HomeMy WebLinkAboutAGENDA BACKUP 10-21-82 District BOARD OF DIRECTORS NO. 3 10/21/82 POSITION PAPER VIA: ROGER J. DOLAN General Manager-Chief Engineer DATE October 15, 1982 SUBJECT AWARD OF CONTRACT FOR DISTRICT PROJECT NO. 3650; 1982 STORM DAMAGE REPAIRS-SOARES LANE, LAFAYETTE AND AUTHORIZE SEWER CONSTRUCTION FUNDS TYPE OF ACTION AWARD CONTRACT AND AUTHORIZE FUNDS Jarred Miyamoto-Mills INITIATING DEPT./DIV. Engineering Division SUBMITTED BY ISSUE: of the A contract must be awarded or proposals rejected within 30 days opening of sealed bids. BACKGROUND: Heavy rains during the winter storms of 1982 damaged portions of the District's 6-inch sewer main off Soares Lane, Lafayette. Collection System Operations crews made emergency repairs to the damaged creek crossings by providing for temporary plastic pipe- lines. On April 15, 1982, the Board authorized funds for design of permanent repairs to various District facilities damaged by the storms of 1981 and 1982. Plans and specifications for the repair work were completed and advertise- ments inviting the submission of sealed bids were placed on October 5 and 10, 1982. The work generally consists of 63 lineal feet of 6-inch diameter sewer main pipeline replacement and construction of appurtenant structures, driveway improvements, 100 cubic yards of sacked concrete slope pro- tection, cut off walls, and restoration of creek bed and creek bank. The Engineerls Estimate for the contract work is $34,000. Bids were received and opened on October 15, 1982 and are nOw being evaluated by Engineering Division staff. Bids will be reported and a recommendation for contract award or re- jection of proposals will be presented at the Board's October 21, 1982 meeting. REVIEWED AND RECOMMENDED FOR BOARD ACTION ~ JM2 ~~CS 0L JL e.~ CLW INITIATING DEPT./DIV. ITEM 10. POST BID - PRECONSTRUCTION ESTIMATE OF COSTS FOR DISTRICT SEWERING PROJECT 3650 DESCRIPTION ITEM AMOUNT 1 . Construction Contract (As Bid) . 2. Estimated Construction Contingencies . . . . . . $ 3. Estimated Construction Incidentals to Project Completion Survey. . . $ 1 .900.00 Inspection .$3,800.00 Engineering . $ 2,000.00 Total Estimated Construction Incidentals . $ 7 , 700 . 00 4. Street Resurfacing or Seal Coat . . . . . . . . . . $ 5. Total Estimate Required to Complete Project 6. Pre Bid Expenditures Survey, Engineering, Printing, Advertising ~M~~~ .CS.O pep't.. E)llerg~ Right-ot-Way Acquisition. . . . . . $ 9,200.00 ~ep~i:s. $ 700.00 .$ - 7. Total Preconstruction Incidentals (as ot 10-20-82). . $ 9.900.00 8. Total Estimated Project Cost (Items 5 & 7) 9. Funds Previously Authorized Total Additional Funds Required to Complete Project. (Item 8 minus Item 9) TOTAL . $ 35,340.00 3,560.00 $7.700.00 . . $ 46 .600.00 $ 9.900.00 . $ 56 ,500.00 . $ 6,300.00 . $ 50.200.00 % CONST. CONTRACT 100% 10% 22% 132% 28% 160% 2050-8-78 October 20, 1982 FROM: THE HONORABLE MEMBERS OF THE BOARD OF DIRECTORS Roger J. Dolan ~ C 1 ark L. Wed d 1 e ~ John Larson J~.{j Curt Swanson CtI" Jarred L. Miyamoto-Mills ~~ AWARD OF CONTRACT FOR DISTRICT PROJECT NO. 3650: 1982 STORM DAMAGE REPAIRS-SOARES LANE, LAFAYETTE AND AUTHORIZATION OF $50,200.00 IN SEWER CONSTRUCTION FUNDS. MEMO TO: VIA: SUBJECT: ISSUE: On October 15, 1982, sealed bids for District Project No. 3650 were received and opened. A contract must be awarded or proposals re- jected within 30 days of the opening of sealed bids. BACKGROUND: Heavy rains during the winter storms of 1982 damaged portions of the District's 6-inch sewer main off Soares Lane, Lafayette. Collection System Operations crews made emergency repairs to the damaged creek crossings by providing for temporary plastic pipelines. On April 15, 1982, the Board authorized funds for design of permanent repairs to various District facilities damaged by the storms of 1981 and 1982. Plans and specifications for the repair work were completed and advertise- ments inviting the submission of sealed bids were placed on October 5 and 10,1982. The work generally consists of 63 lineal feet of 6-inch diameter sewer main pipeline replacement and construction of appurtenant structures, driveway improvements, 100 cubic yards of sacked concrete slope protection, cut off walls, and restoration of creek bed and creek bank. Eight bids ranging from $35,340 to $92,260 were received as per the attached tabulation of bids. The apparent low bidder is Mountain Cascade of San Ramon, California. The Engineer's Estimate for the work is $32,310. A Post Btd/Pre-Construction cost estimate is attached. $50,200.00 is needed to complete the project, including contract construction, construction management, incidentals and contingencies. It is anticipated that work on the project will start in early November. The District's agreement with the California Department of Fish and Game allows work in or near the creek until October 31, 1982. An ex- tension of this condition to late December 1982 has been requested. (2) In accordance with the Federal/State Disaster Report dated May 19, 1982, $17,370 of the project cost will be reimbursable from disaster re1 ief funds. RECOMMENDATION: Award the contract for construction of District Project No. 3650 to Mountain Cascade per their bid received October 15, 1982 and authorize $50,200.00 in sewer construction funds for the project. Central Cont Costa San BOARD OF DIRECTORS District POSITION PAPER VIA: ROGER J. DOLAN General Manager-Chief Engineer NO. IV. ~ids & AW10 21 82 DATE October 18, 1982 SUBJECT AWARD OF CONTRACT FOR THE CLEANING OF ONE ALUM SLUDGE POND AND AUTHORIZE $41,000 IN SEWER CONSTRUCTION FUNDS TYPE OF ACTION AWARD CONTRACT AND AUTHORIZE FUNDS SUBMITTED BY Charles W. Batts INITIATING DEPT./DIV. Plant Operations/Maintenance Issue: On October 18, 1982, sealed bids for cleaning out one alum sludge drying pond located at the District's Water Pollution Control Plant were opened. The Board of Directors must award a contract or reject proposals within 30 days of the opening of bids. Background: The Central Contra Costa Sanitary District is treating alum sludge generated by the Contra Costa County Water District through the use of settling/drying basins on the Water Pollution Control plant site pending the resolution of the alum sludge issue. At present one of the two alum sludge sett1 ing/drying basins is full, dried, and requires cleaning; the other alum sludge basin is now in use. A Sewer Construction Fund Account will be established for this work to track costs and to recover costs from Contra Costa County Water District. Engineers' Estimate was $35,000. This project was advertised on October 7, 1982, inviting contractors to review the project and submit sealed bids within ten days. Bids were received ranging from $35,550 to $245,000. The apparent low bidder is Shands Construction Company. Recommendation: Award the contract for the cleaning of one alum sludge pond to Shands Construction Company per their bid and authorize $41,000 in Sewer Construction Funds for construction, contingencies, and incidentals. REVIEWED AND RECOMMENDED FOR BOARD ACTION CWB TREATMENT PLANT PROJECT AMOUNT $35,550 2,000 DESCRIPTION ITEM l. 2. Construction Contract Estimated Construction Contingencies (5%) 3. Estimated Construction Incidentals $2,000 500 500 Survey Inspection Engineering Total Incidentals TOTAL ESTIMATE 3,000 $40,550 4. 5. Pre-Bid Expenditures Survey, Advertising, Engineering TOTAL PROJECT 450 $41,000 6. October 18, 1982 MEMORANDUM TO: Charles W. Batts, Plant Maintenance Division Manager FROM: Patrick O'Connor, Senior Buyer SUBJECT: CLEANING OF ALUM SLUDGE BASIN I I Formal Bidding commenced with Publication of Notice to contractors on October 7 and 12. Seven contractors completed the site inspection, as required, and were given their package upon completion of the inspection. Bids were publ icly opened and read on Monday, October 18, 1982. Tabulation is as follows: Contractor Bid Amount Exceptions Shands Construction Heim Bros. Winton-Jones Gallagher and Burk Da 1 ze 11 Co. o. C. Jones IT Corp $ 35,550. $245,000. No Bid No Bid No Bid No Bid No Bid None None The lowest Bidder is Shands Construction. They have previously demonstrated their ability to fulfill all of the requirements of a contract. Shands Construction Bid is in line with the engineer's estimate which is $35,000. Purchasing, therefore, recommends that you prepare the Position Paper to the Board of Directors recommending the award to Shands Construction for cleaning of alum sludge Basin I I at the lump sum contract price of $35,550. ^ ~ ~!~A~~ PO:gv cc: K. Laverty Contract File Senior Buyer FORMAL BID OPENING TP-7-8Ja3 OCT. 18, 1982. 10:00 A.M. ALUM SLUDGE BASIH I I Bids Out To Received/Date-Time Amount Bid 1. Winton Jones 2. Shands ":'0 A.M '6- l<it. '6 z.. y s:.fJ oj j) '3S":5'So.oo v 3. Gallagher & Burk q. Da 1 ze 11 5. O.C. Jones 6. Heim Bros. 1. : '3 () 1'. /..f 10.''1- J;2. 31 tI_' l1-J> , ~ L/ S; () d () ~D - 7. IT Cor . p BIDS OPENED BY WITNESS FOR THE PRESENT AT BID OPENING 1. 8((, '- S#,#JJ>S 2. 3. q. 5. 6. 7. 8. 9. BOARD OF DIRECTORS NO. 2 10/21/82 POSITION PAPER VIA: ROGER J. DOLAN General Manager-Chief Engineer DATE October 15 1982 TYPE OF ACTION SUBJECT AWARD OF CONTRACT FOR DISTRICT PROJECT NO. 3662; 1982 STORM DAMAGE REPA IRS - BLACKHAvJK ROAD, LAFAYETTE AND AUTHORIZE SEWER CONSTRUCTION FUNDS AWARD CONTRACT AND AUTHORIZE FUNDS Jarred Miyamoto-Mills INITIATING DEPT./DIV. Engineering Division SUBMITTED BY ISSUE: A contract must be awarded or proposals rejected within 30 days of the opening of sealed bids. BACKGROUND: Rainfall during winter storms of 1982 caused bank erosion in the immediate vicinity of one of the District's trestle bent footings which supports an 8-inch sewer creek crossing near Blackhawk Rd., Lafayette. This erosion resulted in differential settlement of the footing and a consequent 2 foot displacement of the pipe. On April 15, 1982, the Board authorized funds for design of permanent repairs to various District facilities damaged by the storms of 1981 and 1982. Plans and specifications for the repair work were completed and adver- tisements inviting submission of sealed bids were placed on October 7 and 12, 1982. The work consists of the fabrication and installation of a 30 ft. pipe support strut, the installation of 70 lineal feet of new concrete coated and 1 ined 811 steel sewer pipe, the construction of one anchor block and one expansion block and the trimming and cabling of an adjacent 60 inch Oak tree. The Engineer1s Estimate for the contract work is $29 000. Bids were received and opened on October 18, 1982 and are now bei~g evaluated by Engineering Division staff. Bids will be reported and a recommendation for contract award or re- jection of proposals will be presented at the Board's October 21, 1982 meeting. '2- JM2 REVIEWED AND RECOMMENDED FOR BOARD ACTION e;.& -:l ~ JL I a..r:w CLW INITIATINC O:CPT..'DIV. POST BID - PRECONSTRUCTION ESTIMATE OF COSTS FOR DISTRICT SEWERING PROJECT 3662 %CONST. ITEM DESCRIPTION ITEM AMOUNT TOTAL CONTRACT 1 . Construction Contract (As Bid) . . $ 21,900.00 100% 2. Estimated Construction Contingencies . $ 2,200.00 10% 3. Estimated Construction Incidentals to Project Completion Survey. .$ 2.500.00 Inspection . $ 2,850.00 Engineering .$ 2,150.00 Total Estimated Construction Incidentals .$ 7,500.00 $ 7,500.00 34% 4. Street Resurfacing or Seal Coat . $ 5. Total Estimate Required to Complete Project . $31,600.00 144% 6. Pre Bid Expenditures Survey, Engineering, Printing, Advertising. . . . $ 18,200.00 Special Services S.oi.1 COllsu.1tpnt. ... $ 2.600.00 B4s~~WalC~)(~lllIX. Tr.ee Consu1.taJ1t. ar.td . $ 1,800.00 trim branches Total Preconstruction Incidentals (as of 10-18-82). . $ 22,600.00 7. $22,600.00 103% 8. Total Estimated Project Cost (Items 5 & 7) . $54.200.00 247% 9. Funds Previously Authorized . $11 .700.00 10. Total Additional Funds Required to Complete Project. (Item 8 minus Item 9) . $42,500.00 2050-8-78 October 20, 1982 MEMO TO: THE HONORABLE MEMBERS OF THE BOARD OF DIRECTORS VIA: Roger J. Dol an ~ Clark L. Weddle e.~ John La rson~" Curt SwansoncUJ; FROM: Jarred L. Miyamoto-Mills ~~ SUBJECT: AWARD OF CONTRACT FOR DISTRICT PROJECT NO. 3662: 1982 STORM DAMAGE REPAIRS-BLACKHAWK ROAD, LAFAYETTE AND AUTHORIZATION OF $42,500.00 IN SEWER CONSTRUCTION FUNDS. ISSUE: On October 18, 1982, sealed bids for District Project No. 3662 were received and opened. A contract must be awarded or proposals re- jected within 30 days of the opening of sealed bids. BACKGROUND: Rainfall during the winter storms of 1982 caused bank erosion in the immediate vicinity of one of the District's trestle bent footings which supports an 8-inch sewer creek crossing near Blackhawk Rd., Lafayette. This erosion resulted in differential settle- ment of the footing and a consequent 2 foot displacement of the pipe. On April 15, 1982, the Board authorized funds for design of permanent repairs to various District facilities damaged by the storms of 1981 and 1982. Plans and specifications for the repair work were completed and adver- tisements inviting submission of sealed bids were placed on October 7 and 12, 1982. The work generally consists of the fabrication and installation of a 30 ft. pipe support strut, the installation of 70 lineal feet of new concrete coated and lined 8" steel sewer pipe, the construction of one anchor block and one expansion block. Nine bids ranging from $21,900.00 to $61,994.00 were received as per the attached tabulation of bids. The apparent low bidder is Engineering Construction Inc. of Concord, California. The Engineers Estimate for the work is $27,400.00. A Post Bid/Pre-Construction cost estimate is attached. $42,500.00 is needed to complete the project, including contract construction, construction managment, consultants, incidentals and contingencies (2) It is anticipated that work on the project will start in early November. The District's agreement with the California Department of Fish and Game allows work in or near the creek until October 31, 1982. An ex- tension of this condition to late December 1982 has been requested. RECOMMENDATION: Award the contract for construction of District Project No. 3662 to Engineering Construction, Inc. per their bid received October 18, 1982 and authorize $42,500.00 in sewer construction funds for the project. Central Contra Costa Sanitary District BOARD OF DIRECTORS NO. IV. BI DS & AWARDS POSITION PAPER VIA: ROGER J. DOLAN General Manager-Chief Engineer DATE October 19. 1982 SUBJECT AHARD CONTRACT FOR DISTRICT PROJECT 3812, SERVICE AIR COMPRESSOR PREPURCHASE AND AUTHORIZE $87,380 IN SEWER CONSTRUCTION FUNDS TYPE OF ACTION AWARD CONTRACT AUTHORIZE FUNDS SUBMITTED BY Joye L nn Kurasaki Issue On September 30, 1982, sealed bids for District Project 3812. service air compressor prepurchase, were opened. The Board of Directors must award a contract or reject proposals within 30 days of the bid opening. Background The service air system which supplies both service and instrument air, is a critical part of the treatment plant. However, the existing service air compressor units are under capacity and poorly designed. Major maintenance is required about once every six months. Since October 1980, the District has spent over $60,000 in maintenance and rental compressor costs to keep the service air system operational. . The design for the purchase and installation of a new and reliable compressor was submitted to the SWRCB in December 1981. A request for Advance Construc- tion Approval followed in March 1982. Although the SWRCB agrees with the need for a new compressor, any approval for equipment installation will be contingent on their overall approval of the Stage 5A claim settlement agree- ment and subsequent closeout of the Stage 5A grant. This is not expected before April 1983. District staff would like to proceed with the prepurchase of a new compressor due to the long lead time (5 months) for compressor delivery. This would provide for equipment installation by May 1983 instead of October 1983. Approximately $18,000 in maintenance costs could be avoided. District staff is working to obtain Advance Construction Approval from the SWRCB for the compressor prepurchase. The SWRCB staff has indicated that they would review the District's request and will make a determination during the week of October 18, 1982. District staff does not recommend awarding the prepurchase without SWRCB approval since it would eliminate any possibility of grant funding of the purchase cost. The service air compressor is a sole source procurement item due to the type of compressor required. The District received one bid for this contract. The price was $73,245.37 and is approximately 2 percent lower than the engineer's estimate of $74,940. The Districtts staff has evaluated the bid and their evaluation is summarized in Attachment No.1. REVIEWED AND RECOMMENDED FOR BOARD ACTION JLK e~$ cws JL. JL e~ CLW The total installed cost of the service ai-r compressor fs estimated at $138,980 (Attachment NO.2). At thi.s time $87,380 in funds are requi red for the compressor prepurchase, purchase of a motor starter and District force account. A separate position paper to cover the cost of the com- pressor installation and District force account during installation and startup, will be submitted at a later date. This project is included in the 5....Year Capital Expenditure Plan as part of the Stage 5A Completion Project. Recommendation Award the contract for D.P. 3812, service air compressor to Power Machine Company subject to SWRCB approval of the prepurchase. Authorize $87,380 from Sewer Construction Funds. Attachments REVIEWED AND RECOMMENDED FOR BOARD ACTION INITIATING DEPT./DIV. GEN. MGR./CHIEF ENG. JLK CWS JL CLW ATTACHMENT NO. 1 CENTRAL CONTRA COSTA SANITARY DISTRICT SERVICE AIR COMPRESSOR CONTRACT GRANT NO. C-06~0696~010 BID TABULATION ENGINEER'S POWER ITEM ESTIMA TE MACHINE CO. l. Service Air Compressor $66,960.00 $65,755.00 including freight spare parts & startup services 2. Credit (1) - $5,000.00 3. Compressor Space included in $ 2,620.00 Heaters & Thermal item No. 1 ... Protectors 4. Cooling Water $ 3,405.00 $ 5,400.00 Components 5. Sales Tax (2) $ 4,575.00 $ 4,470.37 6. Total $ 74 , 940. 00 $73,245.37 (1) Credits received for fees previously paid for a rental compressor (2) 6~% Sales Tax ATTACHMENT NO. 2 CENTRAL CONTRA COSTA SANITARY DISTRICT SERVICE AIR COMPRESSOR PROJECT PROJECT COST Tota 1 A. Construction Contracts *Compressor Prepurchase *Motor Starter Purchase Compressor Installation Subtotal $ 73,246 6.000 38',000 $117,246 Contingency (5% for prepurchase, 10% for starter & installation) Contract Subtotal 8 ,064 $125,310 $125,310 B. Construction Management - District Force Account *Prepurchase Contract 1. Administrative 2. Shop Drawing Review $440 1,830 Installation Contract 1. Survey 400 2. Inspection 1,360 3. Contract Admin. 1 ,680 4. Grant Admin. 1 ,680 5. Office EngrjAs Builts 1 ,680 Operating Instructions 6. Startup & Testing 3,000 Construction Management Subtotal $12,070 $12,070 C. Other Expenditures *Advertising & Printing $1 ,600 $1 ,600 D. Project Cost $138,980 E. Funds This Authorization (indicated by *) $87,380 F. Future Authorization $51 ,600 District BOARD OF DIRECTORS NO.V. CONSENT CALENDAR 2 10 21 82 POSITION PAPER VIA: ROGER J. DOLAN General Manager-Chief Engineer DATE October 14, 1982 SUBJECT AUTHORIZATION FOR P.A. 82-17 (PLEASANT HILL AREA) TO BE INCLUDED IN A FUTURE FORMAL ANNEXATION TO THE DISTRICT. TYPE OF ACTION AUTHORIZE ANNEXATION SUBMITTED BY Jay S. McCoy .lJ'jITIATING De;PT./DIVCI ~onstructlon an Services Division Parcel No. Area Owner Address Parcel No. & Acreage Remarks Lead Agency 82-17 Pleasant Hi 11 A.G. Carrara, et ux 459 Camino Las Juntas Pleasant Hill, CA 94523 Septic tank failing. District to prepare 'INotice of Exemptionl' CCCSD RECOMMENDATION: Authorize P.A. 82-17 to be included in a future formal annexation to the District. REVIEWED AND RECOMMENDED FOR BOARD ACTION ~CLW <C<SD Central Contra Costa Sanitary District BOARD OF DIRECTORS N~ V. CONSENT CALENDAR POSITION PAPER VIA: ROGER J. DOLAN General Manager-Chief Engineer DATE October 18. 1982 SUBJECT TYPE OF ACTION SUBMISSION OF 1981-1982 AUDIT REPORT PREPARED BY INDEPENDENT AUDITORS RECEIVE AUDIT REPORT SUBMITTED BY Walter N. Funasaki INITIATING DEPT./DIV. Administrative/Accountin ISSUE: The audit of the District's financial statements for the 1981-1982 fiscal year was completed by Laventhol & Horwath. Certified Public Accountants. whose audit report is submitted to the Board of Directors herewith. BACKGROUND: The audit of the District's financial statements was commenced on August 16. 1982; the audit field work was completed on August 31. 1982. The audited financial statements are prepared on an enterprise basis. The auditor's opinion is qualified as to the outcome of the lawsuit related to the construction of the wastewater treatment plant. A copy of the audit report will be distributed to the State Controller's Office. the County of Contra Costa. certain bondholders. and others on request. RECOMMENDATION: Receive the 1981-1982 audit report prepared by Laventhol & Horwath. EVIEWED AND RECOMMENDED FOR BOARD ACTION INITIATING DEP~.~ IVV..~ WN F I2l:fl.. Central Contra Costa Sanitary District BOARD OF DIRECTORS No.VI. ADMINISTRATIVE 1 1 2 POSITION PAPER VIA: ROGER J. DOLAN General Manager-Chief Engineer DATE October 14, 1982 SUBJECT DECLARE CERTAIN DISTRICT EQUIPMENT AND MATERIALS SURPLUS AND/OR SCRAP; AND AUTHORIZE DISPOSAL TYPE OF ACTION Declara tion of Surplus/Scrap; and Authorize Disposal SUBMITTED BY INITIATING DEPT./DIV. K. F. Laverty, Purchasing & Materials Officer Administrative/Purchasing ISSUE: Surplus/scrap equipment and materials need to be disposed of on a District-wide basis. BACKGROUND: It has been approximately 20 months since the last disposal, by the District, of surplus/scrap equipment and materials. Various departments have accumulated, because of reasons of safety, construction and replacement, both surplus equipment and scrap materials. To get the best possible value for the District and to reduce District employee's time, we intend to dispose of all the District's Departments surplus/scrap items at one time. The methods of surplus/scrap disposal has been discussed with the District's legal counsel. He has advised that the "scrap" disposal could be done on an informal sealed bid basis, wherein scrap dealers are verbally invited to take a look at the scrap and submit a sealed bid on the total lot without going for a public advertisement. All surplus equipment will, however, be publically advertised. To reduce the amount of time for District personnel, the equipment will be disposed of on a sealed bid basis rather than a public auction. Attached are listings of the equipment and materials to be declared surplus/scrap. Each equipment item shows the reason for its removal from the District. The estimated value of all the equipment and materials is $15,000. RECOMMENDATION: Declare the listed equipment surplus and the indicated piles of miscellaneous metal scrap; and authorize the disposal thereof. REVIEWED AND RECOMMENDED FOR BOARD ACTION (((sD Central Contra Costa Sanitary District BOARD OF DIRECTORS NO. VI. ADMINISTRATIVE POSITION PAPER VIA: ROGER J. DOLAN General Manager-Chief Engineer DATE October 18 1982 SUBJECT TYPE OF ACTION DEFERRED COMPENSATION PLAN ADMINISTRATIVE PROCEDURES APPROVE ADMINISTRATIVE PROCEDURES SUBMITTED BY Walter N. Funasaki INITIATING DEPT.!DIV. Administrative/Accounting ISSUE: The Deferred Compensation Plan Advisory Committee has prepared the administrative procedures for the District's Deferred Compensation Plan. BACKGROUND: Committee is the Deferred attached. A responsibility of the Deferred Compensation Plan Advisory the development of the internal administrative procedures for Compensation Plan. A copy of the administrative procedures is The administrative procedures will be incorporated in an employee handbook which describes the Deferred Compensation Plan. RECOMMENDATION: Approve the Deferred Compensation Plan administrative procedures developed by the Deferred Compensation Plan Advisory Committee. REVIEWED AND RECOMMENDED FOR BOARD ACTION INITIATING DEPT.!d " WNF ~ ADMINISTRATIVE PROCEDURES FOR CENTRAL CONTRA COSTA SANITARY DISTRICT DEFERRED COMPENSATION PLAN I. INTRODUCTION I. I Purpose The purpose of the Deferred Compensation Plan (Plan) is to offer an attractive employee benefit under which tax-deferred contributions, in lieu of current income, will provide future payments upon death, disability, retirement, or other termination of employment with the District. 1.2 Origin In January 1976, the District voluntarily withdrew from participation in the Federal Social Security System and established a Deferred Compensation Plan. The District's withdrawal from Social Security, however, caused an increase in the District's contribution to the County Retirement System in the amount of $10.90 per month at Plan inception. To keep the District's total contribution to the two plans (Deferred Compensation and County Retirement) from exceeding the combined cost of Social Security and County Retirement, the District's contribution to the Deferred Compensation Plan was set at an amount equal to the Social Security contribution less $10.90 per month for each participant. Therefore, the District's present monthly contribution to each participant's account is an amount equal to the Social Security tax rate times the employee's monthly salary less $10.90. If an employee's annual salary exceeds the maximum taxable amount under Social Security, the District's annual contribution is currently equal to the Social Security tax rate times the maximum taxable amount less $10.90 times the number of months required for the employee to earn the maximum taxable amount. To participate in the Plan and be eligible for the District's contribution, an employee must contribute a minimum of $5 per month. The maximum contribution during any tax year shall not exceed the limit established by law. Both the District's contribution and the amount contributed by the employee to the Plan are not taxable until withdrawn. 1.3 Administration The District has entered into an agreement with Hartford Variable Annuity Life Insurance Company (Hartford) to act as Plan Administrator. Hartford's sales and service agent is Dean Witter Reynolds, Inc. (Dean Witter). The District has the sole authority to enforce the Plan and is responsible for the operation of the Plan in accordance with its terms. -1- 2. DEFERRED COMPENSATION PLAN ADVISORY COMMITTEE To facilitate the internal administration of the Plan, a Deferred Compensation Plan Advisory Committee (Committee), operating under the guidance of the District Finance Officer, was established (Board Position Paper approved on January 28, 1982). 2.1 Committee Membership One non management employee is selected from each department to serve on the Committee. Selection of department representatives to the Committee is the responsibi lity of the Department Managers. The Finance Officer is responsible for notifying the Department Manager when a representative's term has expired or when a replacement is needed for any other reason. 2.2 Term of Service Committee members serve two-year terms beginning the first day of March and ending the last day of February. The initial terms for the Plant Operations and Engineering Departments were three-year and one-year terms, respectively, to provide for overlapping terms. Should a department representative resign, terminate employment, or transfer to another department during the term, the Manager of the department losing representation selects a replacement member to fill the unexpired portion of the term. With the concurrence of the new Manager, a transferred individual will be allowed to remain as an ex officio member in order to complete an ongoing project. 2.3 Scope of Committee Activities Included in the scope of activities are (I) establish internal administrative procedures, (2) develop a document summarizing the Plan, (3) review accountability by Plan Administrator (Hartford), (4) review requests for emergency withdrawals, (5) review investment performance, (6) report to District management and the Board of Directors. 2.4 Operation of the Committee The Committee meets as often as it determines necessary, agrees upon rules of order, and keeps the records it deems appropriate. 3. CHANGES AFFECTING THE DEFERRED COMPENSA TlON PLAN Any changes in the Social Security regulations and laws which would affect the contribution amount are communicated by the Finance Officer to the employees and to the Committee for revisions to various written documents. The Committee shall establish a review schedule for the Administrative Procedures and the P Ian Summary to ensure that these documents are current. -2- 4. DOCUMENT PROCESSING All forms required for enrollment, changes, emergency withdrawals, and termination withdrawals, are avai lab Ie through the Accounting Office. Hartford prepares a quarter Iy statement of earnings for each employee which is distributed by the Accounting Office. Usually, statements distributed each quarter are for the quarter ending the previous month. 4.1 Enrollment The Personnel Office provides all new employees with an information packet containing the Administrative Procedures for the Deferred Compensation Plan and a copy of the Plan Summary. Each new employee is advised by the Personnel Office that a representative of bean Witter will contact the employee to explain the Plan and, if the employee so chooses, enroll him/her in the Plan. The Accounting Office advises Dean Witter of each new hire. A representative from Dean Witter then contacts the employee, meets with him/her at his/her work location, explains the Plan (including the fees and risks associated with various options), and gives him/her a copy of the Hartford Plan prospectus. If the employee elects to participate, Dean Witter has him/her sign enrollment forms ("Joinder Agreement" and "Notification of Change") which are returned to the Accounting Office by Dean Witter for processing. If the employee elects not to enroll within 30 days of hire and signs a statement to that effect, he/she must wait unti I the next open enrollment period (see Section 4.2 below). The Accounting Office processes the enrollment application as follows: a. Checks forms to see that they have been fi lied out completely and correctly. Confers with the employee on any question. b. Obtains authorized District signature (Clyde Hopkins, Paul Morsen, or Roger Dolan). c. Forwards the signed enrollment forms to Hartford via Dean Witter. d. Sends a copy of the signed forms to the employee. e. Starts payroll deductions and District payments. 4.2 Changes to a Participant's Account The District has established enrollment periods during the months of August, November , February, and May. By applying through the Accounting Office dUrIng these months, an employee may make one or more of the following changes to his/her account, effective the following pay period. -3- 1-\ a. An employee who elected not to participate when hired may enroll in the Plan. (Requires "Joinder Agreement" and "Notification of Change.") b. An employee may change the amount of his/her personal contribution to the Plan (increase or decrease). (Requires "Joinder Agreement" and "Notification of Change.") c. An employee may change the account allocation of moneys previously contributed (move money among fixed and variable accounts). (Requires "f\Jotification of Change.") d. An employee may change the allocation of future contributions. (Requi res "Not i fi cat i on of Change.") Forms are available in the Accounting Office and will be processed by the Accounting staff in the same manner as described under Section 4.1. 4.3. Emergency Wi thdrawa I Only in the event of extreme financial hardship may an employee make a cash withdrawal from the Plan. An unforeseeable emergency beyond the employee's control must exist. Any amount withdrawn is subject to federal and state taxes and Hartford's administrative fees. Emergency Withdrawal Applications are available in the Accounting Office. Although applications are processed as expeditiously as possible, the approval procedure may take as long as 30 days. The procedure is as follows: a. The employee receives the form and a copy of this procedure from the Accounting Office and returns the completed form to the Finance Officer. b. The Finance Officer notifies Committee members of the application. c. Based upon the apparent urgency of the request, the Committee either calls a special meeting or confers on the matter at its next regular meeting. d. If appropriate, the applicant is invited to appear at the meeting to explain his/her application. e. The Committee advises the applicant, In writing, of its position on the application. f. The Committee makes a recommendation to the District Board of Directors (Board) for action at the next regular Board Meeting. g. The Board reviews the application in closed session, as a personnel matter, and advises the Committee of its decision. At the Board's discretion, the applicant and/or a Committee representative may attend the Board Meeting to present additional information as needed. h. The Committee notifies the applicant of the Board's action in writing. -4- I. If the Board allows the emergency withdrawal, the applicant must then fill out and submit a "Withdrawal Request" form (available in the Accounting Office) to the Accounting Office for processing as follows: (I) The form is checked for accuracy and completeness. (2) The form is checked to see that the withdrawal amount does not exceed 90 percent of the account balance. (3) "Emergency Withdrawal" is noted on the form. (4) An authorized District signature (Clyde Hopkins, Paul Morsen, or Roger Dolan) is obtained. (5) The Finance Officer sends a cover letter and the withdrawal form to Hartford via Dean Witter. A copy is sent to the employee. (6) The employee receives a check from Hartford in approximately two weeks. J. If the application for emergency withdrawal is approved, the applicant may also reduce his/her personal contribution to the minimum amount ($5), without waiting for the next enrollment period. (See Section 4.2 for the procedure.) 4.4 Terminations (Includes Retirement) Upon termination, a number of options are available to employees, as described in the Plan Summary. An employee leaving the District will be given a copy of this procedure and will be asked by the Accounting Office to choose an option. If the employee is undecided or selects an option other than full cash withdrawal, he/she will be referred to Dean Witter for help in that decision. If the employee elects to make a full cash withdrawal, he/she completes a "Withdrawal Request" form and returns it to the Accounting Office where it is processed as follows: a. Form is checked for accuracy and completeness. b. An authorized signature is obtained (Clyde Hopkins, Paul Morsen, or Roger Dolan). c. A copy is sent to the employee. d. The completed form is sent to Hartford via Dean Witter. e. The employee receives a check from Hartford in approximately two weeks. -5- . . CENTRAL CONTRA COSTA SANITARY DISTRICT DEFERRED COMPENSATION APPLICATION FOR EMERGENCY WIll--1DRAWAL - EXTREME FINANCIAL CIRCUMSTANCES I. Employee's Name 3. Department 5. Social Security Number 2. Date 4. Work Telephone 6. Amount Requested (not to exceed 90% of Item I I ) 8. Dependents 7. Marital Status 9. Current Monthly Deferred Compensation Deduction 10. I wish to reduce the monthly deduction to $5 0 II. T ota I Deferred To Date 12. Please briefly explain the extreme financial circumstances which require an emergency withdrawal from the District Deferred Compensation Plan. (Attach additional information if necessary.) 13. Is your current financial emergency the result of a voluntary decision or is it due to circumstances beyond your control? 14. Describe financial hardship if this application is denied. 15. Please list your monthly net income from all sources (include spouse's and dependent children's incomes): SOURCE MONTHL Y AMOUNT I. 2. 3. I. 2. 3. 4. 4. 5. 5. TOTAL I of 3 . 'I 16. List all amounts of money you have in checking accounts, savings accounts, safety deposit boxes, or located in any other place. 17. List all major monthly payments you are currently making: SOURCE MONTHL Y PAYMENT BALANCE OWED MARKET VALUE Home Automobiles Furniture Medical Other TOTAL 18. I declare that the foregoing is true and correct. I declare that I request early withdrawal of deferred compensation funds based on extreme financial circumstances which were beyond my control. I understand that any false or omitted information may disqualify my application for early withdrawal. DATED , at , California (Signature of Applicant) 2 of 3 FOR COMMITTEE USE ONLY Committee Recommendation: Approve application in the amount of (not to exceed 90% of Item II). Allow reduction in monthly contribution to the $5 minimum. Yes No Deny application for the following reasons: Commi ttee Signatures: (Signature) (Date) (Signature) (Date) (Si gnature) (Date) (Signature) (Date) (Signature) (Date) DISTRICT BOARD ACTION Date: EMERGENCY WITHDRAWAL REDUCTION IN CONTRIBUTION Approve Deny Approve Deny 3 of 3 Central Contra Costa Sanitary District BOARD OF DIRECTORS NO 1 October POSITION PAPER VIA: ROGER J. DOLAN General Manager-Chief Engineer DATE SUBJECT APPROVAL OF AMENDMENT NO. 7 TO THE TASK B AGREEMENT WITH METCALF & EDDY FOR CONSTRUCTION MANAGEMENT SERVICES FOR THE ELECTRIC AERATION BLOWER TYPE OF ACTION APPROVE CONTRACT SUBMITTED BY Curtis Swanson INITIATING DEPT./DIV. Engineering Issue The Task B Agreement with Metcalf & Eddy (M&E) must be amended to reflect reduced construction management responsibilities for the electric motor driven blower project. Background The electric aeration blower project is being constructed under separate prepurchase and installation contracts. The prepurchase contract was awarded in May 1981, and is substantially completed. The installation contract was awarded on September 16, 1982. M&E is currently under contract to provide complete construction manage- ment services for both construction contracts. When the original agree- ment was negotiated, the District anticipated that several Stage 5A completion projects would be under construction at the same time as the electric blower and that District staff would be unavailable for construc- tion management of either the prepurchase or installation contract. M&E provided construction management services for the substantially completed prepurchase contract. However, because the Stage 5A Projects have been delayed, qualified District staff is available to perform specific inspection and contract administration tasks for the installation portion of the electric aeration blower project. As planned now, District staff will perform civil inspection, mechanical inspection and contract administration during the installation contract. M&E will continue to provide electrical and instrumentation inspection services and engineerinq services during construction including shop drawing review and preparation of as-built drawings. Staff has negotiated Amendment No. 7 with M&E which reduces the scope and level of effort for construction management services for the blower installation contract. The cost ceiling under the original cost plus fixed fee agreement coveY'ing both construction contracts has been reduced by $8400 from $49,505 te; $~,l, 055. Staff intends to use the $8,400 in savings to the electric blower force account to cover the increased District construction management responsibilities. REVIEWED AND RECOMMENDED FOR BOARD ACTION INITIATI~N~T./DIV. CWS \JL J L ~ CLW _~__"_,._______._,_~__..__________~__."______.____"m_~__~_.._... Recommendation Approve Amendment No. 7 to the Task B Agreement with M&E and authorize the General Manager-Chief Engineer to execute the amendment. REVIEWED AND RECOMMENDED FOR BOARD ACTION INITIATING DEPT./DIV. GEN. MGR./CHIEF ENG. CWS JL CLW Central Contra Costa Sanitary District BOARD OF DIRECTORS NO. VII. ENGINEERING VIA: ROGER J. DOLAN General Manager-Chief Engineer DATE October 15, 1982 SUBJECT POSITION PAPER TYPE OF ACTION FIVE YEAR CAPITAL EXPENDITURE PLAN UPDATE AND CAPITAL PROJECT STATUS REPORT ACCEPT PLAN SUBMITTED BY Cl ark L. Weddl e INITIATING DEPT.!DIV. Engineering & Construction Issue The Five-Year Capital Expenditure Plan has been revised. The Board is requested to review and accept the updated plan. Background The Five-Year Capital Expenditure Plan is intended to be a tool for managing the District sewer construction fund, setting project priorities, and identifying new projects that may be necessary or desirable for cost-effective operation of the District. The capital expenditure plan was first presented to the Board in October 1981. In April and October of each fiscal year, the plan is revised and presented to the Board for review, comment and acceptance for use by District staff in long-range planning. To accompany the capital expenditure plan, the Engineering and Construction Department staff has prepared a status report for capital projects currently in planning, design or construction phases. Staff will present a summary of the capital expenditure plan and the capital project status report. After the presentation, staff will answer questions from the Board members. Recommendation Accept the revised Five-Year Capital Expenditure Plan. INITIATING DEPT.!DIV. REVIEWED AND RECOMMENDED FOR BOARD ACTION ~:t...~W Contra Sanitary District BOARD OF DIRECTORS NO.VII 1. WTR. POL. CNTR POSITION PAPER VIA: ROGER J. DOLAN General Manager-Chief Engineer DATE October 14, 1982 SUBJECT AUTHORIZE $7,500 IN SEWER CONSTRUCTION FUNDS FOR QUALITY CIRCLE PROJECT "EASTERN PITS MODIFICATION11 TYPE OF ACTION Autholr i ze Funds SUBMITTED BY C. W. Batts INITIATING DEPT.!DIV. Plant Operations Department/Maintenance Issue: The Plant Operations Department's Maintenance Division's Quality Circle has proposed a solution to the problem of servicing the eastern return nitrified sludge and return denitrified sludge pumps. Background: The members of the Plant Operations Maintenance Division, Mechanical Section, have formed a Qual ity Circle known as the "Nut Busters." The first problem that the Qual ity Circle chose to deal with was the lack of accessibility to equipment in the RNS and RDS pump pits. Removal of this equipment requires costly rental of a long boom crane because obstructions prevent the Districtls boom crane from getting close enough. In reviewing solutions to this problem, several alternatives look promising; the Quality Circle is recommending that the best alternative .:lis tq wqve the wall of electrical substations 33A and 34A approximately four feet to allow the District's boom truck to I ift and remove the equipment in these pits. The cost of this project is $7,500 using District personnel to complete the planned alterations. This modification would pay for the cost of the project the first time it is necessary to remove these pumps for maintenance. Recommendation: Authorize $7,500 in sewer construction funds for the Qual ity Circle project "Eastern Return Nitrified Sludge and Return Denitrified Sludge Pit Mod if i cat ions. II REVIEWED AND RECOMMENDED FOR BOARD ACTION ~ CWB RJD <C<S Central Contra Costa Sanitary District BOARD OF DIRECTORS N~ IX. Budget & Financ 1n/?1/p.? POSITION nAPER I VIA: ROGER J. DOLAN r'""" General Manager-Chief Engineer SUBJECT DATE October 15, 1982 TYPE OF ACTION PROPOSITION 4 APPROPRIATIONS LIMIT Authorize Public Notice SUBMITTED BY Walter N. Funasaki INITIATING DEPT./DIV. Administrative/Accounting ISSUE: The Central Contra Costa Sanitary District is required to establish its appropriations limit in accordance with Article XIII B of the California Constitution. BACKGROUN D: General Requirements: Proposition 4 was approved on November 6, 1979, and was incorporated in the California Constitution as Article XIII B. Article XIII B, as implemented by Senate Bill 1352, limits appropriations of State and local governments to the appropriations of the 1978-1979 base year adjusted in each subsequent year for changes in the consumer price index and population. SB 1352 requires government agencies to establish their appropriations limit by resolution each year at a regularly scheduled meeting or a noticed special meeting beginning with the 1980-1981 fiscal year. Notice to the public of the availability of documentation in support of the appropriation limit must be given fifteen days prior to adoption. For 1980-1981, the appropriation limit was open to challenge within 60 days of the effective date of the resolution; for 1981-1982, and each fiscal year thereafter, the period in which a challenge can be commenced is 45 days of the effective date of the resolution. Key Assumptions: The following key assumptions have been used in interpreting the provisions of Article XIII B: o The District accounts for its activities in three separate funds: Running Expense Fund (General Fund); Sewer Construction Fund (Capital Fund); Debt Service Fund. The Running Expense Fund is considered to be an Enterprise Fund and is not subject to limitation under Propo- sition 4. Enterprise Funds are generally used to account for operations that are financed and operated in a manner similar to private business enterprises where the intent is that costs of providing goods or services to the public on a continuing basis be financed or recovered primarily through user charges. o Article XIII B defines "proceeds of taxes" as including, but not restricted to, all tax revenues, income from investment of tax proceeds, and the proceeds of regulatory licenses, user charges and fees to the extent that such proceeds exceed the reasonable cost of REVIEWED AND RECOMMENDED FOR BOARD ACTION INITIATING DEPT./DIV. GEN. MGR./CHIEF ENG. providing the regulation, product or service. IIProceeds of taxes II also include State subventions, other than those for mandated programs for which the state reimburses the local agency. SB 1352 further defined state subventions to include only money received by a local agency from the State, the use of which is unrestricted by the statute providing the subvention. Grant funds received from the state for capital projects are restricted to specific uses and are, therefore, not IIproteeds of taxesll. o Fund balances carried over into fiscal year 1980-1981 are generally subject to limitation unless they were appropriated into a reserve account prior to July 1, 1980; however, as the Sewer Construction Fund is a single purpose fund, the fund balance at June 30, 1981, can be construed as having been appropriated into reserves and, therefore, not subject to limitation. Computation of Appropriations: The District Appropriations Limits are computed on the following attachment: Attachment A - Appropriations Limit: 1979-1980, 1980-1981, 1981-1982 and 1982-1983. RECOMMENDATION: Authorize placement of a Public Notice advising that documentation used in the determination of the appropriation limit shall be available fifteen days prior to the Board of Directors Meeting to be held on November 18., 1982, at which the appropriations limit for the Sewer Construction Fund for the fiscal year 1982-1983 will be adopted. REVIEWED AND RECOMMENDED FOR BOARD ACTION INITIA:~: D~ CENTRAL CONTRA COSTA SANITARY DISTRICT Sewer Construction Fund (Capital Fund) Appropriations Limit 1979-1980, 1980-1981, 1981-1982 and 1982-1983 1978-1979 Appropriations Subject to Limitation 1979-1980 Appropriations Limit: CPI Change State Per Capita Personal Income Population Change Compound Effect: $4,697,644 x 1.1252 << 1980-1981 Appropriations Limit: CPI Change Per Capita Income Change Population Change Compound Effect: $5,285,789 x 1.1470 = 1981-1982 Appropriations Limit: Per Capita Income Change Population Change Compound Effect: $6,062,800 x 1.1127 = 1982-1983 Appropriations Limit: CPI Change Population Change Compound Effect: $6,746,078 x 1.0772 = 1.1017 1.1500 1. 0214 1.1017 x 1.0214 = 1.1252 $5,285,789 1.1468 1. 1211 1.0231 1.1211 x 1.0231 = 1.1470 $6,062,800 1.0912 1.0197 1.0912 x 1.0197 = 1.1127 $6,746,078 1.0679 1.0087 1.0679 x 10087 = 1.0772 $7,266,875 Attachment A $4,697,644