HomeMy WebLinkAboutAGENDA BACKUP 09-06-84
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
NO. I I I. BIDS & AWARDS
1 9 6 84
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
August 29,1984
SUBJECT TYPE OF ACTION
AWARD OF CONTRACT FOR DISTRICT PROJECT 20006 PLANT OPERATION AWARD CONTRACT
BUILDING ELECTRICAL MODICICATIONS FOR HVAC CHLORINE EXCLUSIO ,
AND AUTHORIZE $26,219 FROM THE SEWER CONSTRUCTION FUND
Dave Reindl
SUBMITTED BY
ISSUE: Sealed bids for District Project No. 20006 - Plant Operations Building
EI ectrl ca I Mod I f I cations for Heatl ng, Venti I atl ng, and A I r Cond I tl on I ng (HVAC)
Chlorine Exclusion were received on August 20, 1984. The Board of Directors must
award a contract or reject proposals within 60 days of the opening.
BACKGROUND: On July 26, 1984, the Board of Directors authorized funds for the
design of the Chlorine Exclusion Project. The project will modify the Plant
Operat Ions Pump and B lower Bu II ding HV AC Contro I System to prov I de automat I c
shutdown of ventilation equipment upon a signal from remote chlorine leak
detectors.
Plans and Specifications for the project were completed and advertisements
Inviting sealed bids were placed on Friday, August 3, 1984 and Wednesday,
August 8, 1984.
The District received three bids ranging from $11,501 to $15,447. The lowest
respons I ve bidder was A I hambra E I ectr I c. Th I s bid I s lower than the eng I neer' s
est I mate of $19,600 and ref I ects conservat I sm I n the eng I neer' s est I mate and a
competitive bidding situation. A tabulation of the bids Is attached.
A separate mechanical modification to the HVAC System Involves the Installation of
of Back Draft Dampers for the Pump and Blower Building fresh air fans. This work
has been arranged under a separate contract. The cost for this work Is Included
In the attached budget breakdown. $26,219 Is needed to complete the project
Including contract construction, construction management, engineering support, and
as-built drawings.
RECOMMENDATION: Award the contract for construction of District Project No. 20006
to Alhambra Electric per their bid of August 20, 1984 and authorize $26,219 In
Sewer Construction Funds for contract construction, construction management, and
contingencies.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
RB
INITIATING DEPT./DIV.
~. 1
.., ..
.. \I> ' ?' t.
DJR
f!#J
...^"._...._._---~..__.."~..._.,."._- ,,- _._.~_._. ....,.....-...-.--- ,..- ~-_.'+,-". ._-------~---_._.~,-,..,,_.,....~- ".,,, , ._---_._'-".~-....--.._....,._._-_.""--".._-_.._...._-,"--------_.,----,-----~----
POST BID ~RECONSTRUCTION ESTIMATE OF cosn
FOR
DISTRICT SEWERING PROJECT 20006
ITEM DESCRIPTION
4.
5.
6.
7.
8.
9.
10.
ITEM AMOUNT
1. Construction Contract (As Bid). . . . . . . . . . . .
la. Back Draft Damper Installation (Separate Contract)
lb. Back Draft Damper Materials
2. Estimated Construction Contingencies . . . . . .
3.
Estimated Construction Incidentals to Project Completion
Survey. . . . . . . . . . . . . . . . $ -0-
Inspection a'1d .Copstru.ctj 0'1 M.an~gE;me.nt. . $5.616.00
Engineering .In.c a/~l /.84. . . . . . . . . $2,200.00
Total Estimated Construction Incidentals
. . $ 7.816.00
Street Resurfacing or Seal Coat
TOTAL
. $11.501.00
3,922
2,000
. $ 3,485.00
$ 7,816.00
.:-
-0-
. . . . . . . .$
Total Estimate Required to Complete Project
Pre Bid Expenditures
Survey. Engineering, Printing, Advertising
Special Services
Right-ot-Way Acquisition.
. $ 9.995.00
. $ -0-
-0-
. $
Total Preconstruction Incidentals (as ot 7-31-84 ). . $ 9.995.00
Total Estimated Project Cost
(Items 5 & 7)
Funds Previously Authorized
. . . . . . .. .
Total Additional Funds Required to Complete Project.
(Item 8 minus Item 9)
.$28.724
$ 9.995 .00
. '.' $ 38,719.00
. $ 12.500.00
....
. $ 26,219.0'0 .
% CONST.
CONTRACT
6.6%
22%
12%
20%
32%
45%
- 165%
57%
222%
2050-8-78
s
~
~
\}
t; In
~ ~
c 0
li: ~
< lD
I-
~
In
<
d
l.)
<
!:
z
o
l.)
~
~
l.)
I
III
Z
o
~
..J
al
<
I-
o
a
~ ~
\1) '"
~. tl:
~ "-
~ \l-
~ ",.
~~
.~
~
~
~ ~
\.. \l
~ ~
~~
!
.!
'"
w
.~
Q)
Q)
.:
ell
c
W
,
(
~
~
I
~ ~ en
\ ' ~ ~
~ a
~\~ ~
, ::i::
;
~ ~
~
j:i
o
.,
-
iQ
o
I-
..Q)
.- U
C.-
::>.t
:!
~
-
..Q)
.- U
C._
::>""
0...
:!
~
..Q)
.- U
c.-
::>'"
a..
:!
o
I-
..Q)
.- U
C._
::>Q:
..Q)
.- U
C.-
::>Q:
13
>
'a;
o
Q)
a:
Q)
iO
o
I I I
\\
"
::::
~
\n
"(.
1\
~
~
~
~
1\
~
~
~
:!
~
c
.g
.9:
~
'"
Q)
o
i
~ ~
(
~ ~
~
~
\ ~
~ ~
\l
o
z
\\
~
E
~
....
~
~
In
"'C
~I
"'<.
~
~
~
'"
-<
.\
't
~ ~
~
~
~
~ ~
~ "
~
~
c ~
" \j
t\
"
~
'z
l\
"
~
"
'-
\\
~
I:P
l<)
'-
l
\)
~
~
I[
'<
~
~.
~
I
I Ie
.n
I
CIl
...
o
N
t\
r'..
~
~
~'
,
~\
,
~
,--
....
"!
~
"."
~
~.
"
l\
"~
'-0
~
"
-
...
iii
'0
I-
-.:I
iii
I
BOARD OF DIRECTORS
NO.
1
9/6/84
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
AUGUST 27, 1984
SUBJECT
RECEIVE AND ACKNOWLEDGE THE PROCEDURES FOR DESIGN OF
SEWER SYSTEMS IN HILLSIDE AND CREEK AREAS
TYPE OF ACTION
INFORMATION
SUBMITTED BY
JAY McCOY
INITIATING DEPT./DIV.
ENGINEERING DEPT./CONSTRUCTION DIVISION
ISSUE: It Is necessary to control the locations and types of sewer pipes
wh I ch w III be I nsta II ed In hili s I de and creek areas so that future
adverse effects of sl Ides and bank erosion wll I be minimized.
BACKGROUND: The District's collection system was extensively damaged by
landsl Ides and erosion during the winters of 1982-83 and 1983-84. It has
become apparent that a need ex I sts to forma II ze current po II c I es and
develop written criteria and procedures for avoiding new sewers which are
proposed to be Installed In potentially unstable areas. With such
criteria and procedures, the damage from landslides and erosion wll I be
greatly reduced.
The attached procedures have been prepared to minimize potential future
damage from landslides and erosion. Job engineers will be required to
prepare and submit soils reports which wll I delineate suspected problem
areas for al I hillside developments. If necessary, special geotechnical
evaluations wll I be required along specific sewer alignments to Identify
and prov I de for the correct I on of unstab I e areas. Eng I neers w III be
required to meet certain dimensional standards (which are Included In the
procedures) to minimize the effects of erosion on pipeline Instal lations.
The proposed procedures have been rev I ewed by the Bu II ding Industry
Association, and their comments have been Incorporated. The procedures
are being presented to the Board for information. No formal action is
req u I red. Staff w II I I ncorporate any comments the Board may have and
Inform al I design engineers of the new requirements.
RECOMMENDATION: ACknowledge and comment on the procedures for design of
sewer systems in hillside and creek areas.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
RJD
NG D}%'1.DIV.
/4~t
JSM
J2ft-e
RAB
CENTRAL CONTRA COSTA SANITARY DISTRICT
PROCEDURES TO BE FOLLOWED FOR
DESIGNING SEWERS TO BE LOCATED IN HILLSIDE AND CREEK AREAS
1. Soils reports wll I be required where:
a. Slopes of hills where sewers are proposed for Installation
exceed 1 5 per cent.
b. Sewers are proposed for Installation within 50 feet of
creekbeds.
c. Sewers are proposed for Instal Jatlon within the range of
Influence of a possible landsl Ide from adjacent hll I.
d. Sewers are proposed for Installation In historical sl Ide
locations.
2. A soils report prepared by a registered Civil Engineer practicing In
Geotechnical Engineering must be submitted by the Job engineer which
covers the proposed project.
3. If the project geotechnical report provided does not cover an
off-road sewer alignment, the District may require a supplementary
report. This report, at a minimum, must address the fol lowing:
a. Supplementary geological setting, general soils and bedrock
conditions along the proposed sewer alignment, and recommended
set backs from sl Ides and creeks.
b. Stabl II Ity or Instability of selected sewer alignment.
c. Potential ground water problems.
d. Effect of trenching on slope stabllllty (negative Impacts on
s lope) .
e. Spec I a I backf III, spec I a I trench I ng req u I rements, or spec I a I
supports that may be recommended.
f. Erosion potential of soils around sewer near water courses.
g. Recommended corrections If an Instability exists or may
develop.
4. Installation of sewers In unrepalred sl Ide areas Is to be avoided.
a. If an acceptable gravity route Is feasible around the
unrepalred slide, the sewer must be Instal led around the sl Ide.
b. If the only feasible gravity route is through a slide area, a
complete study of the slide must be made by a Geotechnical
Engineer. The Geotechnical Engineer must propose a solution
which is satisfactory to the District. The normal solution is
the repair of the slide.
c. If a satisfactory gravity solution does not exist, the pumping
of sewage from individual homes will be considered.
5. The Project Engineer must furnish a map which shows existing creeks
or swales which may convey water in the vicinity of any proposed
sewer main alignments.
6. Sewers shall not be designed to be located in the bottom of swales
or creeks.
7. For sewers which will be parallel to swales or creeks, the sewer
must be designed far enough away from the drainageway to eliminate
the possibility of future eroding around the sewer. A Geotechnical
Engineer shall review the proposed alignment and furnish
recommendations regarding long-term erosion potentials.
a. If it is unfeasible to locate sewer mains on the downslope side
of future homes and maintain a safe distance from drainage
ways, consideration will be given to installing the sewers in
street areas which may result in the installation of
residential sewage pumps on individual homes.
8. For sewers which cross creeks or swales, the crossing shall be as
nearly perpendicular to the drainageway as feasible.
a. Bank and bottom protection shall be designed per the
recommendation of a Geotechnical Engineer and shall be
installed in the drainageway as a part of the overhead or
underground crossing.
b. The Project Engineer shall pay particular attention to
designing adequate support foundations and protection for the
foundation.
9. An access easement (mnimum width of ten feet) shall be granted by
the developer from the nearest public street to the creek crossing
structure along the route of the sewer main, if possible, for future
maintenance.
10. The attached design standards shall be used by the Project Engineer
when designing sewers in hillside and/or creek areas.
DESIGN STANDARDS
APPLICABLE TO
SEWERS WHICH ARE TO BE LOCATED IN HILLSIDE AND
CREEK AREAS
1. Sewers to be installed across hillside slopes (generally parallel to
contours) shall be ductile iron (no bedding) if the cross slope of
the hill exceeds 25 percent.
2. Sewers to be installed parallel to defined creeks shall be located
no closer than 20 feet from the top of the bank if the creek bank is
defined; if not, no closer than 30 feet from the centerline of the
creek.
3. Sewers to be installed parallel to defined creeks from 20 to 50 feet
away from the top of the bank shall be ductile iron (no bedding).
4. Manholes to be installed on either ends of creek crossings shall be
located no closer than 20 feet from the top of the creek bank.
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
NO. V. ENGINEER
2 9/6/84
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
AUGUST 24, 1984
SUBJECT
APPROVE AND AUTHORIZE THE EXECUTION OF A LICENSE
AGREEMENT WITH INDUSTRIAL TANK CORPORATION (I.T.)
TYPE OF ACTION
APPROVE AGREEMENT
JAY McCOY
INITIATING DEPT./DIV.
ENGINEERING DEPT./CONSTRUCTION DIVISION
SUBMITTED BY
ISSUE: A license agreement with I.T. is needed to permit I.T. to construct,
reconstruct, maintain, and operate two waste transmission pipes across District-
owned property.
BACKGROUND: The District owns a strip of property near the east end of I.T.'s
treatment plant. The District's outfall pipel ine is located within this strip
of land. I.T. has installed two above-ground, steel pipel ines over the District's
property. The District and I.T. have negotiated a 1 icense agreement which
provides for I.T.'s installation, operation, and maintenance of the pipel ines,
a $600 per year payment to the District for use of the land, I.T. keeping the
land free from waste, and I.T. bearing the costs of relocation or removal of
the pipel ines. The 1 icense has been signed by I.T. and is being forwarded to
the Board for approval and authorization for the President of the Board and
Secretary of the District to sign.
RECOMMENDATION: Approve and authorize the execution of a 1 icense agreement
with I.T.
RAB
fJIrrj
~
AC.. E 'tLL co.....
12'5.1' AC.
\
I,
I
t
.. t" ,H
BOARD OF DIRECTORS
NO. V. ENGINEERING
3 9/6/R4
OS ON nAp I VIA: ROGER J. DOLAN
P ITI r"'I""l ER General Manager-Chief Engineer
DATE
SUBJECT
August 31, 1984
TYPE OF ACTION
AUTHORIZE $30,000 IN SEWER CONSTRUCTION FUNDS FOR OUTFALL
INSPECTION AND REPAIR PROJECT
AUTHORIZE FUNDS
SUBMITTED BY
John Larson, Engineering Division Manager
INITIATING DEPT./DIV.
Engineering Department
ISSUE: An authorization of $30,000 is required to complete the planning phase of the
Outfall Inspection Project.
BACKGROUND:. Treated effluent from the District1s treatment plant is discharged to
Suisun Bay via a four mile long outfall that was built in 1958. The outfall has
experienced leaks at several locations, most notably near the Industrial Tank
evaporation ponds. A major cause of the leaks appears to be settlement induced by
levees and other earthwork which have been placed over or adjacent to the outfall
since 1980. The settlement has caused joint separation in an unknown number of the
approximately 2,000 joints in the outfall. An inspection of the condition of the
outfall is needed at this time to determine the number of bad joints. The inspection
is tentatively scheduled for the end of September.
This authorization would provide the money to complete planning for the inspection
and repair effort and would authorize a previous General Manager-Chief Engineer
$5,000 work order authorization. Additional funds to cover the in-pipe inspection
and repairs will be requested when planning for the project is complete.
RECOMMENDATION: Authorize $30,000 in Sewer Construction Funds for the Outfall
Inspection and Repair Project.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
JAL
~
RAB
GEN.JG:~(cjHIEF ENG.
J~~jL
RJD
INITIATING DEPT./DIV.
District
BOARD OF DIRECTORS
4
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
SUBJECT
AUTHORIZE EXECUTION OF AGREEMENT WITH DAVID M. GRIFFITH AND
ASSOCIATES FOR GRANTS ADMINISTRATION SERVICES AND AUTHORIZE
$16,000 FROM THE SEWER CONSTRUCTION FUND
Au ust 31, 1984
TYPE OF ACTION
AUTHORIZE CONTRACT
AUTHORIZE FUNDS
SUBMITTED BY
Curtis W. Swanson, Senior Engineer
INITIATING DEPT./DIV.
Engineering Department
ISSUE: Authorization is required for the General Manager-Chief Engineer to execute
an agreement with David M. Griffith and Associates to assist in developing indirect
cost rates for District force account work on Clean Water Grant projects. An
authorization of Sewer Construction Funds is also required.
BACKGROUND: The District has received State and Federal Clean Water Grants for the
Stage 5A and 5B projects. Under the grant program regulations, the District may be
reimbursed for certain force account costs related to these projects. Potential
grant eligible force account costs that have been or will be incurred are in excess
of $1.19 million. Indirect costs associated with District staff efforts may also
be reimbursed provided that the indirect cost rates are approved by the State Water
Resources Control Board (SWRCB). Grant eligible indirect cost rates range from
20 to 35 percent of direct costs. Thus, the District has an opportunity to recover
from $238,000 to $416,000 for overhead costs.
Staff proposes to retain David M. Griffith and Associates (DMG) to assist in
developing indirect cost rates for several fiscal years and obtaining approval of
these rates from SWRCB. DMG will provide these grant administration services on a
lump sum basis for a total cost of $16,000.
DMG was selected to provide these services because of their extensive experience in
developing indirect cost rates for various State and Federal programs, including the
Clean Water Grant Program. DMG has provided services to half of the counties, most
major cities, and many special districts in California.
The cost of the grant administration services provided by DMG is not eligible for
grant funding. However, their work product will enable the District to seek
reimbursement of a substantial amount of indirect costs.
RECOMMENDATION: Authorize the General Manager-Chief Engineer to execute the
agreement with David M. Griffith and Associates for grant administration services.
Authorize $16,000 from the Sewer Construction Fund for these services.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
CWS
RAB
L~
\~NF
~
cc{S
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
G NEERING
5 9 6 84
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
SUBJECT AUTHORIZE GM-CE TO EXECUTE CONTRACT AGREEMENT WITH
JOHN CAROLLO ENGINEERS TO COMPLETE STAGE 5B PLANS AND SPECI-
FICATIONS AND AUTHORIZE $33,100 FROM SEWER CONSTRUCTION FUNDS.
Au ust 31 1984
TYPE OF ACTION
AUTHORIZE AGREEMENT
AUTHORIZE FUNDS
SUBMITTED BY
JOHN LARSON
INITIATING DEPT./DIV.
ENGINEERING DIVISION
ISSUE: Board approval is required for the GM-CE to execute a contract amendment with
John Carollo Engineers. Board authorization is required for sewer construction funds.
BACKGROUND: The Board of Directors approved a lump sum contract with John Carollo
Engineers (JCE) in 1982 to complete plans and specifications for the Stage 58 Project.
The total lump sum price was $438,000. The estimated construction cost is $6,000,000.
The 90% plans and specifications were completed in 1982 and were submitted to SWRCB
for grant funding. On July 9, 1984, the State Water Resources Control Board gave its
approval to complete the design. JCE is currently working under the existing lump sum
contract to finish the plans and specifications described in the initial scope of work.
The 2-1/2 year delay in SWRCB approval has caused an increase in design administration
costs. In addition, a change of circumstances has resulted in the need for some
design changes. Consequently, an amendment to the lump sum price has been negotiated
with JCE for an additional $33,100. This increase covers additional work required to
obtain SWRCB approval, new work to reflect current conditions, new work to meet SWRCB
requirements, and the increased labor and overhead incremental costs for the remainder
of the existing lump sum contract. A summary of the costs is attached. This work is
to be completed by the end of October.
To avoid further delays, the District elected to proceed with Stage 58 design without
waiting for grant funding approval. This amendment is therefore not covered by clean
water grant funding.
RECOMMENDATION: Authorize the GM-CE to execute a contract amendment with John Carollo
Engineers to complete the Stage 58 plans and specifications and authorize $33,100
from sewer construction funds.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
f;x- j L
JAL
m
NITIATING DEPT./DIV.
RAB
PLANS AND SPECIFICATIONS
STAGE 5B
CONTRACT AMENDMENT COST SUMMARY
Additional work to support
SWRCB approval
$ 1,300
New work to meet current
conditions:
o Project status review
o Combine D.A.F. and hydraulic
expansion contracts into
one document
o Add MUX connections
6,800
6,000
12,500
New work to meet SWRCB
requirements
Increased labor and overhead
4,000
2,500
TOTAL
$ 33 , 1 00
BOARD OF DIRECTORS
9/6/84
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
August 29, 1984
SUBJECT
TYPE OF ACTION
AUTHORIZE GENERAL MANAGER-CHIEF ENGINEER TO EXECUTE
AGREEMENT WITH URBAN ALTERNATIVES
AUTHORIZE AGREEMENT
SUBMITTED BY
James M. Kell
Division
Division
ISSUE: Authorization is required for the General Manager-Chief Engineer to execute
a contract with Urban Alternatives (U.A.) to provide public participation services
for the District Solid Waste Management Project.
BACKGROUND: On June 28, 1984, the Board authorized $190,000 in Sewer Construction
Funds to conduct the District Solid Waste Management Project. One important element
of this project is the public participation program. The public participation
consultant will perform the lead role in formulating and implementing the District's
public participation program. Public participation is a highly specialized field.
The District staff interviewed several experts in the field to develop the overall
public participation approach and to determine candidate consultants. The candidate
consultants were interviewed; U.A. is recommended to be engaged to perform the lead
role in public participation based upon both excellent qualifications and references
for public participation in projects similar to the Solid Waste Management Project.
U.A.'s Scope of Work will include establishing the method of disseminating
information about the project; establishing workshop and meeting sites; disseminating
general information and notifications of meetings; preparing agenda, mailers, and
graphics for meetings, conducting meetings, and preparing summary reports of the
meetings; and assist the District staff in preparing the public participation portion
of the Summary Report.
District staff has prepared a Scope of Work and has conducted contract negotiations
with U.A. The contract with U.A. is on a per diem basis with a $23,309 cost ceiling.
No additional Sewer Construction Funds are needed as the $23,309 was part of the
original $190,000 authorization.
RECOMMENDATIONS: Authorize General Manager-Chief Engineer to execute contract with
Urban Alternatives to provide public participation consultation for the District
Solid Waste Management Project. The contract will be on a per diem basis with a
$23,309 cost ceiling. No funds are requested in this authorization.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
JMK
RAB
NG.
INITIATING DEPT./DIV.
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
No.VI. W.P. CONTROL PLAN
1 9 6 84
DATi:
AUgust 30, 1984
SUBJECT
TYPE OF ACTION
AUTHORIZATION OF $10,000 IN SEWER CONSTRUCTION
FUNDS FOR A MOISTURE/SOLIDS ANALYZER.
AUTHORIZE FUNDS
SUBMITTED BY
Charles W. Batts
INITIATING DEPT.!DIV.
Plant Operations Department
ISSUE: The Plant Operations Department requests authorization of $10,000
from Sewer Construction Funds to purchase a Multiple Sample
Moisture/Solids Analyzer .
BACKGROUND: An important operational parameter in the sludge handling
process is sludge cake dryness. The Plant Operations Department reports
the sludge cake percent solids through the Acme Landfill to the Regional
Water Quality Control Board, as part of the requirements for landfill
disposal. Normally such measurements are done by the Solids Conditioning
Building operator using an "Ohaus" balance and taking several hours to
dry multiple samples. Currently there are two other important reasons to
measure the percent of moisture/solids in dewatered sludge; first~ such
feedback would facilitate polymer conservation allowing the centrifuge
operator to maintain required solids concentration with minimal polymer
usage. Second, rapid solids analysis will be critical to furnace
operation; sludge feed to the multi-hearth incinerator should be
maintained as constant as possible. Variations in sludge feed to the
furnace can cause air emmissions violations or excessive natural/landfill
gas consumption if the sludge cake is too wet.
The Plant Operations Department has identified a system that will allow
rapid drying and analysis of dewatered sludge samples with minimum sample
handling. Such a system would also allow more efficient use of operator
time and reduce sampling errors. This system combines unique microwave
technology with digital computer electronics; the unit has mul ti-sample
capability. This system would be a sole-source purchase from CEM
Corporation and would cost approximately $10,000. The Plant Operations
Department has examined this piece of equipment during the furnace test
and found the system applicable for sludge moisture/solids analysis. If
such a system resulted in a two percent savings in polymer and landfill
gas consumption, it would pay for itself in less than one year.
RECOMMENDATION: Authorization of $10,000 in Sewer Construction Funds for
a moisture/solids analyzer.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INITIAIT[E
CWB
.!DIV.
BOARD OF DIRECTORS
NO. VII. LEGAL/LITIGATION
1 9 6 84
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
August 31, 1984
SUBJECT
APPROVE $40,000 PAYMENT FOR BARBARA BLUME LANDSLIDE
SETTLEMENT AGREEMENT FROM THE O&M CONTINGENCY ACCOUNT
TYPE OF ACT ION
LEGAL/LITIGATION
SUBMITTED BY
Jack E. Campbell
INITIATING DEPT./DIV.
Risk Management and Safety
ISSUE: The settlement of the Blume case is proceeding and the payment of the District's
portion should be made from the O&M contingency account which was establ ished for the
1984-85 budget year. Expenditures from this account require Board approval.
BACKGROUND: The proposed Blume settlement agreement was presented at the July 26, 1984
adjourned Board Meeting. The Board approved the $40,000 District share, and it now
appears that this settlement will be consummated. One of the expense categories
proposed for the newly establ ished O&M contingency account was for large claim
settlements, and the overall 1984-85 budget was set up accordingly. The Board retained
specific approval authority for this account and the staff requests payment of the
$40,000 Blume settlement from it.
RECOMMENDATION: Approve payment of the $40,000 Blume landsl ide settlement from the
1984-85 O&M contingency account.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INll~AQG DEPT./DI'\I.
". (R-
JEC
PM