HomeMy WebLinkAbout11/18/2004 AGENDA BACKUPCentral Contra Costa Sanitary District
' BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: November 18, 2004 No.: 4.a. CONSENT CALENDAR
Type of Action: ACCEPT CONTRACT WORK
subject: ACCEPT THE CONTRACT WORK FOR THE COW CREEK CROSSING
RENOVATION PROJECT, DISTRICT PROJECT NO. 5672, AND AUTHORIZE THE
FILING OF THE NOTICE OF COMPLETION
Submitted By: Initiating Dept. /Div.:
Tom Godsey, Associate Engineer Engineering / Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
401Y - - 1, f/o
T. Godsey cki B. Bren an A. Farrell *General atts,
age
ISSUE: Construction has been completed on the Cow Creek Crossing Renovation
Project, District Project 5672, and work is now ready for acceptance.
RECOMMENDATION: Accept the contract work for the Cow Creek Crossing
Renovation Project, District Project 5672, and authorize the filing of the Notice of
Completion.
FINANCIAL IMPACTS: None related to this action.
ALTERNATIVES /CONSIDERATIONS: Not Applicable. Filing the Notice of Completion
is advisable under the California Civil Code, Section 3090.
BACKGROUND: Within the Town of Danville, a sewer pipe crosses Cow Creek
between St. Edward and St. Phillip Courts (see Attachment 1). The creek had eroded
the east bank, and the manhole for this pipe was being undermined. This project re-
graded the creek channel to its original configuration and installed riprap protection to
minimize future undermining of this manhole.
The construction consisted of the temporary re- routing of creek flow, re- grading of the
creek channel, installation of riprap slope protection, and restoration of the area. On
July 15, 2004, the Board authorized the award of a contract for the construction of the
project to Pacific General Engineering, Inc. The Notice to Proceed was issued on
September 13, 2004. The work was substantially completed on October 21, 2004. The
remaining work consists of minor punch -list items, which do not affect project
acceptance.
Page 1 of 3
hDesign \Position Papers\20040P5672 Accept.DOC
POSITION PAPER
Board Meeting Date: November 18, 2004
subject. ACCEPT THE CONTRACT WORK FOR THE COW CREEK CROSSING
RENOVATION PROJECT, DISTRICT PROJECT NO. 5672, AND AUTHORIZE THE
FILING OF THE NOTICE OF COMPLETION
The total authorized budget for the project is $77,000. The budget includes the cost of
engineering design, District forces, testing services, contract services, etc. An
accounting of the project costs will be provided to the Board at the time of project
closeout.
RECOMMENDED BOARD ACTION: Accept the contract work for the Cow Creek
Crossing Renovation Project, District Project 5672, and authorize the filing of the Notice
of Completion.
Page 2 of 3
I: \Design \Position Papers\2004 \DP5672 Accept.DOC
Central Contra Costa Attachment
Sanitary District COW CREEK CROSSING RENOVATION
Agent DISTRICT PROJECT 5672
age
Central Contra Costa Sanitary District
' BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: November 18, 2004 No.: 4.b. CONSENT CALENDAR
Type of Action: ACCEPT CONTRACT WORK
subject: ACCEPT CONTRACT WORK FOR THE WALNUT CREEK SEWER
RENOVATION PROJECT, PHASE 2, DISTRICT PROJECT NO. 5709 AND
AUTHORIZE THE FILING OF THE NOTICE OF COMPLETION
Submitted By: Initiating Dept. /Div.:
Andrew Antkowiak, Associate Engineer Engineering / Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
I
&-mak (,�T Oc k W. Brennan A. Farrell h rles . Ba ,
General Man er
ISSUE: Construction has been completed on the for the Walnut Creek Sewer
Renovation Project, Phase 2, District Project No. 5709, and the work is now ready for
acceptance.
RECOMMENDATION: Accept the contract work for the for the Walnut Creek Sewer
Renovation Project, Phase 2, District Project No. 5709, and authorize the filing of the
Notice of Completion.
FINANCIAL IMPACTS: None related to this action.
ALTERNATIVES /CONSIDERATIONS: Not Applicable. Filing the Notice of Completion
is advisable under the California Civil Code, Section 3090.
BACKGROUND: The Walnut Creek Sewer Renovation Project Phase 2, renovated or
replaced several critical line segments identified in the City of Walnut Creek and
unincorporated Contra Costa County area. Approximately 5,500 linear feet of 6, 8, and
10 -inch sewer lines in fourteen locations were renovated (see Attachment 1 for map).
Five sites were located in public Right of Way, four in easements and private streets,
and the remaining five were in both easements and public Right of Way. One site was
located in downtown Walnut Creek. Because of a significant impact on traffic and local
businesses, this site was constructed during the night. The District TV program has
identified a number of other sites in Walnut Creek, and it is anticipated that there will be
at least two additional phases of the Walnut Creek project.
On May 20, 2004, the Board of Directors authorized the award of a contract for the
construction of the project to D'arcy & Harty Construction Inc., of San Francisco. The
Notice to Proceed was issued on June 11, 2004. The work was substantially completed
in October 2004.
I: \Design\Position Papers\2004 \5709 Accept Work.DOC Page 1 of 3
POSITION PAPER
Board Meeting Date: November 18, 2004
Subject: ACCEPT CONTRACT WORK FOR THE WALNUT CREEK SEWER
RENOVATION PROJECT, PHASE 2, DISTRICT PROJECT NO. 5709 AND
AUTHORIZE THE FILING OF THE NOTICE OF COMPLETION
The total authorized budget for the project is $1,572,000. The budget includes the cost
of contract administration, inspection, survey, office engineering and shop drawing
review by District forces, testing services, and contractor services. An accounting of the
project costs will be provided to the Board at the time of project closeout. It is
appropriate to accept the contract work at this time.
RECOMMENDED BOARD ACTION: Accept the contract work for the Walnut Creek
Sewer Renovation Project, Phase 2, District Project No. 5709, by D'arcy & Harty
Construction Inc., and authorize the filing of the Notice of Completion
Page 2 of 3
hDesign \Position Papers\2004 \5709 Accept Work.DOC
FEET
Central Contra Costa Attachment
Sanitary District WALNUT CREEK RENOVATIONS
' PHASE 2
CCCSD 5709
Page 3 of 3
Central Contra Costa Sanitary District
' BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: November 18, 2004 No.: 4.c. CONSENT CALENDAR
Type of Action: ACCEPT CONTRACT WORK
subject: ACCEPT CONTRACT WORK FOR THE ACACIA PARALLEL FORCEMAIN
PROJECT, DISTRICT PROJECT NO. 5727, AND AUTHORIZE THE FILING OF THE
NOTICE OF COMPLETION
Submitted By: Initiating Dept /Div.:
Andrew Antkowiak, Associate Engineer Engineering / Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
A. ntkowiak cki W. Brennan
A. Farrell
General
ISSUE: Construction has been completed on the Acacia Parallel Forcemain Project,
District Project No. 5727, and the work is now ready for acceptance.
RECOMMENDATION: Accept the contract work for the Acacia Parallel Forcemain
Project, District Project No. 5727, and authorize the filing of the Notice of Completion.
FINANCIAL IMPACTS: None related to this action.
ALTERNATIVES /CONSIDERATIONS: Not applicable. Filing the Notice of Completion
is advisable under the California Civil Code, Section 3090.
BACKGROUND: The District's 1989 Pumping Station Master Plan identified the need
to add a second forcemain to the Acacia Pumping Station to increase station reliability.
The project scope of work consisted of the installation of approximately 310 lineal feet of
new 4 -inch forcemain from Acacia Pumping Station to an existing 8 -inch capacity sewer
line. Other improvements included site paving and construction of a valve structure that
allows operating staff to work safely outside of the wetwell. The project site is shown in
Attachment 1.
On May 6, 2004, the Board of Directors authorized the award of a contract for the
construction of the project to Soares Pipeline, Inc., of Hayward. The Notice to Proceed
was issued on June 7, 2004. The work was substantially completed in October 2004.
Page 1 of 3
lADesign \Position Papers\2004 \DP5727Accept.DOC
POSITION PAPER
Board Meeting Date: November 18, 2004
subject: ACCEPT CONTRACT WORK FOR THE ACACIA PARALLEL FORCEMAIN
PROJECT, DISTRICT PROJECT NO. 5727, AND AUTHORIZE THE FILING OF THE
NOTICE OF COMPLETION
The total authorized budget for the project is $166,000. The budget includes the cost of
contract administration, inspection, survey, office engineering, shop drawing review by
District forces, testing services, and contractor services. An accounting of the project
costs will be provided to the Board of Directors at the time of project closeout. It is
appropriate to accept the contract work at this time.
RECOMMENDED BOARD ACTION: Accept the contract work for the Acacia Parallel
Forcemain Project, District Project No. 5727, by Soares Pipeline, Inc., and authorize the
filing of the Notice of Completion.
Page 2 of 3
1ADesign \Position Papers\20040P5727Accept.DOC
FLUSH KLEEN
PUMPING
STATION
r
N
J NEW PARALLEL
r FORCE MAIN
CP // r
ACACIA
r STATIIONG
ACACIA 2 ��e;oql PUMP ING ° STATION / 4
OR EXISTING EXISTING
FORCE MAIN 8" GRAVITY
EL
PROJECT
LOCATION
o
l',S TP
�
N
0 120 240
FEET
lq
z
in LOWER ORINDA
PUMPING STATION
BRQgr�w OOO
0
ORINDA CROSSROAD
PUMP STATION ,
Central Contra Costa Attachment
Sanitary District ACACIA PARALLEL FORCE MAIN PROJECT
' DP 5727
Page 3 of 3
Central Contra Costa Sanitary District
/Jai ` BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: November 18, 2004 No.: 4.d. CONSENT CALENDAR
Type of Action: ACCEPT CONTRACT WORK
subject: ACCEPT THE CONTRACT WORK FOR THE TREATMENT PLANT
ELECTRICAL CABLE REPLACEMENT, DISTRICT PROJECT NO. 721,,AND
AUTHORIZE THE FILING OF THE NOTICE OF COMPLETION
Submitted By: Initiating DeptJDiv.:
Alex Rozul, Associate Engineer Engineering / Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
0
_57T
V' v ' /
Gk
A. Rozul
B. Than
W. Brennan
A. Farrell
General
ISSUE: Construction has been completed on the Treatment Plant Electrical Cable
Replacement, District Project No. 7214, and the work is now ready for acceptance.
RECOMMENDATION: Accept the contract work for the Treatment Plant Electrical
Cable Replacement, District Project No. 7214, and authorize the filing of the Notice of
Completion.
FINANCIAL IMPACTS: None related to this action.
ALTERNATIVES /CONSIDERATIONS: Not Applicable. Filing the Notice of Completion
is advisable under the California Civil Code, Section 3090.
BACKGROUND: Power for the Treatment Plant's electrical system is distributed (fed)
from the main substations to the local area substations through medium -high voltage
electrical cables. These "feeders" cables were installed in the mid -1970s and were
aluminum or copper with insulation that was not suitable for wet locations. In
submersed conditions, the insulation was found to crack and fail catastrophically.
Maintenance inspections uncovered areas that were candidates for premature failures
that could seriously cripple the plant's electrical system. Seventy percent (70 %) of
those cables were replaced in previous capital improvement projects.
This project replaced the remaining medium -high voltage cables to maintain the
reliability of the main electrical distribution system. Plans and specifications for this
Project were produced by ATS Engineering Services (ATS) and District staff and were
reviewed by Montgomery Watson Harza (MWH). MWH also provided construction
support services that included reviewing shop drawings and submittals.
On April 1, 2004, the Board of Directors (Board) authorized the award of a contract for
the construction of the project to Con J. Franke Electric, Inc. of Stockton. The Notice to
L: \Position Papers \Rozul \7214Acceptance.DOC Page 1 of 2
POSITION PAPER
Board Meeting Date: November 18, 2004
subiect: ACCEPT THE CONTRACT WORK FOR THE TREATMENT PLANT
ELECTRICAL CABLE REPLACEMENT, DISTRICT PROJECT NO. 7214 AND
AUTHORIZE THE FILING OF THE NOTICE OF COMPLETION
Proceed was issued on April 26, 2004. The work was substantially completed on
October 29, 2004. The remaining items of work consist of minor punch -list items, which
do not affect the project acceptance.
The total authorized budget for the project is $1,606,000. The budget includes the cost
of engineering design, District forces, testing services, contractor services, etc. An
accounting of the project costs will be provided to the Board at the time of project close-
out. It is appropriate to accept the contract work at this time.
RECOMMENDED BOARD ACTION: Accept the contract work for the Treatment Plant
Electrical Cable Replacement, District Project No. 7214, and authorize the filing of the
Notice of Completion.
L: \Position Papers \Rozu1\7214Acceptance.DOC Page 2 Of 2
Central Contra Costa Sanitary District
' BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: NOVEMBER 18, 2004 No.: 4.e. CONSENT CALENDAR
Type of Action: ACCEPT CONTRACT WORK/AUTHORIZE NOTICE OF COMPLETION
Subject: ACCEPT CONTRACT WORK FOR THE TREATMENT PLANT SAFETY
ENHANCEMENTS PROJECT, DISTRICT PROJECT NO. 7219, AND AUTHORIZE
THE FILING OF THE NOTICE OF COMPLETION
Submitted By: Initiating DeptJDiv.:
Clint Shima, Assistant Engineer Engineering / Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
C. Shima B. Than W. Brennan A. Farrell *General
ager
ISSUE: All contract work has been completed on the Treatment Plant Safety
Enhancements Project, District Project No. 7219, and the project is now ready for
acceptance.
RECOMMENDATION: Accept contract work.
FINANCIAL IMPACTS: None related to this action.
ALTERNATIVES /CONSIDERATIONS: Not applicable. Filing the Notice of Completion
is covered under California Civil Code, Section 3093.
BACKGROUND: The Treatment Plant Safety Enhancements, DP 7219, incorporates a
number of Treatment Plant Maintenance Division safety- related work orders into one
capital project to gain the advantage of economy of scale. The scope of work included:
railing enhancement, concrete work, platform fabrication, ductwork, valve extension,
davit arm placement, earthwork, and grating enhancement.
The Board of Directors authorized the award of a construction contract for the work in
the amount of $143,369 to Valentine Corporation on February 5, 2004. The Notice to
Proceed was effective on March 15, 2004, and called for a completion date of
June 23, 2004. The Contractor performed additional work for which a time extension
was given. This extra work included laying crushed rock for maintenance access to the
primary tanks, installing ladders for the standby generators, eliminating tripping hazards
at the ultraviolet disinfection channel, installing additional davit arm mounts, and
constructing viewing hatches for the sludge blending tank.
It is appropriate to accept the contract work at this time.
this project is $225,000. An accounting of the projec t
Board of Directors at project close out.
The total authorized budget for
costs will be provided to the
LAPosition Papers \Shima \7219 NOC.DOC Page 1 of 2
POSITION PAPER
Board Meeting Date: November 18, 2004
Subject: ACCEPT CONTRACT WORK FOR THE TREATMENT PLANT SAFETY
ENHANCEMENTS PROJECT, DISTRICT PROJECT NO. 7219, AND AUTHORIZE
THE FILING OF THE NOTICE OF COMPLETION
RECOMMENDED BOARD ACTION: Accept Contract work for the Treatment Plant
Safety Enhancements Project, District Project No. 7219, by Valentine Corporation, and
authorize the filing of the Notice of Completion.
L: \Position Papers \Shima \7219 NOC.DOC Page 2 of 2
Central Contra Costa Sanitary District
' BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: November 18, 2004 No.: 4.f. CONSENT CALENDAR
Type of Action: SET DATE FOR PUBLIC HEARING
subject: ESTABLISH DECEMBER 16, 2004 AS THE DATE FOR A PUBLIC
HEARING TO RECEIVE COMMENTS ON PROPOSED REIMBURSEMENT FEES
FOR THE PROPERTIES WHICH COULD DIRECTLY CONNECT TO JOB 5694
(WINCHESTER LANE, MARTINEZ) AND JOB 5732 (ORCHARD ESTATES DRIVE,
WALNUT CREEK).
Submitted By: Initiating Dept /Div.:
Michael J. Penny Engineering /Environmental Services
Associate Engineer
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
y J. Miyamoto -Mills C. Swanson A. Farrell le att ,
General ana r
ISSUE: When a Reimbursement Fee is proposed for properties that could directly
connect to a "standard facility" installed by private individuals, the District Code requires
a public hearing be held prior to the Board of Directors' adoption of the fee.
RECOMMENDATION: Establish the Board's regularly scheduled meeting on
December 16, 2004 as the date for a public hearing to receive comments on proposed
Reimbursement Fees for properties which could connect to the "standard facilities"
identified as Job 5694 (Winchester Lane, Martinez) and Job 5732 (Orchard Estates
Drive, Walnut Creek).
FINANCIAL IMPACTS: None related to this action.
ALTERNATIVES /CONSIDERATIONS: Not Applicable.
BACKGROUND: The design and construction of "standard facilities" for Job 5694 and
Job 5732 were paid for by private individuals. After a project is completed by the
installer and accepted by the District, the installer contributes the project to the District
for public use. Non - installer properties may connect to the contributed public sewers.
The District Code provides for a Reimbursement Fee to the installer, so the installer
may recover a portion of the cost for the contributed facility.
The proposed Reimbursement Fees would be collected from property owners when
they connect to the sewer system. The collected fees would then be disbursed to the
installers of the projects.
Page 1 of 3
U: \Position Papers \Penny \SET HEARING DATE - WINCHESTER & ORCHARD ESTATES.DOC
POSITION PAPER
Board Meeting Date: November 18, 2004
subject. ESTABLISH DECEMBER 16, 2004 AS THE DATE FOR A PUBLIC
HEARING TO RECEIVE COMMENTS ON PROPOSED REIMBURSEMENT FEES
FOR THE PROPERTIES WHICH COULD DIRECTLY CONNECT TO JOB 5694
(WINCHESTER LANE, MARTINEZ) AND JOB 5732 (ORCHARD ESTATES DRIVE,
WALNUT CREEK).
The District Code requires that a notice of public hearing be mailed to owners of
properties to which the fee could be applicable at least ten days in advance of the date
set for the hearing. The notice is to include a general description of the reimbursement
fee program, a description of the facility which gives rise to the proposed fee, and the
amount of the proposed fee.
RECOMMENDED BOARD ACTION: Establish the Board's regularly scheduled
meeting on December 16, 2004 as the date for a public hearing to receive comments
on proposed Reimbursement Fees for properties which could connect to the "standard
facilities" identified above.
Page 2 of 3
U: \Position Papers \Penny \SET HEARING DATE - WINCHESTER & ORCHARD ESTATES.DOC
0
N
Z
00
OWINCHESTER LN, MAMNEZ (JOB 5694)
OORCHARD ESTATES DR WALNUT CREEK (JOB 5732)
Central Contra Costa
Sanitary District
REIMBURSEMENT PROGRAM
JOB LOCATIONS
Page 3 of 3
Attachment
1
Central Contra Costa Sanitary District
' BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: November 18, 2004 No.: 4.g. CONSENT CALENDAR
Type of Action: HUMAN RESOURCES
Subject: AUTHORIZE MEDICAL LEAVE OF ABSENCE WITHOUT PAY FOR
STEVEN PLUNKETT, UTILITY WORKER THROUGH JANUARY 27,
2005
Submitted By: James M. Kelly Initiating Dept /Div.: Operations/
Director of Operations Plant Operations
REVIEWED AND RECOMMENDED FOR BOARD ACTION.
Wreit J. Kell Z. *General a
ag r
ISSUE: Board of Directors' authorization is required for a medical leave of absence
without pay in excess of 30 days.
RECOMMENDATION: Authorize medical leave of absence without pay for Steven
Plunkett, Utility Worker
FINANCIAL IMPACTS: Minimal
ALTERNATIVES /CONSIDERATIONS: Deny medical leave of absence without pay
BACKGROUND: Steven Plunkett, Utility Worker, has been off of work since
September 3, 2004, due to a serious medical condition that may be work - related.
Mr. Plunkett applied for, was granted, and used 12 weeks of Family Medical Leave.
We request that Mr. Plunkett be granted a medical leave of absence without pay until
January 27, 2005. Mr. Plunkett's status will likely be known by that time, and further
Board action will be requested if appropriate.
RECOMMENDED BOARD ACTION: Authorize medical leave of absence without pay
for Steve Plunkett, Utility Worker, through January 27, 2005.
Page 1 of 1
S: \Correspondence \Position Papers12004 \Plunkett -Leave of Absence.doc
Central Contra Costa Sanitary District
' BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: November 18, 2004 No.: 4.h. CONSENT CALENDAR
Type of Action: CONSIDER EMERGENCY WITHDRAWAL
subject: CONSIDER A REQUEST FOR EMERGENCY WITHDRAWAL OF FUNDS
FROM THE DEFERRED COMPENSATION PLAN
Submitted By:
Debbie Ratcliff, Controller
Initiating Dept /Div.:
Administrative /Finance & Accounting
REVIEWED AND RECOMMENDED FOR BOARD ACTION.
D. Ratrl,. " A Vgraves
General
ISSUE: Authorization by the Board of Directors is required for emergency withdrawal of
funds from the Deferred Compensation Plan.
RECOMMENDATION: Approve the request by Derhyl Houck for an emergency
withdrawal of $7,000 effective December 1, 2004, from the Deferred Compensation
Plan, as recommended by the Deferred Compensation Plan Advisory Committee.
FINANCIAL IMPACTS: None
ALTERNATIVES /CONSIDERATIONS: This request could be denied, however, this is
not recommended as the request meets the requirements for emergency withdrawals
as set forth by the Internal Revenue Service.
BACKGROUND: Derhyl Houck, Maintenance Technician III, Mechanical, has
requested an emergency withdrawal from the Deferred Compensation Plan based on
extreme financial hardship caused by a sudden and continuing illness. The Deferred
Compensation Plan Advisory Committee has reviewed the request and determined that
it meets the requirements for emergency withdrawal in the amount of $7,000.
RECOMMENDED BOARD ACTION: Approve the request by Derhyl Houck for an
emergency withdrawal of $7,000 for the month of December, 2004, from the Deferred
Compensation Plan, as recommended by the Deferred Compensation Plan Advisory
Committee.
SAADMIMPOSPAPEMHouck Emergency Withdrawal 11- 18- 04.130C Page 1 Of 1
Central Contra Costa Sanitary District
' BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: November 18, 2004 No.: 4. i . CONSENT CALENDAR
Type of Action: REJECT CLAIM
subject: REJECT CLAIM FOR DAMAGES BY GREGGORY AND FRANCOISE
HANSEN, DBA: ASPEN BUILDING TECHNOLOGIES, 1042 BROWN AVENUE,
LAFAYETTE, CA.
Submitted By: Kimberly Greer Initiating Dept. /Div.: Administrative
Safety and Risk Management Administrator
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
K. Greer 1K. kfdsgraves
Charles
General
ISSUE: The District received a claim for damages due to a sanitary sewer overflow in
the amount of $30,346.67.
RECOMMENDATION: Reject the claim.
FINANCIAL IMPACTS: There are no immediate financial impacts for rejection of the
claim.
ALTERNATIVES /CONSIDERATIONS: The alternative to this action is to pay the claim
as submitted and subrogate against the City of Lafayette.
BACKGROUND: The District responded to a sanitary sewer overflow that occurred on
July 7, 2004. Emergency cleanup services were provided through a District cleaning
contractor. The District received the claim for damages on October 26, 2004. Upon
further investigation it is believed that a paving contractor, performing work under
contractor for the City of Lafayette, dropped debris into the line which caused the line to
plug and thus overflow.
RECOMMENDED BOARD ACTION: Deny the claim submitted by Greggory and
Francoise Hansen and direct staff to send a rejection letter to the claimant(s).
Page 1 of 1
Central Contra Costa Sanitary District
' BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: November 18, 2004 No.: 7.a. ENGINEERING
Type of Action: AUTHORIZE CHANGE ORDER
Subject: AUTHORIZE THE GENERAL MANAGER TO EXECUTE A CONSTRUCTION
CHANGE ORDER GREATER THAN $50,000 TO K. J. WOODS CONSTRUCTION
INC. ON THE M3 SAG RENOVATION PROJECT (DP5630)
Submitted By: Initiating Dept /Div.:
Andrew Antkowiak/ Associate Engineer Engineering /Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
ntkowiak cki W. Brennan
711 1
A. Farrell
General
ISSUE: Authorization of the Board of Directors is required for the General Manager to
execute a construction change order in an amount greater than $50,000.
RECOMMENDATION: Authorize the General Manager to execute a construction
change order greater than $50,000 to K. J. Woods Construction Inc. on the M3 Sag
Renovation Project, District Project 5630.
FINANCIAL IMPACTS: The cost of the construction change order is estimated not to
exceed $180,000 to dispose of contaminated soil to a Class II landfill.
ALTERNATIVES /CONSIDERATIONS: On prior projects, the contaminated soil
excavated from the sewer trench would be placed back in the trench as a backfill
material in order to avoid the cost of disposal. In this situation, the excavated soil was
unsuitable for backfill due to its poor compaction characteristics. Using the soil as
backfill would have created continuous road settlement issues. With upcoming rain
events projected, disposal to a Class II landfill was the only viable alternative available.
BACKGROUND: The existing 36 -inch gravity sewer in Waterbird Way in Martinez
(called the M3 line) was constructed in very soft soil (Bay Mud) and settled several feet
creating a debris trap and high levels of hydrogen sulfide upstream of the sag. The M3
Sag Renovation Project was designed to relocate the existing 36 -inch pipe into stable
soil in the public roadway.
The plans for the M3 Sag Renovation Project required relocating of approximately 300
feet of existing 36 -inch pipe into stable soil in Waterbird Way. See Attachment 1 for
project location. During the design phase, initial potholing was done to verify the limits
of the sag. The groundwater from the potholing was tested at the District laboratory.
The test results did not show signs of contamination; therefore, no additional soil testing
L \Design \Position Papers\2004 \DP5630 Change Order.DOC Page 1 of 3
POSITION PAPER
Board Meeting Date: November 18, 2004
subject: AUTHORIZE THE GENERAL MANAGER TO EXECUTE A CONSTRUCTION
CHANGE ORDER GREATER THAN $50,000 TO K. J. WOODS CONSTRUCTION
INC. ON THE M3 SAG RENOVATION PROJECT (DP5630)
was performed, and the costs of soil disposal in a Class II landfill was unanticipated. If
soil testing had been done and the contamination identified during the design phase,
these additional costs would have been included in the original bid price.
On September 9, 2004, K.J. Woods Construction Inc. (K.J.Woods) performed test
potholes to allow the District to verify the elevations of existing pipe. During excavation
of the potholes, K.J. Woods noticed a layer of black soil that looked potentially
contaminated. The soil was sent to a laboratory for testing. On October 1, 2004 the
District received the results. The results showed that the material is non - hazardous, but
has elevated levels of vanadium. The elevated vanadium levels required disposal at a
Class II landfill. To verify the extent of the soil contamination, a second series of tests
were performed on the soil excavated in the roadway. The District received the test
data on October 11, 2004. The data showed elevated levels of vanadium and mercury;
therefore, all of the trench material had to be disposed of at a Class II landfill.
Since the project site was next to a drainage ditch, the California Department of Fish
and Game permit required the construction to be finished by October 31, 2004. No
suitable temporary storage area for the contaminated soil was available, so District staff
informed the Board of Directors at the October 7, 2004, meeting that staff had directed
the Contractor to begin off hauling the contaminated material to a Class II landfill.
Since the disposal of large quantities of material at a Class II landfill was not included in
the specifications, the Contractor needs to be compensated on a change order basis.
Staff has negotiated unit price costs with the contractor, K.J. Woods. It is anticipated
that the change order will be just under $180,000.
RECOMMENDED BOARD ACTION: Authorize the General Manager to execute a
construction change order greater than $50,000 to K. J. Woods Construction Inc., on
the M3 Sag Renovation Project, District Project 5630.
(:\Design \Position Papers\2004 \DP5630 Change Order.DOC Page 2 of 3
Mti
Central Contra Costa Attachment
Sanitary District M3 SAG RENOVATION PROJECT
t CCCSD D.P. 5630 7
Page 3 of 3
Central Contra Costa Sanitary District
' BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: November 18, 2004 No.: 7,b. ENGINEERING
Type of Action: AUTHORIZE AMENDMENT
Subject: AUTHORIZE THE PRESIDENT OF THE BOARD OF DIRECTORS AND THE
SECRETARY OF THE DISTRICT TO EXECUTE AN AMENDMENT TO A JOINT
POWERS AGREEMENT WITH THE CITY OF PLEASANT HILL FOR THE
PLEASANT HILL RELIEF INTERCEPTOR, PHASE 5, DISTRICT PROJECT 5659
Submitted By: Initiating Dept. /Div.:
Tad J. Pilecki, Principal Engineer Engineering /Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
A0 Q�_
ilecki B. Brennan A. rbffdll
General Man
ISSUE: Board of Directors' authorization is required for agreements with other public
agencies.
RECOMMENDATION: Authorize the President of the Board of Directors and the
Secretary of the District to execute an amendment to the Joint Powers Agreement
(JPA) with the City of Pleasant Hill (City) to remove the paving /road reconstruction of
Patterson Boulevard from the District's projects.
FINANCIAL IMPACTS: $166,800 will be paid to the City of Pleasant Hill in order that
the District meets its paving obligation under the JPA. This is the same amount the
District would have spent on paving under the original JPA. The District will save
$10,000 - $15,000 in expenditures associated with inspection, contact administration,
and change orders by having the City of Pleasant Hill complete this work.
ALTERNATIVES /CONSIDERATIONS: The JPA provides for either the City or the
District to delete the paving /road reconstruction of Patterson Boulevard from the
District's project. The Board could decide not to contribute to the paving projects or
reduce the District's contribution, but this alternative is not recommended.
BACKGROUND: At the April 15, 2004 Board meeting, the Board authorized the
President of the Board and the Secretary of the District to sign a JPA with the City of
Pleasant Hill. The JPA incorporated a replacement irrigation water line owned by
Diablo Vista Irrigation District, complete road reconstruction and repairs of Patterson
Boulevard. Under the terms of the JPA, the District would pay one half of the paving
costs ($166,800) and the City would pay half of the paving costs and 100 percent of the
road reconstruction and irrigation water line replacement. The $166,800 is based on
one half of the bid item for repaving and reflects actual anticipated damage to the
roadway by the District project.
L: \Position Papers \Pilecki \5659 Agreement.doc Page 1 of 2 11/9/2004 11:21 AM
POSITION PAPER
Board Meeting Date: November 18, 2004
subject. AUTHORIZE THE PRESIDENT OF THE BOARD OF DIRECTORS AND THE
SECRETARY OF THE DISTRICT TO EXECUTE AN AMENDMENT TO A JOINT
POWERS AGREEMENT WITH THE CITY OF PLEASANT HILL FOR THE
PLEASANT HILL RELIEF INTERCEPTOR, PHASE 5, DISTRICT PROJECT 5659
Recently, the City of Pleasant Hill approached the District with a request to defer the
paving /reconstruction of Patterson Boulevard until the middle of 2005. The Contra
Costa Water District wants to replace an existing water line in Patterson Boulevard from
Oak Park Boulevard to Boyd Road, on the opposite side of the same road in which the
District installed its new sewer line. The District contractor, Ranger Pipelines, is ready
to start the reconstruction /paving now. The City wants to reconstruct/pave Patterson
Boulevard after the water line is installed to preserve the integrity of the new roadway.
District staff has negotiated an amendment to the JPA with the City, under which the
City will take over the responsibility for design, bid, and construction of the Patterson
Boulevard improvements under a separate project. The District would meet its paving
obligation by reimbursing the City for $166,800, the same amount that would have been
spent on paving under the original JPA. Staff believes this is an equitable cost - sharing
arrangement. A detailed discussion of the cost - sharing arrangements has been
provided to the Board under a separate White Paper.
Under the terms of the Amendment to the JPA, the District and City will be sending a
joint letter to the impacted residents explaining the status of the paving /reconstruction
of Patterson Boulevard.
RECOMMENDED BOARD ACTION: Authorize the President of the Board of Directors
and the Secretary of the District to execute an amendment to the Joint Powers
Agreement with the City of Pleasant Hill.
L: \Position Papers\Pilecki \5659 Agreement.doc Page 2 of 2 11/9/2004 11:21
AM
Central Contra Costa Sanitary District
' BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: November 18, 2004 No.: 7,c. ENGINEERING
Type of Action: AUTHORIZE AGREEMENT
subject: AUTHORIZE THE GENERAL MANAGER TO EXECUTE AN AGREEMENT
WITH MONTGOMERY WATSON HARZA TO PROVIDE PROFESSIONAL
ENGINEERING SERVICES FOR THE DESIGN OF THE ULTRAVIOLET
DISINFECTION EXPANSION PROJECT, DISTRICT PROJECT 7240
Submitted By: Initiating DeptJDiv.:
Ba T. Than, Senior Engineer Engineering / Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
TT [An Wk
B. Than W. Brennan A. Farrell
General
ISSUE: Board of Directors' authorization is required for the General Manager to
execute professional engineering services contracts for amounts greater than $50,000.
RECOMMENDATION: Authorize the General Manager to execute an agreement with
Montgomery Watson Harza to provide design services for the Ultraviolet Disinfection
Expansion Project, District Project 7240, in the amount of $300,000.
FINANCIAL IMPACTS: The estimated design cost for this project, including District
staff, is $330,000. A detailed estimate of the construction cost will be completed after
the project design; the total project cost is expected to be in the range of $2,500,000.
When the construction scope of work and estimate are available, a budget for the
engineering services during construction will be negotiated with Montgomery Watson
Harza.
ALTERNATIVES /CONSIDERATIONS: An alternative would be to design the project
using in -house engineering. This project requires specialized expertise, which is not
available at the District at this time.
BACKGROUND: The existing ultraviolet disinfection facility (UV) was completed and
operational in the second quarter of 1997. UV equipment was installed in six (6) of
eight (8) hydraulic channels; the remaining spare two (2) channels were constructed for
future expansion. Montgomery Watson Harza (MWH) provided design and construction
support for the original Ultraviolet Disinfection Facilities Project, DP 7100.
L: \Position Papers \Than \7240 Execute Agreement.DOC Page 1 of 2 11/8/2004 11:26 AM
POSITION PAPER
Board Meeting Date: November 18, 2004
subject. AUTHORIZE THE GENERAL MANAGER TO EXECUTE AN AGREEMENT
WITH MONTGOMERY WATSON HARZA TO PROVIDE PROFESSIONAL
ENGINEERING SERVICES FOR THE DESIGN OF THE ULTRAVIOLET
DISINFECTION EXPANSION PROJECT, DISTRICT PROJECT 7240
The current UV capacity is about 90 million gallons per day (mgd). District staff
evaluated the wet weather capacities for both bypass and secondary treatment, and
recommended an increase in secondary treatment capacity to 135 mgd. By increasing
our secondary treatment capacity through expansion of the UV capacity, the District will
significantly reduce or possibly eliminate the need to bypass wastewater to the basins
and to Walnut Creek. The detailed flow analysis was presented to the Board on
September 16, 2004, as well as during the 2004 Capital Planning Workshop on
November 4, 2004.
MWH satisfactorily performed the design and construction support of the original
Ultraviolet Disinfection Facilities Project, DP 7100. The MWH staff proposed for this
project is the same staff the District used for the original UV project. This MWH staff
has extensive hydraulic, electrical and instrumentation knowledge of our existing
system. MWH has unique experience and was selected for the original project through
the formal proposal process. Therefore, staff recommends selecting MWH for this
follow -up work. Staff has negotiated a contract with MWH in an amount not to exceed
$300,000 for the design only. MWH will be also needed to provide support during the
construction. The amount of this contract will be negotiated at that time.
The Ultraviolet Disinfection Expansion Project is included in the Fiscal Year 2004 -05
Capital Improvement Budget, pages TP -98 through TP -100. The design for the project
will start this month and will be completed by May 2005. Following the bidding and
awarding processes, construction of the expansion of the ultraviolet disinfection system
will commence in Fall 2005.
At its October 11, 1993 meeting, the District Board of Directors found the Ultraviolet
Disinfection Project to be exempt from the California Environmental Quality Act
(CEQA). A Notice of Exemption was filed with the Contra Costa County Clerk.
RECOMMENDED BOARD ACTION: Authorize the General Manager to execute a
professional engineering services agreement with Montgomery Watson Harza in the
amount of $300,000, for the design of the Ultraviolet Disinfection Expansion Project,
District Project 7240.
L: \Position Papers \Than \7240 Execute Agreement.DOC Page 2 of 2 11/8/2004 11:26 AM
Central Contra Costa Sanitary District
' BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: November 18, 2004 No.: 8.a. COLLECTION SYSTEM
Type of Action: APPROVE AGREEMENT
Subject: APPROVE AN AGREEMENT WITH DUBLIN SAN RAMON SERVICES
DISTRICT FOR WASTEWATER INTERCONNECTIONS
Submitted By: Initiating Dept /Div.:
James M. Kelly, Operations /Plant Operations
Director of Operations
REVIEWED AND RECOMMEND F OARD ACTION.
J. Kell K. Alm
General
ISSUE: Board approval is required for agreements with other public agencies.
RECOMMENDATION: Authorize the General Manager to execute an agreement with
Dublin San Ramon Services District for wastewater interconnections.
FINANCIAL IMPACTS: Minimal.
ALTERNATIVES/CONSIDERATIONS: None
BACKGROUND: During the San Ramon Pumping Station Renovations Project, District
Project No. 5460, a temporary interconnection was constructed to allow flow to be
diverted from the pumping station to Dublin San Ramon Services District's (DSRSD)
collection system. This interconnection was very useful during construction, and was
considered as a potential permanent emergency diversion point. When this
consideration was proposed, DSRSD stated that it would be willing to enter into a long-
term interconnection agreement.
While it would take a series of unusual conditions for the interconnection to be used, a
long -term connection would reduce the possibility of an overflow from the San Ramon
Pumping Station. Based on greatly reducing the possibility of a pumping station
overflow, District staff has worked with DSRSD staff to develop a long -term agreement.
The agreement is for five years with automatic annual renewals thereafter. The
interconnection would normally remain open to provide backup for the pumping station.
DSRSD may wish to install an alarm in its collection system to ensure that use of the
interconnection does not cause an overflow of the DSRSD collection system; the
District would reimburse DSRSD its actual cost to install the alarm. The District would
also pay DSRSD its additional cost for accepting flow from the District.
& \Correspondence \Position Papers\2004 \DSRSD WW Interconnections.doc Page 1 of 2
POSITION PAPER
Board Meeting Date: November 18, 2004
Subject: APPROVE AN AGREEMENT WITH DUBLIN SAN RAMON SERVICES
DISTRICT FOR WASTEWATER INTERCONNECTIONS
The agreement establishes procedures for other interconnections. While no additional
interconnection is foreseen at this time, one could be established under this agreement
if needed for a construction project, spill, emergency response, etc.
RECOMMENDED BOARD ACTION: Authorize the General Manager to execute an
agreement with DSRSD for wastewater interconnections.
Page 2 of 2
S:\Correspondence \Position Papers\2004 \DSRSD WW Interconnections -CMdoc
Central Contra Costa Sanitary District
' BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: November 18, 2004 NO.: 10.a. BUDGET AND FINANCE
Type of Action: APPROVE FINANCIAL REPORT
Subject: APPROVE THE COMPREHENSIVE ANNUAL FINANCIAL REPORT AS OF
JUNE 30, 2004 FOR SUBMISSION TO THE GOVERNMENT FINANCE OFFICERS
ASSOCIATION.
Submitted By:
Debbie Ratcliff
Initiating Dept./Div.:
Finance & Accounting
REVIEWED AND RECOMMENDED FOR BOARD ACTION.
4
D. RaW07 A. Wsgraves
General
ISSUE: Board approval is requested to submit a Comprehensive Annual Financial
Report (CAFR) to the Government Finance Officers Association of United States and
Canada (GFOA) for review.
RECOMMENDATION: Review and approve the June 30, 2004 CAFR for GFOA
submission.
FINANCIAL IMPACTS: There is an application fee for submission of a CAFR for
review based on total revenues of the entity applying. The District fee is $415 based on
this sliding fee schedule.
ALTERNATIVES /CONSIDERATIONS: None for the current year.
BACKGROUND: The GFOA is a professional association of state /provincial and local
finance officers in the United States and Canada, and has served the public finance
profession since 1906. The association's members are dedicated to the sound
management of government financial resources and the GFOA provides input to the
Governmental Accounting Standards Board (GASB). The GFOA sponsors the
Certificate of Achievement for Excellence in Financial Reporting Program.
The Finance and Accounting Division has prepared the District's GAFR as of June 30,
2004. The District was awarded a Certificate of Achievement for Excellence in
Financial Reporting by the GFOA for reports submitted for the 2000, 2001, 2002, and
2003 fiscal years. The Certificate of Achievement is the highest form of recognition for
excellence in state and local government financial reporting. In order to be awarded a
Certificate of Achievement, a government must publish an easily readable and
efficiently organized comprehensive annual financial report. The CAFR includes ten
years of historical financial and statistical data. This report must satisfy both generally
accepted accounting principles and applicable legal requirements.
Page 1 of 2
SAADMINTOSPAPEMCAFR 11- 04.doc
POSITION PAPER
Board Meeting Date: November 18, 2004
Subject. APPROVE THE COMPREHENSIVE ANNUAL FINANCIAL REPORT AS OF
JUNE 30, 2004 FOR SUBMISSION TO THE GOVERNMENT FINANCE OFFICERS
ASSOCIATION.
A Certificate of Achievement is valid for a period of one year only. We believe our
current comprehensive financial report continues to meet the Certificate of Achievement
Program's requirements and we are asking approval to submit it to the GFOA to
determine its eligibility for another certificate.
The Board Finance Committee reviewed a draft of the June 30, 2004 CAFR and
recommended two minor word changes.
RECOMMENDED BOARD ACTION: Approve the CAFR for submission to the GFOA.
Page 2 of 2
S:WDMIMPOSPAPER\CAFR 11- 04.doc