HomeMy WebLinkAboutAGENDA BACKUP 11-20-86
.
Cent:
Contra Costa San ita ')istrict
BOARD OF DIRECTORS
PAGE 1 OF 2
POSITION
PAPER
BOARD MEETING OF
November 20 1986
NO.
V.
CONSENT CALENDAR
1
ACCEPT THE CONTRACT WORK FOR INSTALLATION OF
THE WATERSHED 44 WEST TRUNK PARALLEL (D.P. 4093)
AND AUTHORIZE FILING OF THE NOTICE OF COMPLETION
DATE
November 7, 1986
TYPE OF ACTION
SUBJECT
ACCEPT CONTRACT
WORK
SUBMITTED BY
Ron Klimczak, Senior Engineer
INITtA T1NG DEPT./DIV.
Engineering Department
Construction Division
ISSUE: Work has been completed on the installation of the new trunk sewer
facility in the area of North Concord and the work is now ready for acceptance.
BACKGROUND: A Facil ities Pl an for the sanitary sewer facil ities in the North
Concord/Clyde area (Watershed 44) identified the need to install a trunk sewer
parallel to the existing 12-inch sewer in Bates Avenue near Arnold Industrial Way.
District Project No. 4093 consisted of the installation of approximately 3,900
lineal feet of 18-inch gravity sewer pipeline together with 10 trunk manholes as
shown on Attachment 1.
MGM Construction Co. of Concord was issued a Notice to Proceed on September 3,
1986. The contract completion date was November 7, 1986. All contract work was
substantially completed on or before the specified contract completion date. It
is appropriate to accept the contract work at this time. A detailed accounting of
the project cost will be provided to the Board at the time of project closeout.
RECOMMENDATION: Accept the contract work for construction of the Watershed
44-West Trunk parallel project (District Project 4093) and authorize the filing of
the Notice of Completion.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INITIA TING DEPT./DIV.
'~ ~;1f
13n.49'35 RK JM RB
. .~__~_~_,_,,~,~_~,"'M_'M"'~~_"~___' ...,....'_,'"....m~"__.__..,.~___,_..~"..__.~~.,..,_,_.____.,__,~".___,____..,..__._.__'_~______._._____
SYSTEM MAP
SCALE: 1"= 600'
Page 2 of 2
District Project No. 4093
West Trunk Parallel'
Watershed 44
.,
Centl.. Contra Costa Sanital" District
BOARD OF DIRECTORS
PAGE 1 OF 2
POSITION
PAPefi
BOARD MEETING OF
November 20, 1986
NO.
V. CONSENT CALENDAR 2
SUBJECT
ACCEPT THE CONTRACT WORK FOR THE STORM DAMAGE REPAIR
PROJECT AT RAINTREE PLACE, LAFAYETTE (DP 4060) AND
AUTHORIZE FILING OF THE NOTICE OF COMPLETION
DATE
November 6, 1986
TYPE OF ACTION
ACCEPT CONTRACT
WORK
SUBMITTED BY
Thomas Trice, Engineering Assistant
INITIATING DEPT./DIV.
Engineering Department
Construction Divison
ISSUE: Construction has been completed on the Storm Damage Repair Project at
Raintree Place, Lafayette CDP 4060) and the work is now ready for acceptance.
BACKGROUND: Heavy rains during the winter storms of 1982-1983 damaged the
District's 8-inch sewer crossing at Reliez Creek behind the residence at No. 926
Raintree Place in Lafayette. Approximately 90 properties are served by this
sewer.
This project included the construction of 100 lineal feet of 8-inch pipe to cross
Rel iez Creek, using a box girder for support, as well as the installation of
another 100 1 ineal feet of buried 8-inch pipe with appurtenant structures. The
existing creek crossing was removed. Attachment 1 is a location map of the
project.
Pacific Mechanical Corporation of Concord was issued a Notice to Proceed on
September 16, 1986. The contract completion date was November 1, 1986. All
contract work was substantially complete on that date. It is appropriate to
accept the contract work at this time. A detailed accounting of the project cost
will be provided to the Board at the time of project closeout.
RECOMMENDATION: Accept the contract work for the construction of the Storm Damage
Repair Project at Raintree Place, Lafayette COP 4060) and authorize the filing of
the Notice of Completion.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
1)1
Pff!J
RAB
INITIATING DEPT./DIV.
13:r.?,a.9'85
-r;rn-
TAT
~
RSK
JSM
~
AtTACHMENT 1
DP 4060 - RAINTREE PLACE, LAFAVt:IIE
PROJECT PLOT PLAN
S u 8
50/h
zo
19
JACKSO}J
I
I~
Ill'\
s:..
~
~
~
~
-
C"'"
c-
~
~
~
M'l
- STR- 3 t/6./5
~
14~
~
/5
.
Centr( Contra Costa Sanital District
BOARD OF DIRECTORS
PAGE 1 OF 3
POSITION
PAPER
BOARD MEETING OF
November 20. 1986
NO.
v.
CONSENT CALENDAR 3
SUBJECT
ACCEPT THE CONTRACT WORK FOR THE STORM DAMAGE REPAIR
PROJECTS AT HILLCREST DRIVE. ORINDA AND MORAGA SLIDE
I-A, MORAGA CDP 3886 AND DP 4223) AND AUTHORIZE
FILING OF THE NOTICE OF COMPLETION
DATE
November 10, 1986
TYPE OF ACTION
ACCEPT CONTRACT
WORK
SUBMITTED BY
Thomas Trice, Engineering Assistant
INITIA TING DEPT.lDIV.
Engineering Department
Construction Division
ISSUE: Construction has been compl eted on the Storm Damage Repair Projects at
Hillcrest Drive, Orinda and Moraga Slide I-A, Moraga and the work is now ready for
acceptance.
BACKGROUND; The project consisted of slide damage repairs at two locations within
the District (see Attachments 1 and 2).
The Hillcrest Drive, Orinda, sl ide repair work consisted of excavating
approximately 1,000 cubic yards of loose material from the slope and replacing it
as engineered fill. A subdrain system was installed to take ground water to the
street and approximately 90 lineal feet of an existing 6-inch clay pipe sewer line
in the slide area was replaced with 6-inch ductile iron pipe. Two existing side
sewers were reconnected and the enti re work area was hydroseeded. The two
property owners affected by the sl ide repair are satisfied with the completed
project~ have contributed the total amount of funds outlined in the Agreement with
the District, and have signed the appropriate release.
The Moraga I-A slide repair work consisted of excavating and grading approximately
300 cubic yards of material on the existing slope and installing 66 gabion
mattresses (6'x9'x9") filled with rock on the graded slope to protect it from
erosion. Various other drainage improvements were made to direct the surface
run-off water away from the slope.
Fanfa, Inc. of San Lorenzo was issued a Notice to Proceed on September 10, 1986.
The contract completion date was November 11, 1986. The contractor completed the
work on both projects on October 29, 1986, two weeks ahead of the contract
completion date. It is appropriate to accept the contract work at this time. A
detailed accounting of the project costs will be provided to the Board at the time
of project closeout.
RECOMMENDATION: Accept the contract work for construct i on of the Storm Damage
Repair Projects; Hillcrest Drive, Orinda (DP 3886) and Moraga Slide I-A, Moraga
(DP 4223) and authorize the filing of the Notice of Completion.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INlTlA TlNG DEPT.lDIV. r!1fJ
~ '~
13:m' .9!85
TAT RSK JSM RAB
ATTACHMENT 1
STORM DAMAGE REPAIR
HILLCREST DR., ORINDA
JOB NO. X3886
ATTACHMENT 2.
t-
+
Q
T
JOBSITE
ACCESS
+
"
f-
i
f~ _ .....
1- --
PROJ~CT
LOCATION_
1
-I
STORM DAMAGE 1 A
MORAGA TRUNK SEWER
ST. MARY'S RP RD., LAFA YETTE
JOB NO. X4223
L
.
Centre - Contra Costa Sanitar District
BOARD OF DIRECTORS
PAGE 1 OF 2
POSITION
PAPER
BOARD MEETING OF
November 20, 1986
NO.
v.
CONSENT CALENDAR 4
SUBJECT
ACCEPT THE CONTRACT WORK FOR INSTALLATION OF THE
ESCOBAR STREET SEWER REPLACEMENT (DP 4236) AND
AUTHORIZE FILING OF THE NOTICE OF COMPLETION
DATE
November 17, 1986
TYPE OF ACTION
ACCEPT CONTRACT
WORK
SUBMITTED BY
Ron Klimczak, Senior Engineer
INITIATING DEPT.lDIV.
Engineering Department
Construction Division
ISSUE: Construction has been completed on the installation of the Escobar Street
Sewer Replacement in Martinez and the work is now ready for acceptance.
BACKGROUND: District sewer facil ities in Escobar Street were deficient and in
need of replacement. The city of Martinez was in the process of reconstructing
Escobar Street including the replacement of the Alhambra Creek Bridge. An
opportunity was presented to remedy the sewer deficiencies concurrently with the
city's work on Escobar Street. District staff developed a solution which involved
redirecting sewage flows to a nearby gravity system.
This project provided for the install ation of approximately 210 1 ineal feet of
8-inch and 14-inch diameter sewer main, 240 1 ineal feet of 4-inch and 6-inch
diameter sewer laterals, and other appurtenant structures. Attachment No.1 shows
a plot plan of the project area.
Billings Plumbing, Inc. of Martinez was issued a Notice to Proceed on September
29, 1986. The contract completion date was October 31, 1986. All contract work
was substantially completed on October 20, 1986. It is appropriate to accept the
contract work at this time. A detailed accounting of the project cost will be
provided to the Board at the time of project closeout.
RECOMMENDATION: Accept the contract work for installation of the Escobar Street
Sewer Replacement in Martinez (District Project 4236) and authorize the filing of
the Notice of Completion.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
13:>:>".9!85
RSK
JSM
RAB
INITIA T1NG DEPT.lDIV.
~
'J/
ATTACHMENT' 1
ESCDBAR STREET SEWER REPLACEMENT
DISTRICT PROJECT 4236
CITY OF MARTINEZ
G
RAILROAD
SYSTEM M~e...
N.T.S.
LEGEND
--- EXISTING SEWER
- NEW SEWER
-.-.- ABANDONED SEWER
o NEW MANHOLE
C EXISTING MANHOLE
.
Centre Contra Costa Sanitar District
BOARD OF DIRECTORS
PAGE 1 OF 3
POSITION
PAPER
BOARD MEETING OF
e
NO.
v. CONSENT CALENDAR 5
DATE
SUBJECT
ADVISE THE BOARD OF THE CLOSE OUT OF THE
REPLACEMENT OF EXISTING DEFICIENT SEWER FACILITIES
PROJECT IN MARTINEZ AND ORINDA CDP 4054) AND
AUTHORIZE AN ADDITIONAL $5,930 FROM THE SEWER
CONSTRUCTION FUND
November 12 1986
TYPE OF ACTION
AUTHORIZE FUNDS
SUBMITTED BY
Ron Klimczak, Senior Engineer
INITIATING DEPT.lDIV.
Engineering Department
Construction Division
ISSUE: All work has been completed on the Replacement of Existing Deficient Sewer
Facilities Project in Martinez and Orinda, and this project can now be closed.
Additional funds are required to cover the total actual project costs.
BACKGROUND: This project included the replacement or paralleling of existing
deficient sewer facilities at four sites within the District, described in more
detail on Attachment 1. These sites were identified as having sewers with
existing deficiencies which were contributing to high maintenance costs or were
causing overflows of sewage on private properties.
The Contractor, Gallagher and Burk, commenced work on June 4, 1986. The contract
completion dates were July 25, 1986 for the Glorietta Boulevard site and September
5, 1986 for the remaining three sites. All contract work was substantially
completed on or before the specified contract completion dates. The project was
accepted by the Board on September 18, 1986.
The engineer's estimate for the construction project was $229,400. Gallagher and
Burk's ori gi nal construction contract was for $197,942. There were two change
orders issued on the project totaling $34,097 and the contract amount was
increased by an additional $5,654 because of increases in quantities of bid items
paid at contract unit prices. The factors responsible for the additional
construction costs are presented in Attachment 2. The total contract amount
paid to Gallagher and Burk was $237,693. The total budget for the project was
$253,086. The total completed project cost is $259,016, which is $5,930 more than
budget. An additional $5,930 is needed from the Sewer Construction Fund so that
staff may closeout the project.
RECOMMENDATION: Authorize an additional $5,930 from the Sewer Construction Fund
to cover the total project costs for the Replacement of Existing Deficient Sewer
Facilities Project in Martinez and Orinda <DP 4054) so that the project account
can now be closed.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
13:12/19.'65
RSK
JSM
RAB
~
I)j
tlfB
INlTlA TING DEPT tDIV.
ATTAQi~NT I
REA..ACEf.ENT OF EXISTING DEFICIENT SEWER FACIL !TIES ffiOJ ECT
SOOPE OF WOOl<
COP 4054)
SITE A: ULFlNIAN WAY, f.V\RTINEZ - All existing, damaged 6-inch sewer main located
under an apartment bulld1ng in Martinez was relocated using 250 feet of 8-inch
sewer pipe. Also included was the reconnection of three existing bulldings to
the row system. The restoration of the area 1ncl uded repl acement of 1,400 square
feet of concrete drivet.'ay together with a minor anount of creek slope protection.
SITE B: MORflGA WAY, <lUNDA - An existing deficient section of 12-1nch trunk sewer
on Moraga Way in Orinda was paralleled with 72fJ feet of row 18-inch trunk sewer.
SITE C: GLOOIETTA BooLEY M.D, ORINDA
lO-1nch sewer mai n was repl aced with
addi ti on, four new manhol es were
reconnected.
- Several secti ons of defici ent exi st i ng
800 feet of new la-inch sewer pipe. In
constructed and several 1 ateral 5 were
SITE D: L<l'IER OOINDA ruM=' STATION - A portion of an existing IS-inch trunk sewer
upstream of the Lower Orinda pump station was replaced with l~ feet of 18-inch
ductile iron pipe. Also, an existing trunk manhole at the edge of a creek bank
was supported and protected with approximately 1300 sacks of concrete ri p- rap.
ATTAOiMENT 2
FACTORS CONTRIBUTING TO THE ADDITIONAL $5,930 IN PROJECT COSTS
<DP 4054)
1. The original project design for the new parallel trunk sewer in Moraga
Way, Orinda (Site B) was for a IS-inch diameter sewer. Based on data
subsequently generated from the District-wide COM trunk sewer capacity
study, higher potential ultimate flows were identified which would
contribute to this new trunk sewer. Consequently, a decision was made
to upsize the new trunk sewer to an 18-inch di ameter system at an
additional cost of $7,009.
2. The original project design for the Glorietta Boulevard sewer
install ation work in Orinda (Site C) provided for the repl acement of
approximately 760 feet of deteriorated existing lO-inch sewer. Three
additional locations were identified subsequent to the awarding of the
construction contract where the existing lO-inch system had excessive
sags which were contributing to maintenance problems and reduced
capacity. Since the county would be repaving Glorietta Boulevard upon
completion of the sewer work, the decision was made to correct the
additional deficiencies at this time. The total cost of this extra work
was $27,088.
3. Numerous problems were encountered with unmarked utilities in Glorietta
Boulevard (Site C>' At one point, converging util ity 1 ines within the
proposed sewer trench al ignment prevented continuing with the original
design. The alignment was revised and the contractor was paid additional
money for delay and rework based on contract unit prices.
4. Various increases in actual installed quantities of material were
necessary to accomplish the original design intent at both Ulfinian Way
(Site A) and the Lower Orinda Pump Station (Site D). For example, at the
Ulfinian Way site, a slightly larger than anticipated replacement
driveway slab was installed to satisfy the property owner. At Site D,
the actual installation of the sacked concrete slope protection required
1,300 sacks versus the 1,200 anticipated. These changes in quantities
were paid for at the established contract unit prices.
.
Centre Contra Costa Sanitar District
BOARD OF DIRECTORS
PAGE 1 OF 2
POSITION
PAPER
BOARD MEETING OF
November 20, 1986
NO.
V. CONSENT CALENDAR 6
DATE
November 13, 1986
SUBJECT
EXECUTE "CONSENT TO COMMON USE" AGREEMENT
WITH PG&E - JOB NO. 4250 - LAFAYETTE AREA
TYPE OF ACTION
APPROVE CONSENT TO
COMMON USE
SUBMITTED BY
Dennis Hall, Associate Engineer
INITIATING DEPT.lDIV.
Engineering Department/
Construction Division
ISSUE: A publ ic sewer has been installed within an existing PG&E easement. A
"Consent to Common Use" is required to permit the District to cross PG&E's
easement.
BACKGROUND: The subject Agreement will permit the publ ic sewer to cross PG&E's
easement while protecting PG&E's prior rights. The Agreement protects both
parties' interests in the "consent area" from actions of the other party.
The public sewer was recently installed by the District's contractor in
conjunction with the repair of the landslide in the Sky Hy Subdivision in
Lafayette.
RECOMMENDATION: Approve the Consent to Common Use with PG&E, Job No. 4250,
authorize the President of the District Board of Directors and the Secretary of
the District to execute said document (in duplicate).
REVIEWED AND RECOMMENDED FOR BOARD ACTION
13:>~1' .9.'65
-&t'
DH
hI{J
GEN MGR/CHIEF ENG.
I
INITIA TlNG DEPT.lDIV.
JM
RAB
Sire
G
N I
~
I,
.....-
o'
1'.32..0
€ 11..5~ .- ,,t!'
SLJt3-rp.i?CfiL
~ /.
L:,">;:~~>,
/./ ,cOn"?>
./ Ow!>..
"-\..1.-0'- ./
'5~'l1\ ./"
:!J':J Ii "
/ 4> ;<.
t,1I", ./
~tfl. '" br ./
,pGll-O fl.:?! ./
\00 1'3.0 0 ~ d
~/ ~/OOI RG., e
lEA $c/VI EN!
1.1'
~
--<--
-~
-y~",\ ..-s.:::
1.1' 0
o~
c:- ""0
~~
<:'~
~,
----
N
I,
.....-
N
0
Ul
:J>
./ /
./ .
./ /
OF CONSENT
\0
CONSENT TO COMMON USE
JOB 4250 PARCEL 2
LAFAYETTE AREA
..
IJ8804/'48" It
4/0'
<8
CentrA. . Contra Costa Sanitar) Oistrict
BOARD OF DIRECTORS
PAGE 1 OF 1
November 20, 1986
NO.
v.
CONSENT CALENDAR 15
POSITION
PAPER
BOARD MEETING OF
AUTHORIZE $3,388 FROM THE SEWER CONSTRUCTION FUND TO
COMPLETE THE OUTFITTING OF TRUCK NO. 74
DATE
November 17 1986
TYPE OF ACTION
SUBJECT
AUTHORIZE FUNDS
SUBMITTED BY
INITIATING DEPT./DIV.
John Larson
Collection System Operations Department
ISSUE: Sewer Construction Funds are needed to complete outfitting of Truck No. 74.
BACKGROUND: Sewer construction funds for the purchase and outfitting of Truck No. 74
were previously authorized as part of the 1985/86 equipment budget. Truck No. 74 was
delivered late due to personnel problems at Pittsburg Ford. By the time of delivery
in August 1986, the 1985/86 fiscal year equipment budget funds had been returned to
the Sewer Construction Fund. At this time, $3,388 is needed to purchase and install
a flat bed, tool boxes, and lift gate. This authorization will not exceed the
original line item authorization for Truck No. 74.
RECOMMENDATION: Authorize $3,388 from the Sewer Construction Fund to complete the
outfitting of Truck No. 74.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
DEPT./DIV.
GEN. MGR./CHIEF ENG.
.
Centr~~ Contra Costa Sanitar) District
BOARD OF DIRECTORS
PAGE 1 OF 3
POSITION PAPER
BOARD MEETING OF
November 20, 1986
NO.
VI. ADMINISTRATIVE 1
SUBJECT
DATE
November 12, 1986
ADOPT A RESOLUTION AMENDING EXHIBIT A, DESIGNATED
POSITIONS AND DISCLOSURE CATEGORIES) OF THE CCCSD
CONFLICT OF INTEREST CODE
TYPE OF ACTION
ADOPT RESOLUTION
AMENDING CONFLICT
OF INTEREST CODE
SUBMITTED BY
Joyce E. McMillan,
Secretary of the District
INITIATING DEPT./DIV.
Administrative Department
ISSUE: A need exists to update the disclosure categories contained in Exhibit A
of the District's Conflict of Interest Code.
BACKGROUND: The Central Contra Costa Sanitary District Conflict of Interest Code
was first adopted in 1976. Since that time the designated positions contained in
Exhibit A of the District Conflict of Interest Code have been amended to reflect
changed circumstances, including the creation of new positions and relevant changes
in the duties assigned to existing positions. However, no changes have been made
to the disclosure categories which corresponded to the original disclosure statement
forms.
In the opinion of Couns~l for the District, there are no changes in the law which
require revision of the District Conflict of Interest Code at this time. The
positions designated for disclosure in the Code are all those currently requested
by law. However, the disclosure categories currently utilized do not conform to
the categories used by the state in its standard disclosure Form 730. A proposed
resolution remedying this nonconformity is attached for the Board's consideration.
If the Board approves the proposed amendment to Exhibit A of the District Conflict
of Interest Code, it must then be submitted to the Board of Supervisors, the code
reviewing body. The Board of Supervisors must then, within 90 days after receiving
the proposed code amendment, either approve it, revise it, or return it to the
District for modification. The code takes effect upon its approval by the Board
of Supervisors.
RECOMMENDATION: Review and approve amendment to Exhibit A, Designated Positions
and Disclosure Categories of the Central Contra Costa Sanitary District Conflict
of Interest Code (Resolution No. 86-158) and authorize the Secretary of the District
to submit a copy of such code amendment to the Board of Supervisors of Contra Costa
County for approval.
JEM
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INITIATING DEPT./DIV.
~
RESOLUTION NO. 86-
A RESOLUTION AMENDING EXHIBIT A. DESIGNATED POSITIONS
AND DISCLOSURE CATEGORIES. OF THE CCCSD
CONFLICT OF INTEREST CODE
WHEREAS, Section 2.20.020 of the Code of the Central
Contra Costa Sanitary District provides the Board of Directors
shall from time to time establish by resolution designated
positions of officers and employees deemed to make, or
participate in the making of, decisions which may foreseeably
have a material effect on a financial interest.
NOW, THEREFORE, BE IT RESOLVED by the Board of Directors
of the Central Contra Costa Sanitary District as follows:
THAT Exhibit A, Designated positions and Disclosure
Categories, of the Code entitled "Conflict of Interest Code,
Central Contra Costa Sanitary District," a copy of which is
attached hereto and by reference incorporated herein, be, and
is hereby, approved and adopted for the District, subj ect to
the approval thereof by the Board of Supervisors of the County
of Contra Costa; and
THAT the Secretary of the District be, and is hereby,
authorized and instructed to submit a copy of such Code
amendment to the Board of Supervisors to approve said Code
amendment in accordance with Government Code Section 87303.
PASSED AND ADOPTED by the Central Contra Costa Sani tary
District Board of Directors this by the
following vote:
AYES:
NOES:
ABSENT:
Members:
Members:
Members:
President of the Board of Directors
Central Contra Costa Sanitary
District, County of Contra Costa,
State of California
COUNTERSIGNED:
Secretary of the Central Contra
Costa Sanitary District, County
of Contra Costa, State of California
Approved as to Form:
EXHIBIT "A"
Designated Positions
1. Di rector
2. General Manager-Chief Engineer
3. Secretary of the District
4. Counsel for the District
5. Manager
6. Finance Officer
7. Accounting Supervisor
8. Consultant
9. Principal Engineer
10. Senior Engineer
11. Associate Engineer
12. Source Control Specialist
13. Wastewater Control Technician
14. Survey Party Chief
15. Senior Engineering Assistant
16. Engineering Assistant
17. Engineering Support Supervisor
18. Senior Construction Inspector
19. CSO Inspection Supervisor
20. Survey Supervisor
21. Construction Inspector
22. Buyer
23. Materials Coordinator III
24. Plant Operations Superintendent
25. Collection System Superintendent
26. Plant Maintenance Superintendent
27. Laboratory Superintendent
28. Maintenance Supervisor
29. Electrical Shop Supervisor
30. Instrument Shop Supervisor
31. Maintenance Safety Specialist
32. Mechanical Maintenance Supervisor
33. Machine Shop Supervisor
34. Buildings and Grounds Supervisor
35. Vehicle Maintenance Supervisor
36. Pumping Stations Superintendent
37. Pumping Stations Supervisor
38. Control Systems Engineer
39. Senior Chemist
40. Real Property Specialist
41. Permit and Services Technician
Disclosure Categories
A,B,C,D,E,F,G,H
A,B,C,D,E,F,G,H
A,B,C,D,E,F,G,H
A,B,C,D,E,F,G,H
A,B,C,D,E,F,G,H
A,B,C,D,E,F,G,H
A,B,C,D,E,F,G,H
A,B,C,D,E,F,G,H
B,C,D,E,F,G,H
B,C,D,E,F,G,H
B,C,D,E,F,G,H
D,E,F,G,H
D,E,F,G,H
B,C,D,E,F,G,H
D,E,F,G,H
D,E,F,G,H
D,E,F,G,H
D,E,F,G,H
D,E,F,G,H
D,E,F,G,H
D,E,F,G,H
D,E,F,G,H
D,E,F,G,H
O,E,F,G,H
O,E,F,G,H
D,E,F,G,H
O,E,F,G,H
O,E,F,G,H
O,E,F,G,H
O,E,F,G,H
O,E,F,G,H
O,E,F,G,H
O,E,F,G,H
0, E, F, G, H
O,E,F,G,H
D,E,F,G,H
O,E,F,G,H
A,B,C,O,E,F,G,H
O,E,F,G,H
A,B,C,O,E,F,G,H
A,B,C,O,E,F,G,H
Category Index
A Investments
B Interests in Real Property
C Investments in Real Property and Investments Held by Business
Entities or Trusts
o Income (Other than Gifts or Loans)
E Income (Loan)
F Income (Gifts)
G Business Positions
H Income and Loans to Business Entities
I
.
Centr; - Contra Costa Sanitar-"'District
BOARD OF DIRECTORS
PAGE 1 OF 2
POSITION
PAPER
BOARD MEETING OF
November 20,1986
NO.
VI!.
ENGINEERING 1
SUBJECT
EXECUTE AGREEMENT RELATING TO REAL PROPERTY WITH
EDWARD L. STRONG, ET UX, JOB 3934, PARCEL 1,
ALAMO AREA
DATE
November 10, 1986
TYPE OF ACTION
APPROVE REAL
PROPERTY AGREEMENT
SUB"dl.TTED f3Y
uenn1S Hall, Associate Engineer
INITtA TtNG, DEPiT.lDIV. i D t
~ng neer ng epartmen
Construction Division
ISSUE: The property owner wants to construct a 40' x 60' Sport Court over a
District sewer easement.
BACKGROUND: The property owner has cooperated with District staff by supplying a
site plan and construction drawings of the Sport Court. The site will require
only minor leveling, and will leave the 8-inch ABS sewer main with approximately
15 feet of cover. There are manholes at both ends of the Sport Court site which
will provide good maintenance access.
The subject agreement is' specially written to protect the District from any
liability which could arise from or be caused by the construction and existence of
the improvements within or over the District's easement. Staff has determined
that the improvements will not interfere with the present use of the existing
sanitary sewer; however, if the need shoul d ari se, the agreement requi res the
property owner to remove the Sport Court at the owner's expense within 30 days of
notice.
RECOMMENDATION: Approve the Agreement Relating to Real Property with Edward L.
Strong, et ux, Job 3934, authorize the President of the Board and the Secretary of
the District to execute said Agreement and authorize the Agreement to be recorded.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
JSM
RAB
"JG
JL
ROGER J. DOLAN
1302" .9.'65
toV
DH
f)1tfJ
INITIATING DEPT/DIV.
o
no
...,
. " $'~'
NUT-CREEKs- --- ~..." ~1l.f!oj5
~ [;~3~?~ ~ ~
~!if"'" ~.
136
~
c.J",>-
0- -t.-
v"1"
<'<""0
~+
~
-"-
<""
137
MANHoL.E
T
~.
~
"%~ (c
+~
6O.:J
8'~.8>,
.sfWE'~ Mill
138
SUBD. 4915
237 M 17
160
f3<o E:.:.E.V .
.,"tl._'
.SPORT COURT
of.::nl&. "l~""""," ~
",,'61'>'Wl'_ __
-------
~N""T1I~ 6/'>ODE'"
0~60' Ll6HT ,..,.r pJ~ UoLF'
11"'1. ,,', ~'....e-;.
'!!>.D'~~5
..
.
"
'1...
- lr
i,"Z11
~I:~
..~~
~~;
SEWER SECTION
REAL PROPERTY AGREEMENT
Job 3934 Parcel 1
ALAMO AREA
.
Centr..._ Contra Costa Sanita. I District
BOARD OF DIRECTORS
PAGE 1 OF 2
POSITION
PAPER
BOARD MEETING OF
November 20, 1986
NO.
VIr.
ENGINEERING 2
SUBJECT
APPROVE AGREEMENT RELATING TO REAL PROPERTY WITH
GEORGE P. VILLA, ET AL, JOB 908, ORINDA AREA
DATE
October 29, 1986
TYPE OF ACTION
APPROVE REAL
PROPERTY AGREEMENT
SUjlMITTIiD BY
Uennls Hall, Associate Engineer
INITIATING DEPT.lDIV.
Engineering Department
Construction Division
ISSUE: The property owner has requested permission to construct a wooden
retaining wall over and across a District sewer easement.
BACKGROUND: The retaining wall is planned as part of the landscaping for a
swimming pool which will be built outside of the sewer easement. Maximum height
of the fill to be placed behind the retaining wall is three feet.
Staff has determined that the wall and fill will not interfere with the present
use of our sewers. However, if the need shoul d arise, the subject agreement
requires that the owner remove the improvements within 30 days of notice to do so.
The property owner has cooperated with District staff by providing construction
drawings of the proposed improvements and has paid the District's fee for
processing the subject agreement.
RECOMMENDATION: Approve the Agreement Relating to Real Property with George P.
Villa, et al, Job 908, authorize the President of the Board of Directors and the
Secretary of the District to execute said agreement and authorize the agreement to
be recorded.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
w~
Pf(
J~
1302"9 85
DH
JSM
RAB
JL
INITIATING DEPTfDIV
"POOl..-
(..Q, \.'l , ~] "^ G"',
~ \
-~_ -x-_ .~., \
\ ":S~ ' "-J' \
.~ -~~
'- j
/
o~
.7'
/-Y~()\("~<!;'Do:~ J~~vJb ~/ /~/ ,~
~~\~~?~~~'- --~ . / ~
~~~~~~ if: \0 ~
~.S.
t (
I
Re'TAl N \NG
W A 1.- \....
-i ~Iw ~~ ~q
o'iJ fol-t:. ((.,
~~~ '9'
~y..,\U'D ~o.
REAL PROPERTY AGREEMENT
Job No. 908
ORINDA AREA
.
Centra... Contra Costa Sanitar ~ District
BOARD OF DIRECTORS
PAGE 1 OF 6
POSITION
PAPER
BOARD MEETING OF
November 20, 1986
NO.
VIr.
ENGINEERING 3
SUBJECT
AUTHORIZE GENERAL MANAGER-CHIEF ENGINEER TO EXECUTE
AMENDMENT NO. 1 TO THE AGREEMENT WITH JAMES MONTGOMERY
CONSULTING ENGINEERS AND AUTHORIZE $542,000 IN SEWER
CONSTRUCTION FUNDS FOR FINAL DESIGN OF THE SAN RAMON
VALLEY SEWER IMPROVEMENT PROJECT
DATE
November 17, 1986
TYPE OF ACTION
AUTHORIZE AGREEMENT
AUTHORIZE FUNDS
SUBMITTED BY
INITIATING DEPT./DIV.
Curtis W. Swanson, Principal Engineer
Engineering/Engineering Division
ISSUE: Board of Directors' authorization is required for the General
Manager-Chief Engineer to execute consulting engineering agreements and to expend
sewer construction funds.
BACKGROUND: The District is planning to construct a new 12-mlle trunk sewer to
serve the San Ramon Valley. Portions of the existing trunk sewer through Danville
and Alamo are at capacity. The District recently completed the environmental
review of the proposed project, as required by the California Environmental
Quality Act (CEQA). The Project EIR was certified October 16, 1986, and the
project was approved October 28, 1986. A Notice of Determination for the project
was filed with the County Clerk on October 29, 1986. Staff proposes to begin
construction of the new trunk sewer in 1987. (More information about the project
is included in Attachment 1.)
Design of the trunk sewer is being accomplished in two steps: a preliminary
design of the entire 12-mile sewer followed by a detailed final design of each of
the proposed three phases of the sewer. Preliminary design began in July and was
completed in late October. Staff proposes to begin final design of both Phase 1
and 2 now with the goal of constructing both phases next summer and fall. The
construction schedule presented in the Project EIR was for construction of Phase 1
in 1987 and Phase 2 in 1988. However, 1t was also noted in the EIR that the
District may elect to combine Phase 1 and 2 into a single construction phase. The
length of sewer to be installed under a combined Phase 1 and 2 project is
approximately eight miles. Combining the first two phases of the project should
result in overall lower construction costs and provides trunk sewer capacity in
areas where it is needed to meet present capacity limitations. The COM Master
Plan has revealed that portions of the existing sewer in the Phase 2 area are more
capicity limited than previously realized. Phase 1 extends from San Ramon Creek
near St. James Court in Danville to La Serena Avenue in Alamo. Phase 2 extends
from La Serena Avenue north past Rudgear Road to connect with the Wal nut Creek
Bypass Sewer, which is currently under construction. Staff proposes to design and
construct Phase 3 of the project at a later date since capacity in the area served
by Phase 3 is not needed in this area until the early 1990's.
.
Staff has negotiated Amendment No. 1 to the existing agreement with James M.
Montgomery Consul ti ng Engi neers. Under Amendment No.1, Montgomery will prepare
construction contract documents for a combined Phase 1 and 2 project. Plans and
specifications will be completed by March 31, 1987. Also, Montgomery will prepare
REVIEWED AND RECOMMENDED FOR BOARD ACTION
/JjjJJ
1302A-.9/85
CWS
DRW
RAB
~-'---""'-_._~.....__._------_.,-,.---+,."-,,__.._._,_~'_'~_'__'+~.-.__~_.".__.,____,..~._..._.,.,._.,,__..,_"~__'~'_,"~",____",_",,'._"k.._..~.......~___+_~.___,__..__.___.,___
SUBJECT
AUTHORIZE GENERAL MANAGER-CHIEF ENGINEER TO EXECUTE
AMENDMENT NO. 1 TO THE AGREEMENT WITH JAMES MONTGOMERY
CONSULTING ENGINEERS AND AUTHORIZE $542,000 IN SEWER
CONSTRUCTION FUNDS FOR FINAL DESIGN OF THE SAN RAMON
VALLEY SEWER IMPROVEMENT PROJECT
POSITION PAPER
PAGE 2 OF 6
DATE
November 17, 1986
separate specifications to prepurchase sewer pipe. Prepurchase of a portion of
the required sewer pipe is necessary to allow installation to begin as soon as
possible after the construction contract is awarded. As a mitigation measure for
project impacts, the District is attempting to avoid construction during wet
weather. The prepurchase specifications will be completed by January 31, 1987.
These services will be provided on a lump sum basis at a cost of $499,684.
Montgomery was selected to provide final design services because of their
familiarity with the project and their successful completion of preliminary
design.
The total amount of funds being requested for final design is $542,000. A summary
of the funds being requested is listed in Attachment 2. This request includes
$77 ,000 for force account costs incl uding project management, engineering design
review, and survey activities. This project is included in the lo-Year Capital
Improvement Plan under the Priority A category (Title: San Ramon Valley Project -
Phases 1, 2, and 3).
RECOMMENDATION: Authorize the General Manager-Chief Engineer to execute Amendment
No. 1 to the agreement with James M. Montgomery and authorize $542,000 in sewer
construction funds for final design of Phases 1 and 2 of the San Ramon Valley
Sewer Improvement Project.
---------
13028-9/85
ATTACH~NT 1
CENTRAL CONTRA COSTA SANITARY DISTRICT
SAN RAMON VALLEY SEWER IMPROVEMENT PROJ ECT
PROJ ECT DESCRIPTION
Introduction
The San Ramon Valley Sewer Improvement Project consists of the
installation of approximately ten miles of large diameter gravity trunk
sewer and two miles of force main. The trunk sewer and force main will
be constructed from Larwin Pump Station north to a point near the
intersecti on of Danvill e Boul evard and Rudgear Road in southern Wal nut
Creek. At the northern point, the proposed trunk sewer will connect with
both the existing 36-inch diameter trunk sewer that now serves the San
Ramon Valley and the proposed 60-inch diameter downtown Walnut Creek
bypass sewer. As part of the San Ramon Valley Project, a short
connecting sewer, approximately 70 feet, will be constructed between the
northern end of the Walnut Creek Bypass sewer to the existing 60-inch
sewer near Ygnacio Valley Road. This connecting sewer will allow
temporary operation of the bypass sewer.
Sewer A1ianment
The sewer alignment is the Southern Pacific right-of-way for the entire
length of the project. This alignment will cause the least disruption to
traffic, commercial, and other activities in the valley communities. The
District entered into an agreement in December 1985 with Contra Costa
County to purchase a 20-foot-wide surface easement and a 12-foot-wide
subsurface easement within the railroad right-of-way. The cost for the
San Ramon Valley portion of the sewer easements was $2,959,000.
At the former railroad station site in Danvi11e, the District does not
have the surface and subsurface easements that it has in the rest of the
right-of-way. The District does have the right to use an easement
acquired by Contra Costa County for transit and underground utility
purposes in this 1,SOO-foot-10ng section. The County's easement is 30
feet wide. District's rights would be second to the County's rights in
this section, and the sewer would be under County's planned transit
system whether that be a light rail system or a dedicated busway. Staff
evaluated three alignment options around the former station site. Two of
the three had significantly higher construction costs and more impacts on
the community than the County easement. The third alignment option,
Railroad Avenue, has higher construction costs than the County easement.
The City of Danvi11e prefers the Railroad Avenue alignment option and has
suggested ways to reduce the costs of constructing along this alignment.
Staff will study the cost savings suggested by the City of Danvil1e.
Se1 ecti on of the alignment around the former rail road stati on will be
made during project design based on lowest construction cost,
construction constraints, and minimizing community impacts.
- 3 -
Sewer Size
Staff proposes to design the sewer based on the ultimate buildout
population of the San Ramon Valley and the infiltration/inflow criteria
developed as part of the Collection System Master Plan prepared for the
District by Camp, Dresser & McKee. The design life of the sewer is 50
years.
The Board of Directors previously decided to use growth scenario No. 4 as
presented in the project ErR for designing the sewer. Growth scenario
No. 4 assumes an ul timate popul ati on of 142,000 and development of the
Dougherty Valley subarea of the San Ramon Valley. Based on this
popul ation estimate, the gravity sewer will have a nominal size of 54
inches in diameter from Norris Canyon Road to Sycamore Valley Road. From
Sycamore Valley Road north to Danville and Rudgear Roads, the sewer will
be 60 inches. The force main from Larwin Pump Station to Norris Canyon
Road will nomi nally be 16 inches in di ameter. Actual sizes of the
gravity sewer and force main will be determined during the design phase
of the project. The actual sizes may vary up and down a pipe size
because of utility and other constraints.
Schedul e
Because of the size of the project, the trunk sewer is pl anned for
construction in three phases. The first phase is a fiv~mile section
from La Serena Avenue in Alamo to St. James Court in Danville. The
second phase is approximately three mil es long from La Serena Avenue
north to a point near Rudgear Road where the sewer will connect with the
new Wal nut Creek downtown trunk sewer. The thi rd phase will extend four
miles from St. James Court south to the Larwin Pump Station. The third
phase incl udes two mil es of force main. The first phase of construction
will take care of the sections of existing sewer with the most severe
capacity probl ems.
Construction of the first and second phases of the sewer will be during
1987. The third phase of the sewer is currently scheduled for 1989. The
th i rd phase is not needed as soon as the fi rst and second phases.
Construction of Phase 3 may be deferred for two to three years if effort
must be devoted to other higher priority District projects.
During preliminary design, staff evaluated combining Phases 1 and 2 into
a single construction contract. There are significant construction cost
savings that result from a single construction contract, and therefore
staff proposes to proceed with a combined project.
- 4 -
-^,,-- ......-.--. '___"~._"'~___mm~_...._...._.._.._...,__.,.__._<_...____"_.,_~__.,._..___~_~~.~. '__''''''___'~______'___''_____'"~'_'_-'_~''.''_''__ ~____ '__"M'''_'''___~'___~_.,... .__.__...-.--.____._______
Proiect Cost Estimate
The prel iminary design-l evel estimated proj ect cost is $29.0 mill ion.
This estimate consists of:
Construction including Contingency
Construction Management
Design
$29,000,000
l,300,000
700.000
Total
$31,000,000
The estimated cost of the three phases of the trunk sewer project are:
Phase 1
Phase 2
Phase 3
$14,000,000
7,500,000
9.500.000
T ota 1
$31,000,000
- 5 -
ATTACHMENT 2
CENTRAL CONTRA COSTA SANITARY DISTRICT
SAN RAMON VALLEY SEWER IMPROVEMENT PROJECT
PHASE 1 AND 2 FINAL DESIGN COST ESTIMATE
Description
Funds Requested
Consultants
James M. Montgomery
$499,684
Force Account
Project Management/Engineering
Surveying
Printing & Supplies
$53,250
11,750
12,000
$77,000
$ 77,000
Contingency * (10% of Montgomery contract)
Total Funds Required
$ 50,316
$627,000
($ 85,000)
$542,000
Funds Remaining From Previous Authorizations (see summary below)
Total Funds Requested
*If necessary, staff will use this contingency for additional force account effort
or to issue contract change orders to the consul tants to expand thei r scope of
work.
SUMMARY OF AUTHORIZATIONS AND EXPENDITURES
Expenditures
To Date
Authorization
General Manager-Chief Engineer - 5/1/86
$ 10,000
$ 10,000
Board of Directors - 7/3/86
$488,110
$498,110
$403,110
$413,110
Total
6
.
Centra~ -':ontra Costa Sanitar) Jistrict
BOARD OF DIRECTORS
PAGE 1 OF 3
POSITION
PAPER
BOARD MEETING OF
November 20, 1986
NO.
VIII.
PLANT OPERATIONS
1
SUBJECT
AUTHORIZE $15,000 FROM THE SEWER CONsmUCTION FUND FOR
EQUIPMENT AND CONsmUCTION OF A PLANT OPERATIONS
DEPARTMENT mAINING FACILITY
DATE
TYPE OF ACTION
AUTHORIZE FUNDS
SUBMITTED BY
James L. Bel cher
Associate En ineer
INITIA TING DEPT.lDIV.
Maintenance Engineering
Plant 0 erations De artment
ISSUE: Boa rd authori zati on is req ui red for the expenditure of Sewer Constructi on
funds.
BACKGROUND: The Plant Operations Department is currently in the process of
centralizing all Operations Division training materials and functions into one area.
Due to the compl exity of the Treatment Pl ant, cost of materi al s, and concern for
safety, the Plant Operations Department/Operations Division has found it necessary
to maintain an ongoing training program to keep the Plant operating rel iably,
economically, and safely. The training program consists of written text, graphics,
slide/tape shows, and practical experience emphasizing process and equipment
requirements as well as safety. This type of training format allows Plant operators
to meet certification requirements and learn to operate and maintain new equipment
systems. At the present time, training materials are located in various Plant areas
and need to be consolidated near an area conducive to individual study or group
training. The Plant Operations Department proposes to install built-in training
modules and cabinets in an existing room to produce a centralized training facility.
The consolidation of training activities and materials will enhance the
effectiveness and efficiency of the Plant Operations Department/Operations Division
training program.
The proposed modifications to the Plant's training area include a work area for the
production of training materials. T~is area requires a layout area for graphic and
text preparation pl us adequate storage space for over forty training packages and
the required equipment. A second area separated by an acoustical wall will house
individual training modules which will allow up to four operators to train at the
same time. The use of built-in cabinetry and training modules over commercial
furniture represents the most effective and cost-effective util ization of space.
The purchase of one desk and five chairs are included in the $15,000 project cost.
(See Attachment I). Actual construction work will be under $10,000 and will provide
the Pl ant Operati ons Department with an area suitabl e for operati ons and safety
training.
RECOMMENDATION: Authorize $15,000 from the Sewer Construction fund for equi pment
and construction of a Plant Operations Department training facility.
INITIA TI~EPT.lDIV.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
GEN. MGR./CHIEF ENG.
TRAINING ROOM CABINETRY
Cabinets
Training Modules
Furniture
Tackable Wall Surfaces
ATTAaiMENT 1
$ 7,000
2,600
2,000
3,400
$15,000
10'-0"
"
BUILT-IN
CABINET WITH
OVERHEAD CABIN T
~
~
I
13' -6"
~
I
P.O.D. TRAINING ROOM
Basement - Plant Admin. Bldg. .
D
(]
Trainee Room
D (]
..
"~~~:=>~~~~~~~~~:-~~!~:t:~' .~;".~;.::"~~-
Supervisor
16....,0"
Scale: 1"= 4'
NEW BUILT-IN TRAINING
MODULES
+32"@ DESKS
EW GYPSUM BOARD WALLS
PANELED EACH SIDE WI
SHOWCASE SYSTEM
ACOUSTICAL PANELS
~
Assembly
Room
(GROUP TRAINING)
.
Centra~ ';ontra Costa Sanitary .Jistrict
BOARD OF DIRECTORS
PAGE 1 OF 2
POSITION
PAPER
BOARD MEETING OF
SUBJECT
NO.
VII I.
DATE
PLANT OPERATIONS 2
AUTHORIZE $45,000 IN SEWER CONSTRUCTION FUNDS AND
AUTHORIZE PURCHASE OF A 200 HP PUMP DRIVE FROM
EMERSON ELECTRIC COMPANY
TYPE OF ACTION
AUTHORIZE FUNDS
AUTHORIZE PURCHASE
SUBMITTED BY
INITIATING DEPT./DIV.
David Reindl, Assistant En ineer
Plant 0 erations/Maintenance
ISSUE: The Board of Directors must approve expenditures from the Sewer Construction
Fund for capital projects.
BACKGROUND: The Treatment Plant has two 100 HP No.3 Water High Pressure Pumps which
provide utility water for various plant processes. Utility water is unfiltered
secondary effluent and is used for cooling, gas scrubbing, and chlorination/
dechlorination to name several uses. The demand for this utility (No.3 water) has
increased to a point where both of the existing pumps must be run continuously to
supply the required flow. Operating both pumps leaves the utility water system
without any backup equipment to ensure reliability. Plant Operations Department/
Maintenance Engineering staff have completed a design study and determined that an
additional 200 HP unit should be installed. This new pump would handle the current
flows. The existing pumps would then be used to provide backup and additional
capacity for peak flow.
The new utility water system will require accurate control of pump flow. This is
best accomplished through variable frequency control of the pump motor. The
Treatment Plant has had reliable performance from such drives on other plant
equipment. Since the size of this unit is identical to the variable frequency drives
bid in June 1986 for installation on the furnace 10 fans, staff requests
authorization to prepurchase the drive from Emerson Electric Company for the
previously bid price of $21,000. Purchase of the drive from Emerson will provide for
standardization of drive equipment, improve the efficiency of maintenance and
operation, and reduce inventory of spare parts. In accordance with Section 3400 of
the Public Contract Code, staff is requesting to sole source the purchase of the
third Emerson variable frequency drive unit. The prepurchase has been sanctioned by
District counsel as a suitable sole source item. A breakdown of costs is provided on
Attachment 1. The pumping equipment and the installation contract will be bid
formally at a future date, and additional funds will be requested at that time. The
estimated overall project cost is $150,000.
RECOMMENDATION: Authorize purchase of a 200 HP pump drive from Emerson Electric
Company, and authorize $45,000 from the Sewer Construction Fund for the purchase and
engineering costs.
INITIATING DEPT./DIV.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
/302A.9/85 DR
-----.~.._'-......-"._._---------...__..._---._-_..._-_._--~.,--~------_.~.,_._.._-".."._.._--~-~-~.-.~,._.~-----"._-_.~,-_._------
W
U
...
(0<
o
:z;
..:l
0<
~
~
...
o
4.1
C
II>
a....
II'"
> C
0::1
&~
....0
01 0
o
"''0
& C
0111
C
001
011
II ...
0<
'0
C4.I
..0
II
.......
4.10
C...
Ill'"
...
UII
....c
....4.1
....
.C
...
1I.c
"'4.1
0'"
Ii:'
...
"'0
.0
....0
fClll'
II
'0
IIC
'001
...
>VI
oc
..0
"'VI
..
O.
(0<",
...
o
0'"
....C
II
'OJ;!
C II
Ill>
o
VI'"
II a.
...&
.......
...
"'1Il
....c
U....
III
.......
o
0'"
...
"''0
.Q1Il
::1'0
a. II
III
ll'C
C
.....
4.1 III
..
.....
lC III
Ill'"
4.1
....
>...
0'"
...u
a. III
Ii....
...
S:..
'00 III
C::I"
"110<
11:'4.1
>110
"CIIl
II ......
VI.O
C'O ...
0"''''
U>
O.
o..s:
(0< a.4.I
....
...
><
U
:z;
W
~
<~
:z;
f4'"
~~
:z; :E:W
< "':r:
IIlQSU
~~~~
Will
>0 Q::>
(0< W'"
... 11:(0<
U :z;:r:
W 0...
:r: ;0
(0< ~~
~
III
:z;
~
o
'0 >0 '0
1Il~ -;;~ 0
.c... VI 4.1
4.1-911,. .>0
'06:.c..'O..,
C 4.1"'11'"
.,401 C4.I C
CC"II::1
....~....OI""4.aJ
"'0 ....a...
u~..... S 0
C &...oa.
:,1P"'4e"'Ua.
o III a.u 0
u... ...
U 0 .... C
>011 0 C 4.1 III
4.1 a... 0 C
... Ill'" & ::l '0
U III III
1lI4.111:.'O
C .. &..
0'0 C"'O
EiI""4\DfG......
..Oallll ....
1I:.c0l Ofcl
... .4.1
C... C .
..... .0 II.Q
Ill"'''' II &
:-....10......-4
. 11:4.1'"
.c>o" ...
4JU.OE:J
C.QCO
4011111.....'0
.. ll'ClI &......
.co<o" III
4.1 ClIU'O.
4JQ liS:
:l:C N::I
~~>~!;ll
... a... N 4.1
~O'O CO
.... Ul .04.1
>011 II VI U
IIl>CI.< ll'
ILICl1'OClI.C
a: '0 ClI.Q.Q'"
WClI~Ei ..
:r: a: .. >0'"
C.c"VI
IIlCOU&ClI
...0 '0
all'.... ll'
W.. C... C C
Ua:... 0'" 0
... I.<C..VI
(0< C.. ::I .... .
O..ClIOCllIIO
:l:1Il:r:U.ca.VI
'0
C
..
Ul
.. 0
II....
...4.1
<Ul
...
4011.<
OCll
ClI....
.....0
0..
.....
"'..
.c
IIU
.c
.......
..
......
OC
II
4.lEi
CC
ClI 0
Ei ..
C'"
0>
..C
"'11
>
CII
II....
.Q
......
....
00
...>
....
>0....
.c
a. III
4.1
....
s:
4.1 III
N
....
UVI
C..
illS:
'Ego
..
00
(0<4.1
.
C
o
.......
..,....
C II
II:>>....
.... 0
ClIVI
I.<..C
o
II VI'"
.c"'VI
..,OC
......
... 11) Q..ft'I
o ClI x ClI
"'>ClI...
C ..
....'0
.... CClI
.Q.......c
..... ....
Ul 0 C
III 0 0 C
O....-4....c
a. 4.I.c
........
...ON.....
Ill.......:.
> ....
ClI ... Ul
I.< Ill.., ClI
QJ.a.J.... In
.c III >...
:. III II I.<
VI~"f'
CI'" . II
... C C..,
4.1'" 0 C
... "'11
C >0401
::I..,......
4.1"::1..
"IIC...
o a.... U
a. 0.... H
a.I.<CII
o a.8 ~
1Ill' 0
NCIIU
.......c
E'" 401 ll'
"'VI C
lC'" 1.<...
.. x 04.1
&CI......
...
0.... III lC
(0< 0 III III
.n
>
CO
"401
....c
o Ul
....
..,:.
C
11>0
& ..
ClI a
o
.. 0
.....c
a.;a
VI
...c
'00
III
& ...
::Ill
sa.
....
C III
"'Ul
Ii II
C
Ill'"
Ul
S:::I..
4oI.QClI
... I.<
:...<
o
CIl ..,
......,U
.. C II
OCll......
ll''O 0
"'1.<
II VI'"
VI ClI
111.<11
s: s:
4.1 ...,
..
S:IIC
~~~
....0..,
a. ...
a >0:'
0..,
U..C
UII...
III a...
o B
01.<11
(0< a...
.,;
C
0>0
a.Q .
.. >0
a:CClI....
o.c H
c.... t-o II
.. 4.1 a.
en..... . (.I
VI C I.<
G.lo.-4 ro Q,.cu
~ g.ii: ClI~
o I.< >
C .. ..,.......
~O~&~
..,....BO
..... o..ta ~
:'..,0 0
0.... 0
>OCllGl4.l0
4JT"\ > ......
I.<.QClI'O....
ClI::I'OClI.Q
"'IIlCll"::1
o II: ClI a.
"ClI ;a
a..Q II 0 II
.c a..c
"''0..,11..,
........ II
1lI::11.< C
o ClI II'" >0
(o<;a'O.Q 401
;!..3'Ot:~
t-o II ....... a.
I.<C::IIIlO
:l:O<OOUl"
ILl ...:. III a.
>4.1..,
...0..>0011
~ClICU.....c
......a C 4.1
11:01111'0
ILI"'O ll'C....
:r:",c<..o
t-o 0
~4JU4J .401
C C'OC
II .. II II II
aoa'Oa
1Ila. a.lla.
...0110110
-eCl)...-tCP"I
WCI..ClI II
U>S:>II>
...ClIUClII.<ClI
(0<'01.<'011'0
o 11::1 ClIS:II
:I: II: a.1I: :. ..
C 401 II....
OC 1I.c..
all .c"'''''O
..a 4.1 CII
II: a. .... ClI ..
o ....oe..
c... 0 ca.
..11..>0 11011
1Il> .., ll'1Il I.< I.<
II.......CO...'"
'g'g05~f'~
~g:g'~~[W~
a. "'OH CI'"
OIl,>(UClI.<S:1LI .
I.<.c.. 'OCl4.lI: C
a.4J4J..C.c III
I.<...::I..,'OCI....
tl'OIIC I.<CS:'"
.cCll'O..C::I....,
4.I....CO..... ..,
1""4='..... C"I::JC
1.<.. ...tl<IlIC1C1
ClUII.....Q ......a
'O.c.. "'....a.
"'I.<"'U'O' ..0
IIlCl "'>OClU...
C..,IIlCll::lU.c CI
O....CI.c 0 C.., I.< >
U"N"':'II .CI
c.... ll'C'" '0
0'" I.< 0..,< 0.... II
4.lCI 0401 U ..II:
I.<.c ClI"'''' ClI
III ClI"''''.,...,C 1.<"'0
....c::lCOCllOCll...
.. .. I.< Ei a.s: ..
ll'. ::Ia.a.ClI VI
CCCUl 011:
... .. .. I.< '0.... C I.<
............::J.....CUIOIUO
..",,,,a...> ........
ClI lIlCllI.<'"
S:4oIClI.., 'OGI :.
u.cu ClI'OII"
'OClIt-oCll .a:...s:...
...."r"'\ "f""\ VJ 111 +J
..0 O:.CC tl
CIlI.< ......OOC4.I
"'" a...:l e U 0 ..
.... C .. 401
04J..4J4J1I:0"'1Il
C....CC ..,1.<
tlll"'ClIClIC 00
Ul II = Ei e .. III a.4J
o a. a.a.1Il'" ClI
a.01.<00 a: 401
"'....t 0............ tr' C
::IClI ClIIIOC"'"
a.>=>>"'U::l
ClICClIII>OI.<..1II
11'0"'0'0"''' a. I.<
s:1I....ClIII...ClIa::l
(0<11:'" .. II: Us:... a.
C
... ll'
C
'0 ...
III :.
.... 0
01 ....
::I ....
.... 0
..........
III 0
II
1Il1l.c
.........,
..
01.., C
III Ill'"
I.<
< -'0
.. ClI
4.I......a
0"''''
GI 0 I.<
.,...,UO
o III
....ClI
"'1.<'0
..,
..,C>O
co....
ClIUI.<
B ..
a..... ...
00::1
.... U I:
III >0... <
>..,..,
ClIC....,
'0 ::I .....
ClI 0 a...a
a:u ....
liS:
C .1.< lC
OCOW
a 0 al:
.. a
11:..111
II:"'C
C 0
"C'O'"
lIl..C4.I
1Il1lla.
'0 ...
Ill.... ...
VlOIllU
o ... III
a.>OCII
0..,..'0
1.<... 0
a.U.......
.....
II II.... ll'
.c.c"1I
(o<"'U",
... GI
o .c
II ..,
c.c
...., >>0:'
..... C..Q 0
"'C.. .c
...... "tS II)
'0 "'ClI
II VI 0 III '0
III ClI .... C
00>....
c. C.... I.<
o CP.... tf\
~='...G.lC
g,..... ta :3....
""..-4"''''''0
IIC::IIII..t1
.c... ll'.... ClI ..,
.., ClI .c a.
ll'''>O 0
o C C'O'O
4J.... QI fa.... ro
.....c ..
UI,C.... CUI Q,I
CO'O ..a
0... I.< ..,
........OJl(tU4J
4.I..a .. 0
U . ClI I.< C
ClI I.< :. c...
......O..IIICl1'O
..a ..:l c....
0.., 0 a.::I
.c ClI.... .. 0
>0 ll'.... .c
C......s:>01ll
"""401 Ill..
..alll"'ec
ll' :...
c........ ...P""4
"'OCllOC'"
> a..c..
..ClI :.....'0
S:U.. "'Ill
C ClII.< III
VI..I.<O'OO
C.., 0< Gl a.
0111 . III 0
III'" 401 ll' 0 I.<
..lCOCa.a.
II III Ill"" 0
a. ......'0...
II 0 III a.s:
.....c..1Il ..,
.....,"'UII
III o.c>o
>0'0 I.< ... s:
'OCClIC. :.
C III III C
"'00"011
a. 0 III
>0 0 0"'11: ::l
C.cI.<.....1lI
<:.a.a.ILIU
C .
>0 .....0 ...
4.1 .co.... .Q C
... .., "'11 III II
1.<.... III U I.< I.< II
OOCClI..Gl ....'0 ..a
.c ...... .c 1II11l'O ....
4.1 III s: I.< Ill.., ClI.., CillO
::14.14.1..... 'OC....
"U"''OS:''C ClI....s:C
. ~ :. 5 f-o ~ .. 'g g,4.I III ~
S:1IIll'0 < .111" III III 4.1
4.lIlIC..a. VI 1.<.c1.<1lI
... C 4.1 III 1.<....... .. I.<
. 114.1 II.. 0 III ClI 0
murn.cP"'4G>:JQ.......,.....
::I ::I....., "'..... 0 III c.c I.<
'OlC 0'01.<"''''4.111
OIlClCIIlI.<Ca.CO 4.1
4.1 I.< .... s: "'.. Gl a..... II
>os: 4.1 ... VI e 0 '0
III '0 .... 4.1 CI 4.1 II II
IIC..,....Cs:.......>s:c....
III IlIc:....4.I o..a 0...0 III
o CI ....... ... 0
a. CI VI >os: C II s: a. 0 .., ...
0401 ClI..........1.< C Ei..,.. III
1.<..1.<....1.<s:::I...... N>O
a. C a... 0 4.1 .., a.... s:
... U.......lCs:U.......a.
>011401... :.... O...s:...
o....c....... Ei......III..,
C... ll'''' III II s:..a"::l III
IIC1....UIIIIIIClI:.::IGl II
ll' "'ClI ::I.... a.cou
o<o..aa.rn....as :....c
4.1 1II..0"Cllloalll
..,... Gl1.<4.I.., 04.1
C C '" II ...a.... VI .. II C VI
=~.~ ~:: >o~ ~&'Q.8!;
a."'OEiI.<I.<'O ClI....CI
o VI O<"CC'O'" II
"'CI '0 1Il::l01ll...I.<&IIl
ClS:'OC4J1Il "'C::lClO..,
>4JCIlIOClC"''''IEia.IIlC
II .. ClO"'.. 0 CI
'0>0 C......CI ... .'OI.<CEi
IIl..aUOOCIIl::l4JCa....1I
II: ...s.. ...UCIlI >
4Ja""'IIlVlI.<ClI 1.<.0
C"'OIl: ..........eco,o..
o C '0 lCUa.o....Ca.
BOOCClI'01I 0.... IlIEi
Ill'" 0.. III ClI ClI...... II ...
II: ClIlIl 0 III >0'" III fcl 0' .
'0 a.O.....>N..'O>O
CGJ """0 o....,g.cu........ "'.aJ
:~~O:1.~~ClI'O~-:i!t:~
>::1>0 a.1Il'O'OOCll..a.
1101114.111 ClI"CHIIl:'O
s:1.<.......c III I.< C 111111 1II.c..
f-o a. > U ..,... a....... a. III .., a.
ClI ...
...... III L..
..a Ul 0 '0
.. m G.I 0. C. '"
~.... c CJ 10 ......
10........ 0.. C
~ro III ....:a...
> ~ c CP 0 0
...,tiO .Q ....0 cc w
c: 0- .:J: c....
II II III ... 0'0 II 0....
e'O IIl"C I.<e..
g,.m....cC.l...u..... "'1'0 IOU
o fa o......c. C.l 0 ....,&.J a::
.... .... c _ 10 ... 4J ...
II'OC'O :>>OICl10I.<CC
>COGl..,Oll;.ca.O..O
GI......O'C Gla.lIle
'0 ..,..GI>OIlIlIl:GI ..
GI'O" O'B..a.c.c a: Glll;
a:OII.<CtI ........, .c
4JQ)cu.....~ uc,,",c
>oc.c. c.1I> ......0 ..
.... 0 0 G.I IE Q.I G.I .., a..... .... U)
.... "C ....... u.... fa.... 0
c....,.. ooc.....
~Ul~02:1.E~...g~5
Ei..II.c GlUl.....Ol!
O.cGl:.VlGl.cUl....GI......
u .... ClI.c"':::l ca:....a:
>.Q.cn.....a.J...UQl ...
..O~C::I :::lUlEi'OOO
-..4 c.... 0 ... c "".... C I: c::
c:: CIJ en ..-4 "0 '" GJ....t
1.<0'0"111 I.<.ce
O.c....QJftSC ....... .......<<:1
... a. 0..0>111 u
-4"-'&1) ......."'-...CG.l.&J
.... C Q) ............... w..... lIIIN
-ocu....ocucc.cc ::s N
U~::I....:Ja. GI -a:c..
a. I.< .......a.C ON
GlO ......UOO..C....
,cP"'lCCfltl.....l1I ....04-1
...GlOCl ..,......GI"'....O>O
>...e....o..a ..GlU
S:Gl4J..,GI..1.< .....a.C
...'00.... a.",... C a. III GI
... CIJ cu ~.c .... CU...-t C D"
:.a:c.... ....GI....IIO.....c
III ... 4.1 o.c :. a.....
IICC 0 ... 04.1..401
UO.......IIV1 c...I.<OC
ce ........4JC..II......II
....U...OC......>'" Ei
,oa:....4.lI.<GI "'GI 1Ila.
I.< ....Ca.Ei> '0111....0
Oc..aGl GI...IIG1V1..a...
0"::1'" II I.<...ca: 11..11
UIIla.GI.c....ClI.., C....>
.. II"~'" &g...~-;;;-;;~
c.cOI.<CGI..O..::I>GI
... ........ a.... I.< a.... lIlal .. II:
UIIlC
... CI'"
........
"'4.lS:
U......
CI>..
Po... 0
1Il4.l....
U
C"'4J
:. II
o >0 III
4.lU
CCII
:'GlI.<
o ll'fCl
C<C
'0"''''
CC....
IlIG1'"
Ei
C a.'O
.. 0 II
......111
"'ClO
>a.
"'ClO
.. '0 I.<
I.<GI'"
ClII:
C III
GI...s:
~....4J
..
C .... II
OCO:J
Ii.... 0
III II ...
":'0>'"
CI'" 0
~et...
lIlGlGlIll
Ul......'"
1I..a.Q
.cOO.
4.1 III
GI'O'"
......aC..
o .. 0
'0 ~
Ill.... II
... ::I a.'O
.. 0 0 ClI
0:' U Ul
ll' 1110
C a.
CI .. II 0
.c....cl.<
f-o '" t-o a.
VI
401
...
..:l
0<
o
~
U
...
10.
...
U
ILl
'"
en
>0
401111
....401 III
..0 s:
011 ...
.c a. >0
... III >0... C
::1.0,.............
'" 4.1..
>OCUS:
IICGI"'4J
.c..Ul.....
....EiGl...O
1.<0....
GI II a. GI
III 0 a...,
::1::14.1 III II
'O.c III
o GI ll' GI
401 ....... I.< rn
....0'"
III 'O..a s
GI C
1Il"'''''OfCl
o .. C GI
a. II.... .. ..
0...0 0<
... '" 0 C
a.CUlO..,
... Ei U
>0 S '0 '" Gl
U-4 C Q;'1""\
c..... fa 0
IIG1 CI.<
0' ...'"
.c0....1Il
..... II
.., O.....c
C C.... 0...
QI..Ul
Ei.... >>0....
a.'" .c 401 0
o a.....
...11 UII
II .c II
> 401 U II'"
II ....c...c
'O>Ei.....fCl
1I..a 0 '0'"
a: CCC'"
4.1 0....::1
C'" Us: 0401
o CI......aC
Ei 0 .... II
"'.., .:. II Ei
ll; ... .ca.
'0" ll'''' 0
ccu:JC ....
fCI"'['1i en "" C II
CI)...-l...,.....>
>>Ul.cGl
110 .....,'0
J:w...)(.....cv
!-<a.OCl:.a:
x.
CORRESPONDENCE
Page 1 of 1
1
C
o
e
..
..:
C
..
1Il
...
o
>0
...
...
U
II
s:
4.1
....
o
>0
U
C..C
o 0 GI
Ul .., 0'
coO<
....GI
.Q .. 401
0.... C
a:QII
II
II II a.
II > 0
II.......
.....11
~::I>
UGI
'GI'O
I.<lCGI
:E:wa:
N
.0
al
01
....
.
..
III
-:i!
II
>
o
:I:
:3
<
o
~
..:l
~
~
t:i
o
III
III
III
.Q
U
...
.
o
C
o
U
II
..
II
ll'
C
o
..
4.1
.
'0
C
"'>0
...
'0'"
II C
....::1
~~
III 0
I.<U
II
>'0
"'C
'OtlI
.tlI
II III
"'1.<
.Q<
..
4.1401
II U
CI
..~
o
III.<
'0'"
...
> II
o.c
....,
a.
...
00
t-o....
...
....
"._~-"_._----"._----_._--,.._~-----_._~.._----~-,--_.---~._--,_.,..~---