2006 -07 Capital Improvements Program Workshop
Agenda
• Financial /Human Resources Deliver Projects
— Review historical program activity and accomplishments
— Discuss need for additional authorization for 2005 -06 program
— Revisit revenue projections and ability to fund needed projects
• Strategic Goals Drive Projects
— Review progress on strategic technical issues
— Review programs and selected 2006 -07 projects
• Collection System Program
• Treatment Plant Program
• Recycled Water Program
• General Improvements Program / IT Plan
• Summary and Conclusions
1
Review of Historical Capital Program
Activity
'FY 2005 -06 Budget
Needed projects have been expedited to
take advantage of Dougherty Revenues
CCCSD Projected Capacity Fee Revenue
$16,000,000
$14,000,000 -- —
$12,000,000 —
$10,000,000
$8,000,000
$6,000,000
$4,000,000
$2,000,000
$0
Fiscal Year
■ Base Capacity Fee Revenue 0 DV Capacity F----Re---n--e--]
G
Actual
Actual
Actual
Actual
Actual
Actual
Projected
1999 -00
2000 -01
2001 -02
2002 -03
2003 -04
2004 -05
2005 -06
Total
$21.31M
$28 M
$20.5M
$22.4 M
$19.8 M
$26.5 M
$30.9 M
Expense
($27.7W)
Total
$21.6 M
$18.9 M
$17 M
$23.5 M
$28.2 M
$30.0 M
$28.2 M
Revenue
($20.8M *)
Variance
+$0.3 M
-$9.1 M
-$3.5 M
+$1.1.M
+$8.4 M
+$3.5 M
-$2.7 M
(- $6.9M *)
'FY 2005 -06 Budget
Needed projects have been expedited to
take advantage of Dougherty Revenues
CCCSD Projected Capacity Fee Revenue
$16,000,000
$14,000,000 -- —
$12,000,000 —
$10,000,000
$8,000,000
$6,000,000
$4,000,000
$2,000,000
$0
Fiscal Year
■ Base Capacity Fee Revenue 0 DV Capacity F----Re---n--e--]
G
Expenditure Goal
For FY 2005 -06 —$30 million
For FY 2006 -07 —$35 million
CCCSD Projected Capital Project Expenditures
$45,000
$40,000
$35,000
-
Total Expedited Capacity Expenditures
-Auppro.i..tly 0 mi ion
$30,000
u $25,000
� $20,000
$15,000
$10,000
$5,000
05-06 06 -07 07 -08 08 -09 09 -10 10 -11 11 -12 12 -13 13 -14 14 -15
■ Baseline Renewal & Replacement Expenditures ■ Expedited Capacity Expenditures
Escalated 2005 -06 Projects Require
Additional Authorization
• When construction projects are awarded, funding for the entire
project must be authorized
• Moving award of a number of large projects forward to late FY
2005 -06 has created need for additional authorization
Projects include:
— Chemical Feed Building Renovation
— Service Air system Improvements
— Plant Operations Division HVAC Improvements
— Three Concrete Corrosion Projects (Cured -In -Place Pipe)
— Walnut Creek Renovation- Phase 4
— M4A Force Main
— North Orinda Renovations — Phase 2
Additional authorization needed:
— Treatment Plant Program - $3,500,000
— Collection System Program - $14,000,000
FY 2006 -07 Expenditure
Recommendations
EXPENDITURES
2006 -07
Collection System
$19,652,000
Treatment Plant
$9,691,000
General Improvements
$5,019,000
Recycled Water
$390,000
TOTAL EXPENDITURES
$34,752,000
Staffing and Equipment Resources
Deliver Projects
• Staff engineer program has effectively integrated 10
new entry level engineers into the District
• Rotation /cross training program has prepared all
technical staff to design and construct projects that
meet the needs of the operations departments
• In house design for routine projects has made
delivery more efficient
• Effective utilization of technology has also improved
project delivery
• Board support of staffing and equipment needs is key
4
FY 2006 -07 Capital Cash Flow Estimate
Capital Program Cash Flow
2006 -07
Total Projected Revenue
$38,788,000
Total Projected Expenditures
$34,752,000
Positive Variance
+$4,036,000
SCF Balance June 30, 2007
$60 M
FY 2006 -07 Revenue Projections
Revenues
2006 -07
Facility Capacity Fees
$9,369,000
Pumped Zone Fees
$2,417,000
Interest
$2,499,000
Ad Valorem Taxes
$7,243,000
City of Concord
$3,491,000
Sewer Service Charges $46 /RUE*
$7,479,000
Sewer Service Charges $30 /RUE **
$4,877,000
Other Fees & Charges
$1,413,000
Total Revenue
$38,788,000
zoos -oti capital component
2006 -07 Added Capital Component
5
FY 2006 -07 O &M Cash Flow Estimate
O&M Program Cash Flow
2006 -07
Total Projected Revenue
$47,200,000
Total Projected Expenditures
$54,200,000
Negative Variance
- $7,000,000
O&M Reserves Balance June 30, 2007
$5.8 M
Capital Revenue /Expenditure Projections
Revenue
06 -07
07 -08
08 -09
09 -10
10 -11
11 -12
Facility Capacity /
Pumped Zone Fees
$11.8M
$9.3M
$9.5M
$6.9M
$6.4M
$5.2M
Ad Valorem Tax
$7.2M
$7.6M
$7.9M
$8.3M
$8.7M
$9.1 M
Sewer Service Charge
$12.4M
$6.9M
$6.7M
$7.1M
$7.5M
$8.2M
City of Concord
$3.5M
$5.4M
$3.4M
$3.3M
$3.5M
$2.8M
Other
$3.9M
$3.8M
$3.OM
$3.1 M
$2.8M
$2.8M
Total Revenue
$38.8M
$32.OM
$30.5M
$28.7M
$28.9M
$28.1M
Total Expenditures
$34.8M
$39.3M
$37.7M
$34.7M
$33.8M
$32.1M
Variance
$ +4M
$ -7M
$ -7M
$-6M
$ -5M
$-4M
Sewer Construction
Funds
$61M
$53M
$46M
$40M
$35M
$31M
2006 -07 Capital Improvements Program Workshop
Agenda
• Financial /Human Resources Deliver Projects
— Review historical program activity and accomplishments
— Discuss need for additional authorization for 2005 -06 program
— Revisit revenue projections and ability to fund needed projects
• Strategic Goals Drive Projects
— Review progress on strategic technical issues
— Review programs and selected 2006 -07 projects
• Collection System Program
• Treatment Plant Program
• Recycled Water Program
• General Improvements Program / IT Plan
• Summary and Conclusions
Strategic Goals Drive Projects
"No violations due to inadequate
infrastructure"
• Provide continued WWTP reliability = plant control
system upgrades (April 2004)
• Prevent SSO's = collection system renovation
program (Nov 2004)
• Limit un- permitted discharges = wet weather capacity
improvements (Nov 2004)
• Avoid furnace capacity issues = emergency
backup /furnace upgrades (Nov 2005)
• Meet more stringent mercury requirements = develop
mercury control strategy (Jan 2006)
W
Plant Control System Upgrade
• Rigorous RFP process — 2004 -2005
• Transdyn, Inc. selected — NTP October 2005
• Hardware purchase authorized — March 16, 2006
• Factory testing — March — November 2006
• Installation — December 2006
• Commissioning — December 2006 — July 2007
SSO Prevention Strategy
Investment in Renovation Reduces SSO's
8
FY 90/91 — 99/00
4 Miles/Year = 40 Miles
10 Yr Cost = $40 M
Renovation
FY 00/01 — 05/06
5 Miles/Year = 30 Miles
Program
6 Yr Cost = $30 M
FY 06/07 — 15/16
10 Miles/Year = 100 Miles
10 Yr Cost = $100 M
TV Program
550 Miles of 1500 Miles of District Sewers
Inspected to Date
8
Wet Weather Capacity Improvements
• UV capacity improvements on -line Winter 2006
• Flow through outfall increased from 110 mgd to 135 mgd
• Wet weather bypass project to design in May 2006
• Discharge directly to Walnut Creek, if needed, with adequate
capacity by Winter 2007
01
FY 2006 -07 Expenditure
Recommendations
EXPENDITURES
2006 -07
Collection System
$19,652,000
Treatment Plant
$9,691,000
General Improvements
$5,019,000
Recycled Water
$390,000
TOTAL EXPENDITURES
$34,752,000
2006 -07 Expenditures
Collection System Program
PROJECT
2006 -07
Expenditures
Total
Project Cost
Concrete Corrosion M3
$2,650,000*
$2,985,000
North Orinda Renovation — Phase 2
$2,300,000*
$2,490,000
Alhambra Valley Trunk Sewer
$1,510,000
$2,275,000
M4 -A Force Main Replacement
$1,415,000*
$2,347,000
Walnut Creek Renovations — Phase 4
$1,379,000*
$1,529,000
Danville Sewer Renovations — Phase 1
$1,200,000
$1,365,000
Concrete Corrosion Minert/Arkell
$1,186,000*
$1,186,000
Concrete Corrosion Saint Mary's
$1,070,000*
$1,070,000
Total Collection System Projects <$1,000,000
$6,942,000
NA
Total Collection System Program
* Awarded in late FY 2005 -06
$19,652,000
NA
10
North Orinda Renovations — Phase 1
Customer feedback survey FY 05 -06
• 136 out of 484 surveys returned (28 %)
• 46 out of 89 "Outstanding Service" (52 %)
• 38 out of 89 "Satisfactory Service" (42 %)
• 5 out of 89 "Unsatisfactory Service" (6 %)
• Positive — Crews very polite and accommodating,
work well planned and executed
• Negative — Traffic delays, litter, patched paving
North Orinda Renovations - Phase 2
Issues at 9 Crane Court, Orinda
• Illegal Easement Encroachments:
— House Addition
— Pool
— Retaining Wall
• Three connections that were not approved or
permitted.
11
North Orinda Renovations — Phase 2
9 Crane Court Encroachments
Building permits do not exist for either
the pool or the house addition.
• Sanitary sewer was relocated outside
of easement for construction of the pool.
Relocation was not approved by the
District.
9 Crane Court - Existing Situation
12
9 Crane Court — Renovation Options
• Remove encroachments and reconstruct within
existing easement.
• Pipeburst and obtain a new easement for actual pipe
location.
• Construct sewer in new alignment around
encroachments and obtain new easement.
9 Crane Court -
Proposed
Reconstruction
WCT M4 R. 1 50'
U '
14.10 D. 0 °40'35'
B
WAS BC 13.40.05 'Al
N 2158356.]5
E
99yO�FFh"
8074072.38
S8� REMOVE 2 KS
485.
:ek "`.v
CONSTRUCT M5
- EC 1M30.68'Al 14 51. 5 1'
2159445.00 E 112.E
O A E 80]4091.78
5 $
BC 1-W.64 Al
-- -
80]41 .9
R -100'
U]t'
36' OAK
D.40 °39'374
EX 8' SD /c�9U '-�_-
�- '� K
EX
ND 15LF
SEE NOTE 1 )36' OAKS
K s'
q c
wE �EMEN1
EX STRUCTURE RET.WAL
REMOVE X PB fi
LAWN DO NOT RECON CT POOL LATERA
\
'�\ �BRICKA ON
EC 15,34.80 'Al '
\
1
159517.46
E 4154. 83
6' WOOD FENCE
Be 1
- ROOF LINE
9
159fi 4
4165.59
RET.WALU
- -� 24' REI
PS
CRANE CT
CLEAN OUT/
4
(UNDER STEPS)
R.150
EC 16,12.37'A1'
\
L.54'
21 90.19
13.20°33'33'
E 6074180.74
13
A- Line /Concord Joint Project Overview
Y p
COUNTY
r
x _
-Y _ Ul9lfido�
.MM
w — uW Rmff wTmm"Ca
s
14
A- Line /Concord Joint Project
JPA Contributions
• Recycled Water Line —30% of cost
Based on Concords average annual % of plant influent flow
• A -Line 20 -25% of cost
Based on Concords % of peak wet weather flow in this line
• Concord Intertie 100 % of cost
Replaces Concord Pumping Station and is 100% Concord flow
15
2006 -07 Expenditures
Treatment Plant Program
PROJECT
2006 -07
Expenditures
Total
Project Cost
Ultraviolet Disinfection Expansion
$1,700,000*
$4,584,000
Plant Control System Improvements
$1,000,000
$2,641,000
Standby Power Facility Improvements
$1,000,000
$1,500,000
POD HVAC and Roof Improvements
$900,000*
$1,000,000
Chemical Feed Building Renovation
$900,000*
$1,025,000
Service Air Improvements
$800,000*
$1,055,000
Total Treatment Plant Projects < $800,000
$3,391,000
NA
Total Treatment Plant Program
* Awarded in We FY 2005.06
$9,691,000
NA
2006 -07 Expenditures
Recycled Water Program
PROJECT
2006 -07
Expenditures
Total
Project Cost
Recycled Water— Pleasant Hill Phase 1B
$316,000
$4,151,000
Total Remaining Recycled Water Projects
$74,000
NA
Total Recycled Water Program
$390,000
NA
16
2006 -07 Expenditures
General Improvements Program
PROJECT
2006 -07
Expenditures
Total
Project Cost
HOB HVAC and Roof Improvements
$1,003,000
$1,636,000
Equipment Budget
$1,000,000
NA
CSOD Cal Trans Site Improvements
$800,000
1,000,000
CSOD Facility Improvements
$800,000
$10,608,000
Information Technology Development *
$450,000
NA
Total General Improvements Projects < $250,000
$966,000
NA
Total General Improvements Program
$5,019,000
NA
* Discussion to follow
Information Technology Plan
17
2006 -07 Capital Improvements Program Workshop
Agenda
Financial /Human Resources Deliver Projects
— Review historical program activity and accomplishments
— Discuss need for additional authorization for 2005 -06 program
— Revisit revenue projections and ability to fund needed projects
Strategic Goals Drive Projects
— Review progress on strategic technical issues
— Review programs and selected 2006 -07 projects
• Collection System Program
• Treatment Plant Program
• Recycled Water Program
• General Improvements Program / IT Plan
Summary and Conclusions
Capital Improvement Budget Summary for
FY 2006 -07
18
Estimated
Total
Program
FY 2006 -07
Estimated
Carry-over from
Estimated
Allocation
FY 2006.07
Program
Prior Fiscal Year
FY 2006 -07
Proposed
Expenditures
Authorization
Treatment Plant
$9,691,000
$9,410,000
$6,685,000
$16,095,000
Collection System
$19,652,000
$17,314,000
$22,654,000
$39,968,000
General Improvements
$5,019,000
$1,856,000
$13,059,000
$14,915,000
Recycled Water
$390,000
$31,000
$366,000
$397,000
Total this Fiscal Year
$34,752,000
$28,611,000
$42,764,000
1 $71,375,000
18
Board Role in Capital Program is Ongoing
• Authorize Program Budgets each fiscal year
• Authorize Supplemental Program Funds if needed
• Award Construction Projects > $15,000
• Authorize Construction Change Orders >$50,000
• Authorize Consultant Contracts > $50,000
• Authorize Revisions to Consultant Contracts > 15%
Questions?
Staff is available to stay after meeting for any detailed
technical question.
19
4.b.
Information
Technology
Development
Capital Improvement
Budget
2006 -2007
Overview
Section I: Current 2005 -06 Budget
Section II: Proposed 2006 -07 Budget
Section III: Future Projects
Section IV: Accomplishments
1
Current 2005 -06 Budget
Budget: $490k Projected: $416k
• GroupWise Email Upgrade
• Multi Purpose Room Presentation
System
• Primary Network Server Replacement
• PC Replacement Program
• Network Center Upgrade
• Eng Support Fiber Switch
Current 2005 -06 Budget - cont'd.
• Central Network Storage
• Laser Check Forms
• Mainsaver Upgrade
• Project Management Services
• Intranet Development
• Miscellaneous Hardware & Software
• Sungard HTE Sewer Billing Upgrade
2
Proposed 2006 -07 Budget
$415k
HHHWF Visitor
15
Management System
PC Replacement
110
Program
Eng Support Upgrades
30
Pumping Station
15
SCADA Laptops
35
Plan Review Upgrades
5
Training Laptop
10
Replacements
40
Proposed 2006 -07 Budget - cont'd.
Accela Software
20
Upgrade
Procurement Card
20
Application
Microsoft Office
45
Software Upgrade
Telephone
35
Management System
Upgrade
Internet & Intranet
40
Development
Project Management
20
Services
Contingency / Misc.
50
Hardware & Software
Questions ?
Central Contra Costa Sanitary District
' BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: April 13, 2006 No -: 5.a. ENGINEERING
Type of Action: AUTHORIZE FUNDS
subject: APPROVE SUPPLEMENTAL AUTHORIZATIONS FROM THE SEWER
CONSTRUCTION FUND OF $14,000,000 FOR THE COLLECTION SYSTEM
PROGRAM AND $3,500,000 FOR THE TREATMENT PLANT PROGRAM OF THE
2005 -06 CAPITAL IMPROVEMENT BUDGET (CIB)
Submitted By. Initiating Dept. /Div.:
P. Gail Chesler, PhD, Associate Engineer Engineering /Environmental Services
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
JA
CI�I�
(\' lwffarI4
G. Chesler R. Schmidt C. Swanson A.Pdrrell arles W. Batts
General Manager
ISSUE: Authorization by the Board of Directors is required for the addition of funds to
Program Budgets from the Sewer Construction Fund.
RECOMMENDATION: Authorize an additional $14,000,000 from the Sewer
Construction Fund for the Collection System Program, and an additional $3,500,000 for
the Treatment Plant Program of the 2005 -06 Capital Improvement Budget (CIB).
FINANCIAL IMPACTS: The authorization of additional funds will allow projects
scheduled for bidding this spring to continue.
ALTERNATIVES /CONSIDERATIONS: If this supplemental authorization is not
approved, the award of construction contracts for several planned projects will be
delayed.
BACKGROUND: Each year as part of the CIB adoption process, the Board of Directors
authorizes funds for each of the four capital programs: Treatment Plant, Collection
System, General Improvements, and Recycled Water. When the Capital Budget is
prepared, estimates are made of the amount of authorizations that will be needed in the
next fiscal year. Making these estimates involves projecting how much unspent
allocated money will carry over from one year to the next, and in what fiscal year
construction projects will be awarded.
Since design and construction may straddle two fiscal years, the assumption of which
fiscal year the construction contract will be awarded for large projects has a significant
impact on the size of the funding authorization that is approved by the Board as part of
the CIB.
There are six large Collection System projects that will be awarded in May or June of
2006, and, as a result, funding of the construction contract will occur in fiscal year 2005-
06 rather than 2006 -07. These projects and the estimated required authorization to
N: \ENVRSEc \Position Papers \Chesler\2006Wpprove CSO & TP Supplemental Authorizations CIB 3- 06.doc Page 1 of 2
POSITION PAPER
Board Meeting Date: April 6, 2006
subject: APPROVE SUPPLEMENTAL AUTHORIZATIONS FROM THE SEWER
CONSTRUCTION FUND OF $14,000,000 FOR THE COLLECTION SYSTEM
PROGRAM AND $3,500,000 FOR THE TREATMENT PLANT PROGRAM OF THE
2005 -06 CAPITAL IMPROVEMENT BUDGET (CIB)
fund construction include: Walnut Creek Renovation — Phase 4 ($1.6M); M4A Force
Main ($2.4M); North Orinda Renovation — Phase 3 ($2.6M); and three cured -in place
(CIPP) pipe projects ($5.6M).
In addition to the Ultraviolet Disinfection Expansion Project, where an additional
authorization was included in the position paper to award the construction contract on
April 6, 2006, there are three significant treatment plant projects that are scheduled to
award during the last three months of FY 2005 -06. These were previously thought to be
awarded in early FY 2006 -07. The projects and estimated construction allocations
include the Chemical Feed Building Renovation ($1 M); Service Air System
Improvements ($1.5M); and Plant Operations Division Building HVAC Improvements
($1 M).
All of the above projects appear in the FY 2005 -06 CIB but were not planned for
construction award until FY 2006 -07. In order to award the construction contracts for
these projects in FY 2005 -06, an additional authorization is needed. Staff requests that
the Board of Directors approve supplemental authorizations of $14M for the Collection
System program and $3.5M for the Treatment Plant program. The majority of the
construction related expenditures on the above projects will occur in FY 2006 -07.
RECOMMENDED BOARD ACTION: Authorize an additional $14,000,000 from the
Sewer Construction Fund for the Collection System Program, and an additional
$3,500,000 for the Treatment Plant Program of the 2005 -06 Capital Improvement
Budget (CIB).
N: \ENVRSEC \Position Papers \Chesler\2006\Approve CSO & TP Supplemental Authorizations CIB 3- 06.doc Page 2 of 2