HomeMy WebLinkAboutACTION SUMMARY 10-06-88Central Contra Costa Sanitary Dist
~..
BOARD MEETING
=~~ .
ACTION SUMMARY
October 6, 1988
I. ROLL CALL:
II. PUBLIC COMMENTS:
III. APPROVAL OF MINUTES:
1. Minutes of September 1, 1988
2. Minutes of September 8, 1988
3. Minutes of September 15, 1988
4. Minutes of September 27, 1988
IV. BIDS AND AWARDS:
1. Reject all bids for designing,
furnishing, and installing a
telemetry system for the Dis-
trict's fourteen (14) pump
stations to transmit data to
the Treatment Plant Mainframe
Computer Room; Bid Request
T0049P
V. CONSENT CALENDAR:
Staff recommends the following:
1. Resolution No. 88-123 accepting
an easement at no cost to the
District from GEORGE W. KASTEN,
et ux, Orinda area (Job 4532 -
Parcel 2)
2. Resolution No. 88-124 accepting
an easement at no cost to the
District from RUSSELL ALLAN
ABRAHAM, et ux, Orinda area
(Job 4532 - Parcel 3)
3. Resolution No. 88-125 accepting
an easement at no cost to the
District from JACK A. SUNSERI and
MARIAN L. TIM, Orinda area (Job
4543 - Parcel 1)
BOARD OF DIRECTORS:
' SUSAN McNULTY RAINEV
President
PARKE L. BONEYSTEELE
NELS E CARLSON
JOHN 8. CLAUSEN
WILLIAM C. DALTON
Present: Mbrs. Boneysteele, Dalton,
Clausen, Carlson, Rainey
Absent: None
None
Approved as presented
Approved as presented
Approved as presented
Approved as presented
Rejected all bids
Consent Items 1 through 14 approved
as recommended, resolutions adopted
as appropriate, and recordings duly
authorized
4. Resolution No. 88-126 accepting an
easement at no cost to the District
from TRANS-BAY BUILDERS, INC., Orinda
area (Job 4543 - Parcel 4)
5. Resolution No. 88-127 accepting an
easement at no cost to the District
from RUSSELL ALLAN ABRAHAM, et ux,
Orinda area (Job 4543 - Parcel 10)
6. Resolution No. 88-128 accepting an
easement at no cost to the District
from the ESTATE OF MILTON A. WRIGHT,
Orinda area (Job 4543 - Parcel 14)
7. Resolution No. 88-129 accepting an
easement at no cost to the District
from LOIS L. HANSON, a.k.a. LOIS L.
WILDER, Walnut Creek area (Job 4556
- Parcel 1)
8. Resolution No. 88-130 authorizing the
execution of a Consent to Dedication
to Contra Costa County (Job 1627 -
Parcel 2) Sub 7062 (Alamo area)
9. Authorization for P.A. 88-18 (Orinda),
P.A. 88-19 (Alamo), P.A. 88-20 (Dan-
ville), and P.A. 88-21 (Alamo) to be
included in a future formal annexa-
tion to the District
10. Resolution No. 88-131 initiating
proceedings to formally annex 10
separate areas under the title of
District Annexation 106
11. Establish November 3, 1988, at 3:00
pm as the date and time for a public
hearing on Annexation 104 as amended
by the Local Agency Formation Com-
mission (LAFCO)
12. Accept the contract work for Schedule-
A, San Ramon Valley Interceptor Sewer
Project (D.P. 4224A) and authorize the
filing of the Notice of Completion
13. Accept the contract work for the Out-
fall Rehabilitation Phase II Project
(D.P. 20056) and authorize the filing
of the Notice of Completion
14. Receive results of election of Manage-
ment Support/Confidential Group Officers
for 1988-1989
2
CALL FOR REQUESTS TO CONSIDER ITEMS OUT
OF ORDER
VI. ADMINISTRATIVE:
Item Nos. X. 1 and 3, Solid Waste,
and XIV., Closed Session, were taken
out of order to accommodate interested
persons in the audience
1. Consider adoption of revised District Modified instructions on speaker card;
Board meeting procedures and initia- adopted Resolution No. 88-132 as
tion of speaker's card system recommended
VII. ENGINEERING:
1. Authorize the General Manager-Chief
Engineer to execute an agreement
with East Bay Municipal Utility
District for relocation of 10-inch
water main for the Diablo Road
Sewer Improvements Project, DP 4455
Approved as recommended
2. Order completion of District Annexa-
tion 103 (Acme Transfer Station
Annexation)
Approved as recommended; adopted
Resolution No. 88-133
VIII. APPROVAL OF EXPENDITURES:
1. Expenditure List dated October 6,
1988
Approved as recommended
IX. PERSONNEL:
1. Receive and adopt salary survey
results modifying salary ranges
for six positions
Approved as recommended
X. SOLID WASTE:
1. Receive presentation of a recycling Received presentation; set public
plan proposed by Valley Waste Manage- hearing for PJovember 3, 1988; and
ment for Franchise Zones 2, 4 and 5 authorized staff to meet with Valley
Waste Management
2. Authorize the General Manager-Chief Dropped item from consideration at
Engineer to enter into a professional this time
engineering services agreement with
HDR Engineering, Inc. for Feasibility
Study of a Transfer Station
3. Breach of contract appeal by Pleasant Continued to October 20, 1988, at the
Hill Bay Shore Disposal and Orinda- request of Mr. Ken Little, attorney
Moraga Disposal Service, Inc. for the disposal companies
XI. EMERGENCY SITUATIONS REQUIRING BOARD None
ACTION:
3
•
XII. REPORTS:
General Manager-Chief Engineer a.
b.
c.
d.
e.
f.
9•
Status report of North Concord
Annexation
There will be a Board workshop,
tour of the Martinez pumping
station, and demonstration by
CSO at 3:00 p.m. on Tuesday,
October 11, 1988
TWA status presented; a meeting
with the Board Committee and TWA
representatives has been scheduled
for 11:30 on October 20, 1988 in
Walnut Creek
Status report of Water Reclamation;
a joint Board meeting will be
scheduled with Contra Costa Water
District
Status of ash disposal options
presented
Announcement concerning lost time
accident
Announcement concerning paper on
the Outfall Project presented by
Dave Williams, Engineering Division
Manager, at the WPCF conference in
Dallas
2. Counsel for the District Mr. Hazard announced that he may be
unable to attend the October 20, 1988
Board meeting; Mr. Alm will attend in
his place
3. Secretary of the District None
4. Board Members Reports of solid waste meetings and
issues
XIII. ANNOUNCEMENTS: None
XIV. CLOSED SESSION: 4:02 p.m. to 4:33 p.m. to discuss
litigation pursuant to Government
Code Section 54956.9(a)
XV. ACTIONS RESULTING FROM DISCUSSIONS IN None
CLOSED SESSION:
XVI. ADJOURNMENT: Adjourned at 5:55 p.m. to reconvene
at 3:00 p.m. on Tuesday, October 11,
1988, for a Board workshop on pumping
stations and CSO activities and a tour
of the Martinez Pumping Station and
a demonstration by CSO
4