HomeMy WebLinkAboutCAPITAL PROJECTS ACTION SUMMARY 06-02-10Central Contra Costa Sanitary District
SPECIAL MEETING OF THE
CENTRAL CONTRA COSTA
SANITARY DISTRICT
CAPITAL PROJECTS COMMITTEE
ACTION SUMMARY
Chair McGill
Member Menesini
BOARD OF UIRF.C"l'ORS
A/lCH:Ifif. H ,l/CG/L(,
Pre.vidun
HAXH: VL! U. HUCAE.f.l.
Presider! Pro %'em
GEH:ILU H. LUCt.'Y
AfdWO h!. M1lfiNfSlNI
PHOh'E.~ (925)118-9500
F.lX: (915J 676-72 / l
wwu, ~o~,.,,1~„~ ,,.o
Wednesday, June 2, 2010
3:00 p.m.
Executive Conference Room
5019 Imhoff Place
Martinez, California
PRESENT: Mike McGill, Mario Menesini, Jim Kelly, Ann Farrell, Randy Musgraves, Tad
Pilecki, Curt Swanson, Randy Grieb, Don Rhoads, Andrew Antkowiak, Ba Than,
Alex Rozul, Michael Penny, Gail Chester
1. Call Meeting to Order
Chair McGill called the meeting to order at 3 p.m.
2. Public Comments
None.
'3. Results of Sewer Renovation and Maintenance Benchmarking Study with other
representative agencies
Principal Engineer Michael Penny reviewed the results of the Sewer Renovation
and Maintenance Benchmarking Study (attached), which found that the District's
sewer system overflow rate and past and planned renovation rates fall in the
middle of those agencies surveyed.
COMMITTEE ACTION: Concurred that the District's current planned
renovation rate should continue to be funded as recommended in the 2010
Capital Improvement Plan being considered by the Board at the June 3,
2010 Board Meeting.
Recycled Paper
Capital Projects Committee
May 27, 2010
Page 2
`4. Update on selected current Capital Projects (Staff)
• Dry/Wet Weather Bypass
• Seismic Improvements
Senior Engineer Ba Than provided updates on the Dry/Wet Weather Bypass
Project (attached) and the Seismic Improvement Project. Both projects have
been delayed. Bids were received on the Dry/Wet Weather Bypass project on
May 19, 2010; however, a permit is forthcoming which would allow the project to
be awarded at the June 17, 2010 Board meeting. If the permit is not received,
staff will recommend rejecting all bids. at the July 1, 2010 Board meeting and re-
bidding next year. Staff is developing the scopes of work for the initial
engineering work on the seismic improvements and is planning to bring the
contracts back to the Board at the July 15, 2010 Board meeting.
COMMITTEE ACTION: Received the updates.
*5. Review of selected closed-out Capital,Projects
Staff provided a review of all projects over $1 million in expenditures, as well as a
number of other projects of interest (attached). Those reviewed included the
following:
• Aeration Air Renovations Phase 2
• Auxiliary Boiler Improvements
• Piping Renovations Phase 4
• Control System Improvements
• Sewer TV Inspection Program
• South Orinda Renovations Phase 4
• Lafayette Renovations Phase 6
• A-Line Phase 2A
• Northern Pumping Stations Upgrades
• Collection System Master.Plan
The close out position papers will be brought to the Board at the June 17, 2010
Board meeting.
COMMITTEE ACTION: Reviewed selected closed-out projects.
6. Adjournment - at 4:50 p.m.
r
Sewer Rehabilitation
Benchmark Study
Board Capital Projects Committee Meeting
June 2, 2010
Agenda
• Past Renovation Rates
• Planned Renovation Rates
• SSO Rates
• Enforcement Actions
• Conclusions
3.
1
Percentage of System Renewed in Last 25 Years
Llnlon San Dlstrlct -
Iamalpah CSD ,j
Str.'r Shcl DIStI'iCt
tin~.laulnltuAlraSO
1 lark County bVRD t.. i,• of 1, •.h•nl Rrnr•.•. r~l
(itv of Santa Rosa ~ ~~
Uty of San L>ieV,u
('lTy of Oakleud
Clty of Lus Angrles -
City of Fullerton
City of 8rlkrlry
City of Antiudt ~ li
CCCSD
0°~-~ .10"• 20`+~ 30~H d(7:: SO`v~ 60tt~ 70`ti
Percentage of System Planned for Renewal in Next 10 Years
I Inion San Di~. trir t ~ i
{
1 amalpai'. CtiD
Stegr San Dlstrltt
Sar rmnr. nto AI ra SD
Clark (orally WRD ~ ^4 of System Renewed
City of Santa Rosa
City of San Dle~o
illy of Oaklanrl ~
(ity of I ns ~nprlrs
I
City ~f Fullrtton I
Cib, of Berkriry
CityufAntiorh
i1.i1D ~
2
T
SSO Rates by Agency
at; _ ,
SA;IO 2008 ~ ae I
~ ~D
SASO 2000 ~ CA ~
-lhion San Dislrkt
g 25 _ _ _ _.____ _
Sacramento Area SD
d
~ ` 20 ~dty of Antioch
O
N ~ dry of Santa Fbsa
N
~ ~ 15
- i
-dty of Fu9erton
E d dry of Los Angeles
Z ~ I ~! - - ~ Si
S
LL
t
t
m
~
C ege
an
s
rc
dty of Berkeley
_._ . __..... _.
~
I
Q \.
\ my of Oakland
.
~~ ~,~.,~, t.ry of San Diego
0
?OU~+ JL'pa 2005 20O(i 2UOi 2008 2009 L,nNlpars CSD
late aoo9 oma rrom ravos
Agencies with Enforcement Actions
Requiring Specific Renewal Rate
• City of LA -Settlement Agreement with EPA,
RWQCB, and Baykeeper - 0.92%/year
• City of Oakland -Cease and Desist -
1.45%/year
• City of San Diego -EPA Consent Decree -
0.69%/year
• CCCSD Planned Renewal Rate - 0.4%/year
3
Staff Conclusions
• Our past and planned renovation rates are
not as aggressive as other agencies
• Our SSO rate is at the top of the main pack
but well below the worst performers
• Agencies with enforcement actions have
planned renovation rates over three times our
planned rate
• We should not reduce our planned renovation
rate
T
4
4.
Dry/Wet Weather Bypass Improvements
DP 7241
• Project Description: Provide offsite discharges to Walnut Creek during the
extreme wet weather events and/or during the maintenance of the ouffall in the
summer.
• Received fourteen bids on May 19, 2010
• Low apparent bidder is Siteworks Construction, Inc.
• Received a letter of protest from Gordon N. Ball, Inc. on May 25, 2010
o Claimed low bidder did not list electrical subcontractor
o Low bidder is self-performing the electrical work, therefore reject protest
• Waiting for the U.S. Army Corps of Engineers, Sacramento District, Operations
Section to provide approval to the Flood Control District so CCCSD can be given
the encroachment permit
o As of today (June 2, 2010) have not received approval letter/permit from
Flood Control DistricUUS Army Corps of Engineers (Sacramento)
o Approval letter needs to be received by June 10th. Without an approval
letter, staff would ask for Board to reject all bids
N:\TREATPLANT\0001 -Capital Improvements Budget\CIB 09-10\Projects Status.doc
~~
Projects Completed/Closed out
in FY 2009-10
Board Capital Projects Committee
Workshop
June 2, 2010
Total 2009-10 Closed/Completed
Projects by Program
~~
Program Total Expenditures
Treatment Plant $8,061,800
Collection System* $46,156,500
General Improvements $1,044,500
Recycled Water $492,800
Total $55,755,600
* Includes reimbursement from Concord for city's portion of A-line Project
Treatment Plant Program
> $1 million
Treatment Plant Program
< $1 million
Project Title Total Expenditures
Aeration Air Renovations, $1,839,200
Phase 2
Piping Renovations, Phase $1,177,000
4
Plant Control S stem
Improvements $2,761,000
Project Title Total Expenditures
Auxiliary Boiler Improvements $674,500
Control Room Modifications $732,000
Electrical Renovations $172,100
Final Effluent Flow Meter $48,200
Headworks/Mech Shop Roof $248,400
Primary Effluent Pumps
Refurbishment $11,300
2
Treatment Plant Program
< $1 million
Project Title Total Expenditures
Treatment Plant Hydraulic
Profile $253,000
Treatment Plant Site Planning $141 800
Selector Channel Condition
Assessment $3,300
Bac
Collection System Program
> $1 million
Project Title Total Expenditures
A-Line. Ph 2A $23,800,000
TV Inspection Program $6,879,000
South Orinda Renovations. Ph 4 $2,378,700
Lafavette Renovations, Ph 5 $1,976,400
Lafavette Renovations, Ph 6 $2,374,000
Martinez Sewer Renovations, Ph 2 $2,067,000
2009-10 Development Sewerage $1,126,500
Northern Pumping Station
Upgrades $1,341,000
Collection System Program
< $1 million
Project Title Total Expenditures
2006 Storm Damage Assessment $499,300
Danville Sewer Renovations, Ph 2 $248,600
Pleasant Hill Renovations, Ph 1 $617,000
Collection System Planning & Flow
Monitoring $597,000
Lafayette/Moraga Storm Drain Risk
Assessment $16,200
Collection System Master Plan
Update $455,400
Collection System Program
< $1 million
Rac
Project Title Total Expenditures
Pump Station Master Plan Update $71,300
Treat Blvd. Bridge Sewer
Relocations $11,800
Miner Road Orinda, TR 02-200 - $634,900
Walnut Creek Downtown
Predesign $37,000
Pumping Station Corrosion $430,000
San Ramon PS Upgrades $33,600
4
General Improvements Program
Project Title Total Expenditures
ADA Improvements $393,100
CSO Welding Shop
Modifications $39,900
GDI Follow On Applications $36,500
Vehicles and Equipment
Acquisition $56,000
Capital Legal Services
Back $519,000
Recycled Water Program
Project Title Total Expenditures
Grayson Creek REW
Repair $493,000
Aeration Air Renovations -
Phase 2
Project Purpose:
Repair air leaks in basin plenums and
stabilize base rock
Scope of Work:
• Inject polyurethane grout beneath basins
• Coat air plenums
• Replace air header actuators
• Replaced miscellaneous air diffuser
equipment
Aeration Air Renovations -Phase 2
Financial Summary
• Construction Contract $1,823,101
- (F.D. Thomas, Inc.)
• Change Orders (-12.7%) ($231,043)
• Total Construction $1,592,058
• Engr, CM, Admin (14.6%) $247,142
• Total Expenditure ~ $1,839,200
Total Project Cost for Phase t - $2,435,200
6
Location
I~ Map
C,~C~®
U"'~~ PROJECT
e AREA
~~ ~,
i'
~~
~o ~~~~ /
oU ~ ~~~ ~
~- J
J
~z ,:
.,M ~
a` a a,.
^'m'.?~aI
^
*~"8
8
Auxiliary Boiler Improvements
Project Purpose:
Improve reliability and efficiency of boilers
Scope of Work:
• New boiler control system
• New insulation
• Repair shell door
• New emissions monitoring system
Auxiliary Boiler Improvements
Financial Summary
• Construction Contract $325,897
- (R.F. McDonald)
• Change Orders (14.3%) $54,276
• Total Construction $380,173
• Engr, CM, Admin (43.6%) $294,371
• Total Expenditure$674,500
9
' ~ \~U~ ~ Location
u
PROJECT ,~i Map
Op SITE /,~
i~
~/
~~ O ~~ vr°, ii i~
\\U ii ~ i
d ~%
~ ~ ~
~^` ~/ ~/
/~/
~ ~ ~ / iJ
_ 4
////~~\\\\ m ~. ~~
t %/
i~ ~~
II 11 /
l~
Piping Renovations -Phase 4
Project Purpose:
Replace process piping for operational reliability and
safety
Scope of Work:
• Replace Return Activated Sludge (RAS) Piping
• Replace ash piping system in the SCB
• Secondary scum electrical conductors
• Replace six influent channel slide gates at the UV
facility
Piping Renovations -Phase 4
Financial Summary
• Construction Contract $810,000
• Change Orders (3.9%) $31,984
• Total Construction $841,984
• Engr, CM, Admin (39.8%) $335,112
• Total Expenditure ~ $1,177,000
tt
~ ~ ~ - Location
S,N ~~~\` ~ ... Map
9~ souos `~
CON~1-ONINC
BmL01NG ' ]\~ ~~ iurvNELS
~f -NOFrR sourN ~.f~ '~
CLMIFIERS CLMIFIERS +IL~
I~\,. , ~1 ~4~'~ ~,
o n,
~~ ~ , ,
~ ,." ~~ d~~j ~ i ,
.,,
RAS. PUMP ~tlf ~ ~
SLAiI(1N ~ ~ J ~ l~
OV FACIL~IY ~~ 3 i _/
12
Plant Control System
Improvements
Project Purpose:
Replace treatment plant computer
control system
Scope of Work:
New control system, new servers,
interface, and data storage.
13
Plant Control System Improvements
Financial Summary
• Construction Contract $1,286,000
-(Transdyn)
• Change Orders (5.4%) $69,040
• Hardware $273,320
• Total Construction $1,628,360
• Engr, CM, Admin (69.6%) $1,132,973
• Total Expenditure $2,761,000
14
Rack
A-Line Relief Interceptor Phase 2A
Project Purpose:
• Joint project with the City of Concord
• Provide additional wet weather capacity to the A-Line
Interceptor
• Provide the City of Concord with a reliable gravity
inter-tie to replace their deteriorating forcemain
Scope of Work:
• Install approx. 4,600 LF of 48, 72 and 96-inch PVC
lined reinforced concrete pipe using tunneling
technology and traditional trench excavation and
backfill method
15
A-Line Relief Interceptor Phase 2A
Financial Summary
• Construction Contract
(Mountain Cascade, Inc.)
• Change Orders (17) -0%
• Total Construction
• Right of Way (-1 %)
• Engr, CM, Admin (14.2%)
Total Expenditure
Concord Reimbursement
$ 20,650,750
$ (52)
$ 20,650,698
$ 213,500
$ 2,935,800
-$ 23,800,000
$ 7,909,095
Site Map
A-Line Relief Interceptor Phase 2A
16
17
Site Map
A-Line Relief Interceptor Phase 2A
~E.
q
18
19
A-Line Relief Interceptor Phase 2A
Crossing Walnut Creek & Venturi Meter
Sewer TV Inspection Program
Project Purpose:
• Inspect sewers and develop a
comprehensive assessment of the
collection system.
Scope of Work:
• Multi-year effort to inspect the entire
collection system.
Zo
Sewer TV Inspection Program
Financial Summary
• Construction Contract $6,101,544
- (Roto Rooter)
• Engr, CM, Admin (22.5%) $1,339,246
• Total Expenditure$7,440,800
21
South Orinda Renovations Phase 4
Project Purpose:
Replace/Renovate deteriorating and
high maintenance sewer lines
Scope of Work:
Replacement/Repair of 11,500 linear
feet of 8- and 10-inch sewer lines by
open-cut, pipe burst, and horizontal
directional drilling in easements and
public right of way.
South Orinda Renovations Phase 4
Financial Summary
• Construction Contract $1,124,281
(McNamara 8 Smallman Construction Inc.)
• Change Orders (6.7%) $75,036
• Total Construction $1,199,317
• Right-of-Way (34.3%) $411,695
• Engr, CM, Admin (63.9%) $767,653
• Total Expenditure$2,378,665
22
Typical Sewer Construction
23
Lafayette 5 Renovations
Project Purpose:
Replace/renovate deteriorating/high
maintenance sewer lines
Scope of Work:
• Reconstruct 14,000 feet of 8- to 15-inch
sewers in Lafayette and Moraga
• Repair sewer in City of Pleasant Hill and
replace creek crossing in Lafayette
24
Lafayette 5 Renovations
Financial Summary
• Construction Contract
- (K.J. Woods Construction, Inc.)
• Change Orders (21 %)
• Total Construction
• Right-of-Way (6%)
• Engr, CM, Admin (27%
• Total Expenditure
$1,238,000
$ 263,079
$1,501,079
$ 93,111
1 $ 400,844
$1,976,000
zs
26
Lafayette Renovations Ph 6
Project Purpose:
Replace/Renovate deteriorating and
high maintenance sewer lines
Scope of Work:
Reconstruct 13,000 linear feet of 8- and
12-inch sewers in Lafayette and Orinda
Lafayette Renovations Ph 6
Financial Summary
• Construction Contract $1,314,125
(Precision Engineering, Inc.)
• Change Orders (13%) $171,373
• Total Construction $1,485,498
• Right-of-Way (12.3%) $182,222
• Survey (9.9%) $147,459
• Engr, CM, Admin (37.6%) $558,332
• Total Expenditure$2,374,000
a~
Night Construction
N:~o
as
Martinez 2 Renovations
Protect Purpose:
Replace/renovate deteriorating/high
maintenance sewer lines
Scope of Work:
• Reconstruct 6,000 feet of 6-inch sewers
in Martinez
Martinez 2 Renovations
Financial Summary
• Construction Contract
- (William G. McCullough Co.)
• Change Orders (2.4%)
• Total Construction
• Right-of-Way (11.5%)
• Enc1r, CM, Admin (34.6%
• Total Expenditure
$1,379,595
$ 32,697
$1.,412,929
$ 162,494
1 $ 492,054
~~ $2,067,000
29
30
Northern Pumping Stations
Upgrades
Project Purpose:
Renovate and improve deteriorating and high
maintenance pumping station systems.
Scope of Work:
• Renovate Concord Industrial, Clyde,.
Martinez, and Orinda Crossroads Pumping
Stations.
• Install new grinder at Concord Industrial.
Northern Pumping Stations Upgrades
Financial Summary
• Construction Contract $619,000
- (California Trenchless, Inc.)
• SCADA Programming $27,659
• Change Orders (3.5%) $21,675
• Total Construction $668,334
• Engr, CM, Admin (93%) $620,087
• POD Support (8%) $52,579
• Total Expenditure $1,341,000
31
32
Northern Pumping Stations Upgrades
Grayson Creek REW Repair
Project Purpose:
An emergency repair project to the REW
pipeline on Grayson Creek
Scope of Work:
Pipeline section replaced on the northern side
of the Grayson Creek Bridge on Imhoff Drive.
The pipeline support system located under
the bridge deck had failed and the pipe fell
into the creek channel.
Grayson Creek REW Repair
Financial Summary
• Construction Contract $319,000
• Engr, CM, Admin (54.9%) $174,000
• Total Expenditure $493,000
33
Grayson Creek REW Repair
34
Thank You for Your Time
Questions?