HomeMy WebLinkAboutAGENDA BACKUP 07-02-81
<c(sD
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
NO.
1 - ~-'?J
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
July 1, 1981
SUBJECT
TYPE OF ACTION
JOHN J. CARNIATO lAW OfFICE, JUNE 26, 1981 BilliNGS
Li t i ga t ion
SUBMITTED BY
D. G. Ni les
INITIATING DEPT./DIV.
Deputy General Manager
Issue: John J. Carniato law office, June 26, 1981, billings.
Background: The John J. Carniato, June 26, 1981, bill ings are for professional
services relative to the following matters from March 21, 1981, through June 25,
1981. Included in this bill ing are three new cases:
Current Cases
Fees Cost Bill ing
Acme Fi 11 Corp. (condemnation) $ 75.00 $ 75.00
Acme Fi 11 Corp. (damage) 1 ,050.00 $ 141.. 1 5 1,194.15
Fred J. Ea r 1 y Jr. Co. vs. C.C.C.S.D. 1,195.50 1,195.50
East Bay Municipal Utility District 88.00 88.00
Ka i se r Industries vs. C.C.C.S.D. 161.00 47.00 208.00
King vs. C.C.C.S.D. 92.50 92.50
McEvoy vs. C.C.C.S.D. 114.00
Peterson Simpson vs. C.C.C.S.D. 2,081.00 15.00 2,096.00
Contra Costa County Water Dist./Alum 750.00 750.00
D. W. Young Construction Company 225.00 225.00
Total, Current Cases $5,832.00 $206.15 $5,924.15
New Cases
Fees Cost Bill i ng
Altech-Keenan vs. C.C.C.S.D. $185.00 $185.00
Great American Homes vs. C.C.C.S.D. 75.00 75.00
lin vs. C.C.C.S.D. 110.00 110.00
Tota 1, New Cases $370.00 $370.00
General Matters $55.00 $ 55.00
Recommendation: Board approval of bill ings for current cases and review of new
cases in Executive Session with District counsel for inclusion in professional
services bi 11 ings.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
/(). 0.
DGN
INITIATING DEPT./DIV.
ra San
BOARD OF DIRECTORS
NO. ~ __ if- _~ }
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
July 2, 1981
SUBJECT
A~JARD OF CONTRACT FOR DISTRICT PROJECT 3431, REPAIRS T
MARTINEZ & LOWER ORINDA PUMP STATtONS, GROUP I REPAtRS
AND AUTHORIZE $64,710 FOR PROJECT COMPLETION
TYPE OF ACTION
AWARD & AUTHORIZE FUNDS
Jay S. McCoy
INITIATING DEPT./DIV.
Collection System Engineering
SUBMITTED BY
BACKGROUND: On May 15, 1981 the Board authorized staff to advertise for
bids for subject project. Bids were received July 1, 1981, and are
summarized on the attached tabulation.
The low bid by Monterey Mecahnical Co. is $49,710.00, 118% of the
Engineers estimate.
The Engineers estimate, prepared by our consultant Waste & Water
International, and the bid prices are anaylzed on the attached WWI
letter.
The post bid, preconstruction cost estimate (attached) is $74,710.00.
An authorization of $64,710.00 is necessary to complete project.
RECOMMENDATION: Award contract to Monterey Mechanical Co. and authorize
$64,710.00 for project completion.
Attachment
REVIEWED AND RECOMMENDED FOR BOARD ACTION
e~ CLW
POST BID - PRECONSTRUCTION ESTIMATE OF COSTS
FOR
DISTRICT SEWERING PROJECT 3431
ITEM
DESCRIPTION
ITEM AMOUNT
1.
Construction Contract (As Bid) .
2.
Estimated Construction Contingencies
3. Estimated Construction Incidentals to Project Completion
Survey. . . $ 0
Inspection . $ 4,500.00
Engineering . $ ~. 000.00
Total Estimated Construction Incidentals
. $ 7,500.00
4.
Street Resurfacing or Seal Coat
. . . . . . . . . . $
5.
Total Estimate Required to Complete Project
6.
Pre Bid Expenditures (Group I contract only)
Survey, Engineering, Printing, Advertising
Specia I Services
Right-ot-Way Acquisition. .
. $ 1 0, 000. 00
. $
.$ 0
7.
Total Preconstruct ion Incidentals (as ot 6-1-81 ). . $ 10,000.00
8.
Total Estimated Project Cost
(Items 5 & 7)
. . . . . . . . . . . . .
TOTAL
. $ 49,710.00
. . . $
7,500.00
$7,500.00
o
. $64.710.00
$10,000.00
. $74,710.00
9. Funds Previously Authorized ($6.7, aOO tota 1. p roj .). G.ro\.lP. 6111 Y' $ 10,000
10.
Total Additional Funds Required to Complete Project.
(Item 8 minus Item 9)
. . . . . $ 64,71 0.00
% CONST.
CONTRACT
100%
15%
15%
2050-8-78
CENTr .L CONTRA COSTA /ANITARY DISTRICT
JOB
District Project
DATE July 2, 1981
LOCATION 'Martinez & Orinda ENGR. EST $42.220.00
B I DDE R
NAME BID PRICE
ADDRESS
PHONE
Monterey'Mec'han i tal $49,710.00
8275 San Leandro S~reet
Oa k 1 and, CA 94521
K.G. Walters Construction Co. Inc. $56,298.00
P.O. Box 4359
Santa Rosa, CA 95402
.'
;>..... ,--.,':
,
:, ~. ,.
-
JOB BY DATE____
CHKD.BY
DATE:
SHEET NO.
OF_
D
Centra.. ';ontra Costa San ita,
BOARD OF DIRECTORS
District
NO.
VII 1. 2
7/2/81
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
June 30,1981
SUBJECT
POSITION PAPER
TYPE OF ACT ION
SUBMITTED BY
AUTHORIZE SUPPLEMENTAL FUNDS IN THE AMOUNT OF
$367,000 FOR CAPITAL PROJECTS - SUMMARY
PPROVAL OF ADDITIONAL
FUNDS
Clark L. Weddle
INITIATING DEPT./DIV.
Engineering
BACKGROUND: Several projects have exceeded the budgeted amounts and
some need additional authorization of expenditures to continue work
required by staff. Attached is a summary of authorizations requested,
followed by a position paper explaining each authorization request.
RECOMMENDATION:
1. Authorize $165,000 in supplemental funds for treatment plant
construction - Stage 5A - Phase I. ,
2. Authorize $83,100 in supplemental funds for treatment plant
construction - Stage 5B - Phase I.
3. Authorize $15,900 in supplemental funds for the influent
sampler installation, Project 3346.
4. Authorize $17,000 in supplemental for Project 3474, Treatment
Plant North Parking Lot.
5. Approve $5,000 budget for contract preparation. obtaining
funding agency approval, and bid advertisement for the emergency
___________ __ _ power system.
6. Authorize an additional $70,000 for chlorination F9cility
Improvements, Project 5B-I. I
7. Authorize $11,000 in supplemental funds for the Alternative
Disinfection Study, Project 52000.719.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INITIATING D:"\T./_D~~.
~.~LW
:l>-i
c 0
-<I> -<I> rtrt
\.0 N N :::r0.l
C> V1 .I:- 0' \,J.J \.0 0 -
\,J.J W V1 C> ex> V1 C> ""l
W C> 0 -....J .I:- 0 N
ex> 0 0 0 0 0 ex> 0 0.1
N 0 0 0 0 0 N 0 rt
0
:J
<((sD
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
NO.
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
July 26. 1981
SUBJECT AUTHORIZE $165,000 IN SUPPLEMENTAL FUNDS FOR
TREATMENT PLANT CONSTRUCTION - STAGE 5A PHASE I
TYPE OF ACTION
SUBMITTED BY
John Larson, Special Projects Engineering Division
BACKGROUND
In November 1979. the Board authorized funds in the amount of $125,000
to cover work on the project by District staff. The work that has been
accomplished since that time includes consultant procurement and review and
coordination of the Metcalf & Eddy Task A work. Supplemental funds in the
amount of $45.000 are necessary at this time to cover prior expenditures
associated with this project through June 30, 1981.
An additional $120,000 is necessary to cover future District staff
work in conjunction with grant administration, completion of current
engineering studies and design work. and approval of final plans and
specifications by SWRCB. This work is planned for completion in April 1982.
The total authorization of supplemental funds requested is $165,000.
This work will be partially reimbursable under the Clean Water Grant Program.
RECOMMENDA TI ON
Authorize the expenditure of $165,000 of Sewer Construction Funds to
cover District Staff work on treatment plant construction - Stage 5A Phase I.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
EN. MGR./CHIEF ENG.
JAL ~~ CLW
SHEET OF
t((SD
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
NO.
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
June 26. 1981
SUBJECT
AUTHORIZE $15.900 IN SUPPLEMENTAL FUNDS FOR THE
INFLUENT SAMPLER INSTALLATION. PROJECT 3346
TYPE OF ACTION
AUTHORIZE FUNDS
SUBMITTED BJohn Larson. Special Projects Engineering Division
BACKGROUND
The original design for the influent and primary effluent samplers
was accomplished by the Engineering Department. In an attempt to minimize
cost. the original influent sample pump was reused in the new location.
Since the installation was completed in Summer 1980. the level of
operator attention to maintain operation has been excessive. Interim
modifications were made at a cost of $6.000 over the original authoriza-
tion with partial success. It now appears that the reused sample pump
and some of the piping will have to be replaced at an additional cost
of $9.900. This work will be completed during July 1981.
RECOMMENDATION
Authorize the expenditure of $15.900 of sewer construction funds to
supplement funds for the influent sampler installation. Project 3346.
REVIEWED AND RECOMMENDED FOR BOARD ACT/ON
OF
JAL
~CLW
<((sD
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
NO.
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
June 26, 1981
SUBJECT AUTHORIZE $83,100 IN SUPPLEMENTAL ~UNDS FOR TREATMENT
PLANT CONSTRUCTION - STAGE 5B PHASE I
TYPE OF ACTION
SUBMITT~DIiBY L S' 1 P . t E' . D'"
vO n arson, pecla rOJec s nglneerlng lV1Slon
BAC KGROUND
In April 1976, the Board authorized funds in the amount of $56,082 to
cover work on the project by the District Staff. The work that has been
accomplished since that time includes the review and coordination of the
Stage 5B Phase I design by Brown and Caldwell, review and appeal of grant
eligibility decisions by SWRCB, subsequent consultant procurement (Metcalf
& Eddy), and review and coordination of the Metcalf & Eddy Task B work
(this includes prepurchase of the electric motor driven aeration blower).
Supplemental funds in the amount of $68,100 are necessary at this time
to cover prior expenditures associated with this project through June 30,
1981 .
An additional $15,000 is necessary to cover future District staff work
in conjunction with grant administration, completion of the aeration blower
design, and completion of the Task I-B Report (this report summarizes the
Brown and Caldwell work that can be used for the next capacity expansion).
The total authorization of supplemental funds requested is $83,100.
This work may be partially reimbursable under the Clean Water Construction
Grant Program.
RECOMMENDATION
Authorize the expenditure of $83,100 of sewer construction funds to
cover District Staff work on Treatment Plant Construction - Stage 58
Phase I.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
JAL C~ CLW
OF
Cent
BOARD OF DIRECTORS
NO.
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
June 26, 1981
SUBJECT
AUTHORIZE $17,000 IN SUPPLEMENTAL FUNDS FOR PROJECT
3474, TREATMENT PLANT NORTH PARKING LOT
TYPE OF ACTION
SUBMITTED BY
Jay S. McCoy
INITIATING DEPT.!DIV.
Collection/Engineering System
ISSUE: The incidental account for the Parking Lot Project is over-
expended.
BACKGROUND: In estab1 ishing the funds for Project 3474, an error was
made in calculating the amount of money which was expended on pre-
construction incidentals. This error resulted in an lnsufficient
authorization of funds. It is appropriate to augment existing funds
by $17,000.
RECOMMENDATION: Authorize $17,000 in supplemental funds for project
3474, Treatment Plant North Parking Lot.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
JSM
~~
CL
ENG.
. <c(sD
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
NO.
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
SUBJECT
June 17, 1981
TYPE OF ACTION
AUTHORIZATION OF $5,000 FOR PREPARATION OF CONTRACT
AND PUBLIC ADVERTISING, PROJECT 3525, EMERGENCY
POWER SYSTEM
BUDGET APPROVAL
K. Barker
SUBMITTED BY
ISSUE: Budget approval for contract prpeparation, obtaining funding agency
approval, and bid advertising is required on Project No. 3525, Emergency Power
System. The estimated cost for this work is $5,000.
BACKGROUND: The Board authorized preparation of the contract and public
advertisement at the April 23, 1981 meeting. The Position Paper is attached.
Since the estimated cost for the remaining work included construction, no
budget was approved.
When the State Water Resources Control Board has approved the contract, the
Emergency Power System Contract will be advertised.
RECOMMENDATION: Approve $5,000 budget for contract preparation, obtaining
funding agency approval, and bid advertisment.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INITIATING DEPT./DIV.
~c8~.
\:.~
-<((SD
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
N~IV. Engineering
4. 4 23 81
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
April 17, 1981
SUBJECT
TYPE OF ACTION
APPROVE CONTRACT DOCUMENTS AND AUTHORIZE PUBLIC ADVERTISING
FOR BIDS FOR DISTRICT PROJECT NO. 3525
BID AUTHORIZATION
SUBMITTED BY
K. Barker
INITIATING DEPT./DIV.
Engineering/Construction
ISSUE: An emergency power system is required at the Treatment Plant. The
estimated cost for the remaining work is $65,000.
BACKGROUND: The Board has previously recognized the need for an emergency power
supply at the Treatment Plant and has previously authorized the purchase of
a 20.8 KVA electrical transformer. District Project No. 3525 covers the District's
design, construction, and construction management costs for installing the
previously-purchased transformer and making the emergency power system operable.
The work will be performed by an outside contractor selected by competitive bids.
RECOMMENDATION:
1. Approve the Contract Documents.
2. Authorize public advertising of District Project No. 3525.
INITIATING DEPTo/D"Z&.
K. Barker CLW
REVIEWED AND RECOMMENDED FOR BOARD ACTION
BOARD OF DIRECTORS
NO.
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
June 30, 1981
SUBJECT
POSITION PAPER
TYPE OF ACTION
SUBMITTED BY
AUGUMENT FUNDS PREVIOUSLY AUTHORIZED FOR CHLORINATION
FACILITY BY AN ADDITIONAL $66,000
APPROVAL OF ADDITIONAL
FUNDS
INITIATING DEPT./DIV.
K. Barker
Engineering/Construction
ISSUE: $73,100 was previously authorized by the Board for modifications
to the Treatment Plant Chlorination Facility.
BACKGROUND: The construction phase of this project has now been completed
and formally accepted by District. The project incurred cost overruns
over the amount previously authorized, and an additional $70,000 is
required to cover the actual expenditures on this project.
RECOMMENDATION: Authorize an additional $70,000 for the Chlorination
Facility, 5B-I, for a total to date of $143,100.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INITIATING DEPT./DIV.
e~
CLW
k..~~
lt~
<c(sD
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
NO.
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
June 30, 1981
SUBJECT
AUTHORIZE $11,000 IN SUPPLEMENTAL FUNDS FOR THE
ALTERNATIVE DISINFECTION STUDY
TYPE OF ACT ION
AUTHORIZE FUNDS
SUBMITTED BY
John Larson - Special Projects Engineering Division
BACKGROUND
The original authorization for this work was $40,000. An
additional $11,000 is required to supplement the original
authorization. The consultant's scope of work was increased by the
addition of an executive summary, the analysis on one additional
alternative, and by the requirement to obtain more meteorological data.
The increase in the consultant's work accounts for $6,000 while the
remaining $5,000 is needed to cover the cost of work on this project
by District staff.
RECOMMENDATION
Authorize the expenditure of $1 Y,OOO of Sewer Construction
Funds for completion of the project report and to cover District
staff work on the Alternative Disinfection Study.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
~ CLW
SHEET OF
JL
..,...
.
-
San
BOARD OF DIRECTORS
NO.
IV. Hear; ngs: 1 a&B
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
June 26, 1981
SUBJECT
HEARING ON DELINQUENT SEWER SERVICE (EQC) CHARGES AND
ADOPTION OF A RESOLUTION OVERRULING PROTESTS AND ADOPT
ING THE REPORT PURSUANT TO SECTION 5473, HEALTH AND
TYPE OF ACTION
SUBMITTED BY
Jay S. McCoy
INITIATING DEPT./DIV.
Collection/Engineering Systems
BACKGROUND: The District is legally required to conduct a hearing for
the purpose of placing delinquent sewer service charges on the tax
roll for collection. Notices of this hearing were published in the
newspaper and each of the delinquent property owners was notified in
writing of the hearing date. The report containing the names of the
owners who have not paid delinquent sewer service charges is attached.
Considering valid protests, the outstanding charges should be placed on
the tax roll.for collection.
RECOMMENDATION: Adopt resolution overruling protests and adopting the
report pursuant to Section 5473, Health and Safety Code.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INITI T7~DIV. ~
, r JSM CL\-J
~
.
-
BOARD OF DIRECTORS
NO.
IV. Hear; ngs: 1 a&B
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
June 26,1981
SUBJECT
HEARING ON DELINQUENT SEWER SERVfCE (EQC) CHARGES AND
ADOPTION OF A RESOLUTION OVERRULING PROTESTS AND ADOPT
ING THE REPORT PURSUANT TO SECTION 5473, HEALTH AND
TYPE OF ACTION
SUBMITTED BY
Jay S. McCoy
INITIATING DEPT./DIV.
Collection/Engineering Systems
BACKGROUND: The District is legally required to conduct a hearing for
the purpose of placing delinquent sewer service charges on the tax
roll for collection. Notices of this hearing were published in the
newspaper and each of the delinquent property owners was notified in
writing of the hearing date. The report containing the names of the
owners who have not paid del inquent sewer service charges is attached.
Considering valid protests, the outstanding charges should be placed on
the tax roll .for collection.
RECOMMENDATION: Adopt resolution overruling protests and adopting the
report pursuant to Section 5473, Health and Safety Code.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
~
CU.}
;.
a
.a
DELINQUENT ACCOUNTS
SEWER SERVICE CHARGE
The following list of owners are delinquent in payment of previously
invoiced sewer service charges for their respectively listed proper-
ties:
County De 1 i nquent
Assessors No. Owner & Address Property Address Balance Penalty Total
198-061-004 Lorrine McClure 1445 Danvi11e Blvd. $105.00 10% $115.50
Address Unknown Alamo, CA 94507
373-152-003 Allan & Ann DeFraga 924 Court St. $399.30 10% $439.23
5215 Smith Dr. Martinez, CA 94553
Martinez, CA
TOTAL: $554.73
I
BOARD OF DIRECTORS
NO.
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
June 26, 1981
SUBJECT TYPE OF ACTION
EXECUTE CONSENT TO DEDICATION TO CONTRA COSTA COUNTY -
M.S.24-81 (JOB 934-Parcel 20) RIGHT OF \~AY
SUBMITTED BY
Jay S. McCoy
INITIATING DEPT./DIV.
Collection/Engineering System
ISSUE: A portion of M.S.24-81 is being dedicated to the County for
publ ic road purposes. An existing public sewer easement is located
within the dedicated area.
BACKGROUND: The County requires a IIConsent to Dedicationll whenever
an area dedicated for public road purposes encroaches upon an
existing easement.
This is our standard consent document, the District retains prior
rights.
RECOMMENDATION: Approval, execute document and authorize its
recording by the County.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INIT ;2/J2;IVO JSM
~
CL\.J
, '"
r
I
Centra ';ontra Costa Sanit~~ :I District
BOARD OF DIRECTORS
NO. IX. WATER POL CONTRa
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
Jun,e 25, 1981
SUBJECT
TYPE OF ACTION
AUTHORIZATION OF $49,UOO FOR THE REMOVAL. AND DISPOSAL
OF ASBESTOS INSULATION PRESENTLY COATING PORTIONS OF THE Capital Expenditure
PUMP BUILDING AND BASEMENT OF THE PRIMARY CONTROL B
SUBMITTED BY INITIATING DEPT./DIV.
Robert A. Baker Plant Operations
Issue: The asbestos insulation placed in the Pump Building and basement of the
Primary Control Building poses a potential health hazard.
Background: In the late 19501s, asbestos insulation was placed in the basement of
the Primary Control Building and on the ground-level floor and first basement of the
Pump Building. This insulation was painted by the contractor, at that time, after
installation. The area has been recently repainted with a polyurethane-type paint
to insure proper encapsulation of tbe asbestos. Air sample tests taken prior to the
painting of the polyurethane paint passed the safe-l imit criteria as establ ished by
Cal/OSHA.
However, a potential hazard exists as long as the asbestos remains on the plant
property. At any time during operation or maintenance of the area, the asbestos
may be damaged, resulting in a condition that may not conform to safety requirements.
Due to the serious nature of the potential hazard, the Plant Operations Department
recommends that the asbestos be removed and disposed of as outl ined by the Division
of Industrial Safety.
Three informal bids were sol icited from the asbestos removal industry. The price on
these bids indicates that it will cost the District approximately $49,000 to remove
and dispose of the asbestos in the manner prescribed by Cal/OSHA.
A formal bidding procedure will be used to permanently solve this problem.
Recommendation: Authorization of a capital expenditure of $49,000 for the removal
and disposal of asbestos insulation currently in the Primary Control Building and
the Pump Building.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INITIATING DEPT./DIV.
PAF
RAB
<C<SD
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
NO. VIII. Engineering 1
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
June 25, 1981
SUBJECT AUTHORIZE THE EXPENDITURE OF SEHER CONSTRUCTION FUNDS
FOR INTERIM MODIFICATIONS TO THE ODOR CONTROL SYSTEM AT
THE TREATMENT PLANT
TYPE OF ACTION
AUTHORIZE EXPENDITURE
SUBMI,TT~D EjY S' 1 P . t E' . D'"
VOlin Larson, pecla rOJec s nglneerlng lVlslon
BACKGROUND:
As the result of engineering investigations conducted by Metcalf & Eddy, the
capacity of three of the odor control units at the treatment plant has been
found to be below the anticipated capacity. Prior to the expenditure of
large sums of money to correct this deficiency, a test will be conducted
during August to determine the required capacity. New equipment, if required,
would then be designed and installed for next summer under the auspices of
the Stage 5A Project Completion Work.
Interim modifications totaling $14,850, as summarized on the reverse side of
this position paper, are recommended to maximize the capacity of the existing
odor control units. By increasing their chemical delivery capacity this
action is intended to minimize odor complaints that are anticipated later this
summer.
RECOMMENDATION:
Authorize the expenditure of $14,850 for modifications to the odor control
system at the treatment plant.
REVIEWED AND RECOMMENDED FOR BOARD ACT/ON
JL
{{J-b RAB
~~
CLH
GEN. MGR./CHIEF ENG.
SHEET OF
INTERIM MODIFICATIONS TO THE ODOR CONTROL SYSTEM
COST ESTIMATE
EQUIPMENT COST (INCLUDES CONTINGENCY)
INSTALLATION COST (INCLUDES CONTINGENCY)
CONTRACTOR OH&P (@ 15%)
SUBTOTAL
CONSTRUCTION ADMINISTRATION/MANAGEMENT
8 DAYS X $250/DAY
SUBTOTAL
START-UP AND TROUBLESHOOTING
3 DAYS X $250/DAY
TOTAL
$5,500
5,000
1,600
$12,100
$ 2,000
$14,100
750
$14,850
Central
BOARD OF DIRECTORS
I VIA: ROGER J. DOLAN
POSITION PAPER General Manager-Chief Engineer
SUBJECT
DATE
NO. .vl CONSENT CALENDAR
A' 7/?/Ql
June 26, 1981
TYPE OF ACTION
AUTHORIZATION FOR P.A. 81-13 (SAH RAMON AREA) AND P.A.
81-14 (\JALNUT CREEK AREA) TO BE INCLUDED I N A FUTURE
FORMAL ANNEXATION TO THE DISTRICT ANNEXATION
SUBMITTED BY
Jay S. McCoy
INITIATING DEPT./DIV.
Collection/Engineering System
Parcel
No.
Owner
Address
Parcel No. & Acreage
Area
81-15
Conc
Public Storage
11828 Dub 1 in Blvd.
Dub 1 in, CA 911566
110-120-10,-11 & 39
4.2 Acres
81-16
Mtz.
Clyde R. King
4849 Pleasant Hilta~~'
Martinez, CA
162-150-001
6.73 Ac
Remarks
Owner plans to build a
20,000 sq. ft. light
industrial building and
a 65,300 sq. ft. mini-
warehouse complex. Plans
approved and "Negative
Declarationl' by City of
Concord.
Proposed Subd. 5992, Ma~i
mum 12 lots (may be less).
Seven of the lots are in
an area presently within
the District. Plan appro-
ved and "Negative Declara-
tion" by the city.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
'"1;7 ;;Z;'v, JSM
e~
CL~J
Lead
Agency
City of
Concord
City of
Mart i nez
/"\
, ~ ~p.7l. ':