HomeMy WebLinkAboutAGENDA BACKUP 11-19-81
t((SD
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
NO. I II .
r
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
October 19 1981
SUBJECT
TYPE OF ACTION
ACCEPTANCE OF DISTRICT PROJECT NO. 3330, SOLIDS
CONDITIONING BUILDING REPAIRS, PHASE I
ACCEPTANCE OF
CONTRACT WORK
SUBMITTED BY
Edwin J. Anderson
ISSUE: The Contractor, Ric Mar Construction Company, has satisfactorily
completed construction of the Project. The Project is ready for
acceptance by the District Board of Directors.
BACKGROUND: On April 16, 1981, District entered into an agreement with
Ric Mar Construction Company for siding repairs to the Solids
Conditioning Building at the Treatment Plant. The Contractor
satisfactorily completed all construction work on October 14,
1981, including punch list items.
RECOMMENDATION: The following Board actions are recommended:
1. Accept Contract work for Project No. 3330.
2. Authorize filing the Notice of Completion with the Contra
Costa County Recorder.
3. Authorize final payment to the Contractor 35 days after the
Notice is filed provided no claims are received.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INITIATING DEPT./DIV.
e.
CLW
((sD
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
NO. IV. ADM.
? ll/l'/Rl
POSITION n I VIA: ROGER J. DOLAN
r>APER General Manager-Chief Engineer
SUBJECT
DATE
SLUDGE HAULING RATE INCREASE REQUEST
November 12, 1981
TYPE OF ACTION
Consider Rate Increase
Req ues t
SUBMITTED BY
Walter N. Funasaki, Finance Officer
INITIATING DEPT./DIV.
Accounting Division
ISSUE: Pleasant Hill Bay Shore Disposal advised the District by letter dated August
11, 1981 that its sludge hauling rate would increase from $125 to $145 per pull
beginning September 1, 1981.
BACKGROUND: Pleasant Hill Bay Shore Disposal has provided sludge hauling service
for the District since 1977. The $20 increase per pull, which represents a rate
increase of 16%, is the first rate adjustment sought by the company.
The District requested that the company provide data in support of the rate
increase on August 28, 1981. A subsequent letter was sent by District Counsel on
September 16, 1981 requesting the supporting information.
Information provided by the company was received by the District on November
3, 1981 and is summarized below:
Comparison of Certain Sludge Hauling Operating Expenses For the
Period From 1977 to 1981
Typical Cost Increase
Expense 1977 1981 Amount Percent
Driver Wages & All Employee
Benefits, annual $23,617 $37,258 $13,641 57.8
Fuel per gallon:
Diesel $.39 $ .95 $.56 143.6
Gasoline .54 1. 32 .78 144.4
Dumping Fees, per cu. yd. .55 .80 .25 45.5
Invoice copies in support of operating expense increases and computations of
labor and benefit increases which were submitted by the company were reviewed by
District staff.
The average monthly number of sludge hauling pulls during the 11 months
through August 1981 were 489 for an average monthly cost of $62,398. The 16% rate
increase will increase the present average monthly sludge hauling cost by $9,984.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INITIATING DEPT./DIV.
GEN. MGR'/CHIEF ENG.
\mF
RECOMMENDATION: It is recommended that the Board of Directors authorize acceptance
of the rate increase for sludge hauling from $125 to $145 per pull with such increase
becoming effective November 1, 1981.
REVIEWED AND RECOMMENDED FOR SOARD ACTION
ce<SD
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
NO. IV. ADM.
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
November 16, 1981
SUBJECT
TYPE OF ACTION
WORKERS' COMPENSATION INSURANCE
Notification of
Staff Rev i ew
SUBMITTED BY
Walter N. Funasaki
INITIATING DEPT.!DIV.
Accounting Division
ISSUE: A review of the District's workers' compensation insurance program should
be undertaken to determine whether self-insurance is cost effective and feasible.
BACKGROUND: In their risk management audit report which was issued in July 1978,
Warren, McVeigh & Griffin recommended that the District revise its insurance program
by self-insuring a portion of the risks of property, liability and workers. compensation
losses. The District did revise its insurance coverages to include self-retained
limits of $25,000 and $50,000 for property and general liability losses, respectively,
beginning the policy year 1979-1980. Self-insuring workers' compensation losses
to a maximum limit with the purchase of excess coverage for losses above the self-
retained limit was deferred for later review.
The District's workers' compensation insurance coverage is presently provided
by the State Compensation Insurance Fund. The District's premium and loss experience
is pooled with 22 other sanitary districts which are members of CASA.
The District's premiums and incurred loss history for the past 7 years are
summarized below:
1980
1979
1978
1977
1976
1975
1974
Net Incurred
Premium Losses
$74,988 $38,038
57, 194 24,377
71 , 1 82 30, 1 50
59, 132 23,820
33,930 8,888
28,898 29,785
21 ,878 1 ,464
Fiscal
Year
While Warren, McVeigh & Griffin recommended that a self-insurance program for
workers' compensation be implemented for the District, the following cautionary
observations were made:
ZIN=.
EVIEWED AND RECOMMENDED FOR BOARD ACTION
0"-..
. Organizationswiththe District's premium volume usually do not self-insure;
however, most organizations with the District's premium volume do not have
the advantage of the District's risk retention capacity.
. The costs of administration and excess insurance may offset any savings.
These costs can be easily determined by requesting proposals for claims
administration, loss control, and excess insurance.
. The possibil ity of several large losses could reverse the indicated financial
advantage of self-insurance; however, excess insurance can be designed to
protect the District against losses in excess of its risk retention capacity.
RECOMMENDATION: This position paper advises the Board of the initiation of a review
to determine the feasibility of implementing a self-insured workers' compensation
insurance program, and subsequent submission of a report to the Board of Directors
of the results of the review.
REVIEWED AHD RECOMMEHDED FOR BOARD ACTIOH
INITIATING DEPT./DIV.
GEN. MGR.lCHIEF ENG.
c((SD
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
NO. IV. ADM.
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
SUBJECT
AUTHORIZE AN ADDITIONAL MEMBER OF THE DISTRICT STAFF
TO ACT AS SECRETARY PRO-TEM IN THE ABSENCE OF THE
DISTRICT SECTRETARY
TYPE OF ACTION
ADOPT! ON OFRESOLUT! ON
SUBMITTED BY INITIATING DEPT.!DIV.
f District ADMINISTRATION
BACKGROUND: The Secretary of the District, due to vacation or other
reasons, is occasionally absent from Board of Directors Meetings or
unabailable at other times to conduct necessary District business.
For that reason, Roger J. Dolan, General Manager-Chief Engineer, was
authorized on August 4,1977, by Resolution No. 77-21& to act as
Secretary Pro-Tern. The increasing number of meetings and conferences
concerning District business that require the attendance of the
GM-CE, make it desirable to authorize an additional member of the
Administration Department to act as Secretary Pro-Tern.
RECOMMENDATION: Adopt a resolution authorizing the Administrative
Department Manager to act as Secretary Pro-Tern in the absence of
the District Secretary.
EVIEWED AND RECOMMENDED FOR BOARD ACTION
((<SD
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
NO. v. ENG.
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
October 29, 1981
TYPE OF ACTION
SUBJECT
CONSIDER REQUEST OF BRIAN THEISSEN ON BEHALF OF THE
DEVELOPERS OF RANCHO DEL SOL SUBDIVISION
CONSIDER REQUEST
SUBMITTED BY
Jay S. McCoy
INITIATING DEPT./DIV.
Construction and Services
ISSUE: The developers of Rancho Del Sol have requested that the Sanitary
District operate and maintain a package treatment plant for their proposed
development east of Blackhawk (see attached map).
BACKGROUND: On August 6, 1981, the engineer for Rancho
the District to accept the responsibility for operating
a package treatment plant for the proposed development.
Weddle responded to this request on September 11, 1981,
the position of staff as one of not being in a position
responsibility (see attached letter).
Del Sol requested
and maintaining
Dr. Clark
establishing
to accept said
Subsequently, several letters were received from the County (copies
attached) and from Brian Thiessen (copy attached) again requesting the
District accept the responsibility for operating and maintaining the
proposed package treatment plant. It is now appropriate to establish
a position of the Board on this matter. It is the position of staff
that there is no reason to accept the responsibility. In fact it is
anticipated that the package plant would become an unwanted burden.
RECOMMENDATION: Deny the request that the District operate and main-
tain a package treatment plant for the Rancho Del Sol subdivision.
Attachments
REVIEWED AND RECOMMENDED FOR BOARD ACTION
c~ CL~J
Central Costa San
BOARD OF DIRECTORS
District
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
NO. . Eng.
2 11/19/81
DAT~ovember 13, 1981
SUBJECT
TYPE OF ACTION
REPORT ON THE REGIONAL WASTEWATER REUSE STUDY
REPORT
SUBMITTED,BY
Jay S. McCoy
INITIATING DEPT./DIV.
Construction and Services Div.
BACKGROUND: CH2M Hill in conjunction with Bay Area water suppliers
and wastewater dischargers have completed a 3-year, $2 million program
to evaluate the potential for large scale reuse of San Francisco Bay
Area wastewater. Two apprarent best projects have been identified.
They are the Southern San Joaquin Valley Project and the Delta
Salinity Control Project. Maps are attached depicting the general
routes for the two projects. Details on the two projects will be
presented in an oral report at the Board meeting.
The conclusion of the three years of effort is that the Delta Salinity
Control Project is the apparent best reuse project and warrants
further consideration. Staff has concerns about the effects of the
discharge of treated wastewater on the Delta. It appears that the
Department of Water Resources will continue ongoing studies and that
agency will consider the effects of the proposed discharge on the
Delta. One position the Board could take is to support the
continuance of the studies with a stipulation that CCCSD will not
take a position on the Delta alternative until discharge effects are
fully determined. On the other hand, the Board might conclude that
the apparent best alternative project is unacceptable. In this case
the Board could decide that the appropriate position to take would
be that the study should be completed with no recommendation to
continue by any other party.
RECOMMENDATION: Support the continuance of ongoing Delta alternative
studies with specific emphasis on water qual ity issues. Withhold
establishing a position on the Delta alternative until after water
quality concerns are satisfactively addressed.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
JSM
e~ CLW
Sanitary District
BOARD OF DIRECTORS
NO. V. Eng.
3 11 /19/81
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
November 13, 1981
SUBJECT
TYPE OF ACTION
REPORT ON THE STATUS OF THE NEW OFFICE BUILDING
CONSTRUCTION CONTRACT
REPORT
SUBMITTED BY
Ja
INITIATING DEPT./DIV.
Construction and Services
w. A. .Thomas Construction Company began work on the new office building,
meeting room and Plant Operations West Wing renovation in June, 1981.
W. A. Thomas. initial construction schedule provided for completion
of the West Wing renovation on December 20, 1981, completion of the
meeting room on March 20, 1982 and completion of the new office build-
ing on August 17, 1982. The current status of each phase of the
project is reported below.
West Wing Renovation
The initial work effort of the constractor was minimal. By September,
the contractor was well behind schedule. Approximately a month aqo
a more experienced project manager was put in charge by the Contractor.
Since that time the contractor has made a concerted effort on the West
Wino and is close to his orioinal schedule. It is anticioated th~t th~
majority.of the work on the West Wing will be completed by December 31,
1981. .
There is a current problem with respect to light fixtures. There is
a 90 day delivery on the light fixtures specified. A substitution of
equal, alternate fixtures is being pursued. If readily available,and
satisfactory fixtures are foun~ this problem will be solved.
Other existing problems with obtaining matching floor tiles and
locksets will not be solved by the end of December. The renovated
area can be occupied without the completion of these items. The
contractor projects that he will have most of the work on the West
Wing completed by the end of December.
Meeting Room
The contractor estimates that he will complete the meeting room on
schedule (March 20, 1982). There is a current problem on delivery
of structural steel. The date for delivery is November 23, 1981
which is five weeks behind the original schedule. The contractor
plans to put more emphasis on the meeting room after steel is
de 1 i vered.
REVIEWED AND RECOMMENDED FOR BOARD ACT/ON
Page 1 of 2
-e. ~ CLW
-2-
New Office Building
Work on the main building proceeded slowly at first generally due to a
lack of manpower commitment on specific work phases by the Contractor.
Excavation, utility relocations, reinforcing steel and forming took
longer than scheduled mainly due to the Contractor having a low number
of workmen on said phases. After the new project manager was assigned
by the Contractor, the number of workmen increased and the Contractor
improved his progress. Wet weather has slowed the Contractorls progress,
a situation which occurs in any large contract. This particular
contractor has aggravated the effect of weather due to his slow, initial
progress resulting in the walls of the building not being completed
and backfilled prior to the starting of the rains.
Structural steel is also a problem with the schedule for the main
building. Delivery of steel is estimated to occur at the end of
January. Subsequent work efforts will be rescheduled and consolidated
to result in a modified completion near the end of October. The
revised completion date is approximately two months later than the
completion date contained in the contract. A two month delay in
completion of the project is an unacceptable situation. It is recognized
that time extensions will not be granted for delays caused by the
Contractor's inadequate staffing. But, the Contract documents provide
for extensions of time for delays which are not the fault or are beybnd
the control of the Contractor. If delays caused by bad weather, strikes,
natural disasters, etc. actually impair the contractorls progress, he
will be given time extensions accordingly. Staff will continue to
monitor the contractor's progress and advise accordingly.
REVIEWED AND RECOMMENDED FOR SOARD ACTION
INITIATING DEPT./DIV.
GEN. MGR./CHIEF ENG.
((sD
BOARD OF DIRECTORS
NO. v. ~t!i-'A>61F"".J - .y
" /,/'1'
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
November 13, 1981
SUBJECT
TYPE OF ACTION
AUTHORIZE $15,000 FOR DESIGN OF HOLDING BASIN C
RENOVATION, DISTRICT PROJECT 3615
AUTHORIZE FUNDS
SUBMITTED BY
John Larson
INITIATING DEPT./DIV.
Engineering Division
BACKGROUND
There are three holding basins at the treatment plant providing storage
for flows that are bypassed during peak storm flows and emergencies.
The District has embarked on a three-year program to return all three
holding basins to their original operating condition. Holding Basin A
was renovated in 1979 and Holding Basin B was renovated in 1980.
Holding Basin C was used between 1975 and August 1980 to store alum
sludge accepted from CCCWD. During the last construction season the
alum sludge was turned to facilitate drying and a portion of the alum
sludge was removed. Holding Basin C is now ready for the renovation
work. Funds are required for the preparation of plans and specifications.
The overall project will consist of removal of alum sludge deposits,
reconturing the basin interior for proper drainage, improvements to the
drain-back structure, and improvements to the dechlorination facility
piping that is located in Holding Basin C. Upon completion, HOlding
Basin C will provide approximately 30 million gallons of additional
storage capacity t20 hours at current dry weather flows).
RECOMMENDATION
Authorize $15,000 for design of Holding Basin C renovation.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
JL
CLW
((sD
BOARD OF DIRECTORS
NO..lt ~AJ;ltJEEA.I>> ..s-
/I /11A I
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
November 13, 1981
SUBJECT
TYPE OF ACTION
AUTHORIZE $3,300 TO PURCHASE A FINAL EFFLUENT
FLOWMETER FOR TESTING
AUTHORIZE FUNDS
Jo e L nn Kurasaki
Division
SUBMITTED BY
BACKGROUND
A final effluent flowmeter is required for the District's plant in order
to ensure compliance with its NPDES discharge flow requirements and to
provide accurate flow pacing control for chlorination and dechlorination.
A final effluent flowmeter was provided under Stage 5A, however, it did
not perform as designed.
Metcalf & Eddy has recommended the procurement and testing of a magnetic
velocity probe type flowmeter for monitoring final effluent flow. The
Monitek unit, which costs $3,300, offers a $100,000 cost savings in
installed cost over the next best alternative, a Venturi flowmeter. The
unit requires testing because there is not extensive operating history
in the wastewater field.
The cost of the meter is eligible for reimbursement under the Clean Water
Grant Program. The SWRCB is being notified that the District will
prepurchase the flowmeter. Since the meter cost is less than $10,000,
prior approval is not required.
RECOMMENDATION
Authorize $3,300 in Sewer Construction Funds for the purchase of one
Monitek flowmeter.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
JL
CLW
cc<SD
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
NO. v.
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
October 30, 1981
SUBJECT
AUTHORIZE ADOPTION OF AMENDMENT NO. 1 TO THE CSSWMB/
CCCSD ANDWEGMAN/CAROLLO-CCCSD CONTRACTS
TYPE OF ACTION
APPROVAL OF CONTRACT
AMENDMENTS
SUBMITTED BY
Steve McDonald, Associate Engineer
Engineering Division
BACKGROUND
On June 13, 1980 the Board of Directors adopted a resolution accepting a
$438,431 grant from the California State Solid Waste Management Board (CSSWMB)
to perform Predesign Engineering for a Solid Waste to Energy project at the
District. The contract with the CSSWMB includes a rough definition of the
work to be performed, and an associated Schedule of Grant Payments. This
preliminary Scope of Work was also included in the contract with Wegman/
Carollo Engineers for engineering services on the project. District staff
and Wegman/Carollo have recently refined the Scope of Work as necessary to
reflect minor modifications in detail that have arisen. Also, the sequential
order of tasks was modified to more closely reflect the progress to date.
To satisfy our contractual obligation with the CSSWMB it is necessary to
amend the finalized Scope of Work to the original grant contract, and to amend
the associated contract with Wegman/Carollo. These are no-cost amendments
with no changes in the cost to complete the work.
The CSSWMB moved to Adopt Amendment No. 1 to incorporate the final Scope of
work in their contract with the District on October 29, 1981. Wegman/Carollo
has also agreed to adopt Amendment No.1.
RECOMMENDATION
(1) Authorize the GM-CE to execute Amendment No.1 (copy attached) to the
CSSWMB/CCCSD contract.
(2) Authorize the President of the Board to execute Amendment No.1 to the
Wegman/Carol10-CCCSD contract.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
tf:>lv.-
SMc
J/rL- JL
e.~ CLW
OF
INITIATING DEPT./DIV.
Costa
BOARD OF DIRECTORS
District
NO. VI. Items Late for
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
SUBJECT
POSITION PAPER
DATE
November 18,1981
TYPE OF ACTION
SUBMITTED BY
AUTHORIZATION TO ADVERTIZE FOR BIDS FOR CARPETING IN
THE RENOVATED PLANT OPERATIONS BUILDING AND NEW
DISTRICT OFFICE BUILDING
AUTHORIZg AOVERTIZING
Ron Klimczak
INITIATING DEPT.!DIV.
Engineering Division
BACKGROUND: The office building construction contract with W.A. Thomas
includes carpeting in the meeting room area only. Per Architect and
carpet sales representative recommendations, it was decided that a
separate contract should be awarded for the balance of the carpet in-
stallation to insure installation by the most qualified personnel at
the lowest cost.
The Architect intends to finalize the carpet layout drawings within
the next several days. The District Purchasing Division is currently
preparing the contract specifications and associated bidding documents.
Since the remodeling of the Plant Operations Building has a December 20,
1981 completion date, the carpeting work must be advertized as soon as
the plans and specifications are completed to avoid any delay in the
District occupying the remodeled space. The carpeting contract would
provide for carpeting of the New Office Building upon completion of
the work in the fall of 1982.
Although a final engineer1s estimate has not been completed pending
an accurate quantity takeoff by the Architect, a rough cost estimate
for the quantity of carpeting required (including overage for storage
and cleaning equipment) would be approximately $75,000. A bid item
will be included to allow for possible deletion of carpeting on a
portion of the second floor.
RECOMMENDATION: Authorize the Purchasing Division to advertize for
bids for carpeting in the Renovated Plant Operations Building and
New District Office Building as soon as the plans and specifications
are completed.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INITIATING DE~V ~
(~. ~ JL
CLW