000 or 13.3 percent of the contract value of
NAPESUP \Cbradley \Position Papers \2006 \December\Substitution of B &B PP.doc Page 1 of 2
POSITION PAPER
Board Meeting Date: December 14, 2006
Subject AUTHORIZE THE SUBSTITUTION OF B &B PAVING AND GRADING, INC.,
THE LISTED SUBCONTRACTOR, WITH FREMONT PAVING, FOR THE GRADING
AND PAVING WORK ON THE CSOD LEASE AREA AND SITE IMPROVEMENT
PROJECT, DISTRICT PROJECT 8215
$832,900. Under these circumstances, William P. Young Construction, Inc. now seeks
Board approval to contract with Fremont Paving to supply the necessary equipment,
materials, and labor to complete the grading and paving work. Under California Public
Contract Code, Section 4107, substitution of a listed subcontractor is permitted only in
certain situations, including situations where the subcontractor has failed to perform its
subcontract. District staff notified B &B Grading and Paving, Inc. by certified mail, on
December 6, 2006, of the request for subcontractor substitution by William P. Young
Construction, Inc., and has advised them of the requirement to notify the District in
writing within five (5) working days of any objection to this proposed action. Based on
conversations and written documentation with B &B Grading and Paving, Inc., no written
objection is anticipated. CCCSD Legal Counsel has reviewed this issue and concurs
with District staff.
RECOMMENDED BOARD ACTION: Authorize the substitution of the listed
subcontractor, B &B Grading and Paving, Inc., with a different subcontractor, Fremont
Paving, for the grading and paving work at the CSOD Lease Area and Site
Improvement Project, District Project 8215.
N:\PESUP\Cbradley \Position Papers\2006 \December \Substitution of B &B PP.doc Page 2 of 2
Central Contra Costa Sanitary District
' BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: December 14, 2006 No.: 3.b. CONSENT CALENDAR
Type of Action: Human Resources
Subject: AUTHORIZE EXTENSION OF MEDICAL LEAVE OF ABSENCE
WITHOUT PAY FOR HARRY WYLES, BUILDINGS AND
GROUNDS SUPERVISOR, THROUGH FEBRUARY 1, 2007
Submitted By: Douglas J. Craig, Initiating Dept /Div.: Plant Operations
Director of Operations
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
4 Of, tom— q!Q �---
OF Craig C. Freitas
mes M. Kelly,
eneral Manager
ISSUE: Board of Directors' authorization is required for a medical leave of absence
without pay in excess of 30 days.
RECOMMENDATION: Authorize medical leave of absence without pay for Harry
Wyles, Buildings and Grounds Supervisor.
FINANCIAL IMPACTS: Minimal
ALTERNATIVES /CONSIDERATIONS: Deny medical leave of absence without pay.
BACKGROUND: Harry Wyles, Buildings and Grounds Supervisor, has been off of
work since June 8, 2006, due to a medical condition. Mr. Wyles applied for, was
granted, and used 12 weeks of Family Medical Leave. We request authorization to
extend Mr. Wyles' leave without pay through February 1, 2007. Mr. Wyles' status will
be reviewed at that time, and further Board action will be requested if appropriate.
RECOMMENDED BOARD ACTION: Authorize medical leave of absence without pay
for Harry Wyles, Buildings and Grounds Supervisor, through February 1, 2007.
N: \POSUP \Correspondence \Position Papers\2006 \Wyles Leave of Absence.doc
BOARD MEETING
Thursday
December 14, 2006
2:00 p.m.
5. Announcements:
a) Bypass lines installed at storm damage site at 42 Haciendas in Orinda.
At the July 6 Board meeting, staff reported on the status of 13 storm damage
sites. Since the meeting, six sites have been repaired or are in the process of
being repaired. Four sites have been stabilized for the winter. Staff feels that
two sites are homeowner association responsibilities and pose minimal risk to
District lines at this time.
The remaining site, 42 Haciendas in north Orinda, has not been fixed or
stabilized because state Fish and Game restrictions prevent the District from
working in the creek to stabilize the site until next spring. The 12 -inch diameter
trunk sewer crossing the creek at this site serves 130 homes. The creek bank
that supports the creek crossing was washed away during last winter's storms.
To minimize the potential for overflows into the creek, three short bypass
sewer lines have been constructed to redirect flow from 115 of the 130 homes
to parallel sewers and away from the creek crossing. K.J. Woods, the
contractor for the North Orinda Sewer Renovations Phase 2 Project,
completed the installation of the bypass lines this week as a change order to
the North Orinda project. The District can pump flow from the remaining 15
homes to a nearby sewer if the creek crossing appears to be near failure.
Bypass equipment is staged nearby so that a bypass could quickly be put in
place. The crossing will be repaired next summer. The cost of the change
order to install the temporary bypass lines was within staff authority levels.
This information is provided for Board information only, no Board action is
required.
b) Regional Water Quality Control Board inspection of treatment plant on
November 30, 2006.
On November 30, 2006, the Regional Water Quality Control Board conducted
an inspection of the treatment plant. The inspector, Matt Oxsalida, is under
contract with the EPA to provide inspections for the San Francisco Regional
Board. The inspection included a treatment plant tour and a review of
laboratory records. Mr. Oxsalida was at the plant for about 2'/2 hours and prior
to departure, he commented that the plant appears to be well operated and
maintained. He had one minor comment on a laboratory certification analysis
which the District was in the process of repeating. He reiterated that it was a
very minor issue and the District has responded appropriately.
December 14, 2006 Announcements
Page 2
c) Staff attendance at Underground Construction Technology Conference in
Houston. Texas.
Associate Engineer Craig Mizutani and Assistant Engineer Clint Shima are
planning to attend the twelfth annual Underground Construction Technology
Conference and Exhibition in Houston Texas on January 30 through February
1, 2007. This conference is of significant value to the District and has served
as a major training opportunity in underground construction technology. Funds
were included in the 2006 -07 Training and Conference budget to cover the
costs of attendance.
d) Staff attendance at World of Concrete Conference in Las Vegas, Nevada.
Assistant Engineer Nathan Hodges is planning to attend the World of Concrete
Conference in Las Vegas, Nevada on January 21 through 26, 2007. Funds
were included in the 2006 -07 Training and Conference budget to cover the
costs of attendance.
Staff Recommendation: Hear the announcements.