CAPITAL PROJECTS COMMITTEE
ACTION SUMMARY
Chair Hockett
Member McGill
Wednesday, September 5,2007
3:00 p.m.
Third Floor Executive Conference Room
Central Contra Costa Sanitary District
5019 Imhoff Place, Martinez, CA
PRESENT: Barbara Hockett, Michael McGill, Jim Kelly, Ann Farrell, Dr. Gail Chesler,
Earlene Millier
1. CALL MEETING TO ORDER
Chair Hockett called the meeting to order at 3 p.m.
2. PUBLIC COMMENTS
None.
3. REVIEW RECYCLED WATER PROGRAM - Ann Farrell
The Committee discussed the status of the recycled water portion of the A-line project.
The project is out to bid and the recycled water line is still included but is a separate bid
item that can either be awarded at a later date or not awarded at all. In the meantime,
staff is evaluating the cost of the additional cross connection protection that Contra
Costa Water District is requiring and the impact on the cost effectiveness of the recycled
water line extension and will be developing some options for the Committee to consider
in early October. There was also some general discussion of the recycled water
program and suggestions for items to be included on the agenda for the Recycled
Water Committee meeting in October.
ft
to;>> Recycled Paper
Capital Projects Committee
September 5, 2007
- Page 2 -
4. PREVIEW OF FY 2006-07 CAPITAL IMPROVEMENT YEAR END REPORT-
Ann Farrell
Ms. Farrell discussed the revenue and expenditures for the FY 2006-07 Capital
Program. The expenditures were approximately $39.6 million and revenues $36.3
million resulting in a draw down of the capital fund of approximately $ 3 million to a
balance of approximately $52.5 million. The Committee noted that there are a
number of large projects that will need to be funded in the upcoming years and the
fund balance will be helpful in minimizing the need for bond financing.
5. PREVIEW OF POSITION PAPER RE: NEED FOR ADDITIONAL
AUTHORIZATION FOR FY 2007-08 GENERAL IMPROVEMENT PROGRAM
/EXPLANATION OF CIB AUTHORIZATION/ALLOCATION PROCESS - Dr.
Gail Chesler
Dr. Chesler reviewed the process for developing the Board authorization needed for
the Capital Program. Estimates of allocations that will be carried over from one
fiscal year to the next are made approximately six months in advance of the end of
the current fiscal year. If these estimates are not correct, the amount authorized by
the Board for the following fiscal year may not be sufficient and a correction to the
authorization amount may be necessary. In this case, we have an immediate need
to add authorized funds to the General Improvements Program to allow planned FY
2007 -08 expenditures to occur. The Committee will review the authorization process
at a future Committee meeting to determine if a new procedure should be adopted to
correct for actual carryover each year when the period 13 financials are available
and thus avoid the need for additional authorizations during the year.
COMMITTEE ACTION: Recommended approval of the Position Paper by the
full Board.
6. CSO UPDATE
Ms. Farrell reviewed the schedule for the improvements at the Collection Systems
Operations site and noted that the Draft Mitigated Negative Declaration will be
available for distribution to the Board and the public by the end of September. The
City of Walnut Creek staff has been involved in the development of the document
and will receive an Administrative Draft for comment prior to the document being
released to the public. A position paper to set the public hearing for the document is
planned for the October 4 Board meeting and the public hearing itself is planned for
the November 15 Board meeting.
7. ADJOURNMENT - at 4:30 p.m.