HomeMy WebLinkAboutAGENDA BACKUP 07-03-86
.
Centr~
Contra Costa Sanitar Jistrict
'-
BOARD OF DIRECTORS
PAGE 1 OF 1
POSITION
PAPER
BOARD MEETING OF
J ul 3, 1986
NO.
IV. HEARINGS
SUBJECT
CONDUCT A HEARING ~ lHE FORFEITURE OF ADVANTAGE
PLUMBING'S $1,000 CONlRACTOR CASH DEPOSIT
DATE
June 24, 1986
TYPE OF ACTION
HOL 0 HEAR ING
SUBMITTED BY
Dennis Hall, Associate Engineer
INITIATING DEPT.lDIV.
Engineering Dept./Construction Div.
ISSUE: A Board hearing is required prior to ordering forfeiture of a
contractor's cash deposit.
BACKGROUND: Advantage Pl umbi ng is the contractor who was hi red by the developer
of a Subdivision in north Walnut Creek which includes the construction of 336 feet
of 8-inch sewer main, private sewer project No. 3961. During the final phases of
the project, a contractual conflict arose between the developer and the contractor
and, consequently, the project was not compl eted. Hanes were subsequently
connected without i nspecti on or permits and were occupi ed duri ng the summer of
1985. In August, 1985, sewage was reported to be running out of one of the newly
constructed manhol es. Di stri ct forces responded to the emergency and performed
corrective work to eliminate the imminent heal th hazard. A subsequent
i nvesti gati on 1 ed to the concl usi on that Advantage Pl umbi ng caused the sewage
overflow by placing concrete in a manhole, apparently as a result of a payment
di spute between Advantage Pl umbi ng and the developer. Cl ean up and repai r costs
incurred by the District exceed the value of the contractor's bond.
Section 5.08.050 of the District Code provides for the forfeiture of a
contractor's $1,000 cash deposit if the appl icant viol ates any term of the permit.
The General Manager-Chief Engineer has made a determination that Advantage
Pl umbi ng has viol ated the terms of its permit by not compl eti ng the publ ic sewer
work and by all ow ing the houses to be connected to the i ncompl eted publ ic sewer
without inspection by the District or payment of connection fees.
The Board of Di rectors, at its meeti ng on May 30, set July 3 as the date for
heari ng thi s matter. Staff has sent notificati on of the proposed heari ng to
Advantage Plumbing. It is the position of staff that, unless Advantage Plumbing
prov ides substanti al evi dence at the heari ng that no viol ati ons have occurred,
the Board shoul d order the forfeiture of the contractor's $1,000 cash deposit.
RECOMMENDATION: Make a finding that the contractor has committed code and permit
violations and order forfeiture of Advantage Plumbing's $1,000 cash deposit.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INITIATING DE7'V'
13021'.9/85 D H
Central Contra Costa Sanitary Distrid
5019 Imhoff Place. Martinez, CA 94553-4392 (4151689-3890
June 9, 1986
CERTI FlED MAIL
RETURN RECEIPT REQUESTED
Advantage Plumbing
P. O. Box 20834
Castro Valley, CA 94546
Gentlemen:
FORFEITURE OF CASH DEPOSIT
This letter is to advise you that the Central Contra Costa Sanitary
District Board of Directors, at their meeting of June 5, 1986, declared
their intent to consider forfeiture of your $1,000 cash deposit for
violation of the terms of the permit on District Job No. 3961. The
Board of Directors established 7:30 p.m., July 3, 1986, as the time
and date for hearing this matter. You have the right to appear at the
hearing and to provide testimony on your behalf. If you plan to speak
at the hearing, please notify the undersigned.
Sincerely,
;J "-'{ C<. t . ) 7J <fJ:;u: c'a,,--,,
( ! .;
.../,
Joyce E. McMillan
Secretary of the District
cc: Board of Directors
R. Dolan
J. Hazard
bcc: R. Baker
J. McCoy
BOARD OF DIRECTORS
ROGER J. [)()V.N
~ral Managrr
Chi~ Englt1l!ef
JIIMES L- HIllARD
Cou~1 for ~ OosuiCl
14151938-1430
JOYCE E McMlUAN
S<<rrtary of ~ OoSUICl
PARKE L SONEVSTEELE
JOHN B. CLAUSEN
NEts E. CARLSON, JR.
President
WILLIAM C. DALTON
SlMN H. McNULlY
.
Centn.
Contra Costa Sanitar District
.
BOARD OF DIRECTORS
PAGE 1
OF 5
POSITION
PAPER
BOARD MEETING OF
Jul
3, 1986
NO.
v. BIDS AND AWARDS
SUBJECT
AUTIiORIZE $61,818 IN SEWER OONSlRUCTION FUNDS AND
AUTIiORIZE ~AAD OF PUROiASE ORDER TO EtJfRSON ELECTRIC
OOMPANY FOR FURNACE INOOCED DRAFT FAN V NHABLE FREQUENCY
DRIVES
DATE
June 30, 1986
TYPE OF ACTION
AUTIiORIZE FUNDS
AUTIiORIZE ~AAD
SUBMITTED BY
David Reindl
Assistant En ineer
INITIATING DEPT./DIV.
Plant Operations Department/
Maintenance
ISSUE: On June 23, 1986, sealed bids for District Project 10017, for the purchase
of Furnace Induced Draft Fan Variable Frequency Drives were opened. The Board of
Directors must award a contract or reject proposals within 45 days of the bid
opening.
BACKGROUND: Each of the multiple hearth furnaces is equipped with a 200 hp motor-
driven damper-controlled, induced draft fan- This system is considerably oversized,
where reduced a i rfl ow is requi red by the furnace for normal operati on. Under such
operating conditions the damper is 85 percent closed. This mode of operation wastes
costly electrical power. A variable frequency drive will allow these fans to run at
a slower speed under these conditions matching air flow to the furnace requirements.
Reducing the fan speed 1s the most effective method of saving electrical energy in
this case. The District staff has calculated the cost savings to be realized by
installing a variable frequency drive at approximately $30,000 per year. The simple
payback on the installed cost is approximately two and one-half years.
The District's staff has evaluated the bids listed in Attachment 1 and determined
that the lowest responsible bidder is Emerson Electric Company with a bid of
$50,817 .69. The engineer's cost estimate for the installation of the drives is
$19,500. This installation work will be bid prior to the delivery of the units in
October, 1986.
REOOMMENDATION: Authorize award of a purchase order for DP 10017, Furnace Induced
Draft Fan Variable Frequency Drives to Emerson Electric Company and authorize
$61,818 from Sewer Construction Funds for purchase and engineering.
1302.....9/85
DR
J.1S,
~
JB
OMMENDED FOR BOARD ACTION
LAN
25;??PT./DIV
Central Contra Costa Sanitary District
June 24, 1986
TO: DAVID REINDL, ASSISTANT ENGINEER
FROM: CHERI ARSTANI, BUYER' ~------
SUBJECT: BID REQUEST NO. T0027C, VARIABLE FREQUENCY DRIVES
Formal bidding commenced with publication of Notice inviting sealed bids on
June 7 and 16, 1986. Ten bid packages were distributed to bidders who had
expressed an interest in bidding this project.
Bids were publicly opened and read on Monday, June 23, 1986. The following
nine bids were received:
1. Sweetland Company
2. Emerson Industrial Controls
3. Stuart Associates (Sabina)
4. Unger Brothers (Toshiba)
5. Reliance Electric
6. Eaton Corporation
7. Square D Company
8. Air Treatment Equipment Corporation (Sabina)
9. Allen-Bradley
A commercial evaluation was conducted by Purchasing (See Attachment 1.) The
evaluation reveals that the lowest responsible bidder is Emerson for $50,817.69.
Purchasing recommends that you prepare the position paper to the Board of
Directors recommending award to Emerson for Variable Frequency Drives at the
lump sum price of $50,817.69.
Attachment
,..,
~1I
--
V
o I +uaw4J~n'd
.
I 0
a. ~ ~'" ("I')
~!It ~ 0
~ ~ c ~ l!f 0
v '" 0
~~ I.~ -l-' '" 0
~ I-~ ("I')
~ l.O
';:; ~'" I ~
.u f\l I III III '"
;)f I OJ 0 OJ 0 '"
>- z: >- z:
M 0">
0">
f+J ~'" 0
~\1 '" 0">
~ C OJ ef l.O 0">
N -ttz; L.() 0
~ v ~ '"
~ '- ~ - ("I') 1.0
U ~ i: :"\. t S:H L.() L.()
'" !- ~'" I OJ . ~
N I I~ I C III III ("I')
0 I 0 OJ OJ 0 L.()
0 ~ ... z: >- >- z:
I-- ~
I .-t
0
~ eo
i I; Ie ~t! ("I')
.-t 0
I '" ~ ::.::I~ ~f ~ 0
i c 'd" 0
~ V ~~ '" eo
{,.. 0 ("I')
{,.. 0"> ~ .-t
~ (,.. ~'" l.O III 0 ~
I~ 0 OJ 0 C 0 'd"
2~ ~ >- Z or- Z '"
'" :E
("I')
0">
i'" 1.0
0
e~ '" 0">
~ .-t 1.0
r;- eo 0
r; tl~ - ~ '"
~ <::> .-t
::=, L.() eo
~ ~ ~2 itl I OJ III OJ III ~
l- I C OJ C OJ 0
;,f I 0 >- 0 >- L.()
z: z:
III
OJ ~
> ~i or-
or- .0
~ rn
Cl 0
Z ~
>, ~ or-
U . o::l
C
OJ ~ ~i 0
~ I z:
0- I
OJ I
I s-
I..L.
'+- ..E;
OJ III I 0
r- Ii OJ or-
.0 > 0) X
to i i I e"'a: or- e to ~
I or- I I s- OJ .j..J OJ
s- j ~ i ~~i ~ s-
to o ... ~ III ~
> ~ d . II: ~ >- r- OJ
... Q to: Q S ... u OJ r- OJ
> . ...
.. C Or- to ~
... OJ '+- III
is 6 C'-o C'-o
~ '+- ~ V) OJ OJ C
OJ 0 C Z > V) > 0
s- to 0 or- z: or- or-
'+- III ...... III 0 III .j..J
.. -e: OJ. III I-- c ...... C to
a ..... ..c OJ u .j..J a.. 8- I-- 0 ~
to I ..... or- s- I..LJ a.. 0. .....
- .0 > to U III I..LJ III to
.. or-
s- ~ to s- o. >< OJ U OJ >
.. .j..J or- OJ I..LJ c:: >< c:: OJ,.-.
0 III i: r- i- s- III OJ I..LJ
Z ~ r- C.. to s- -1 ~ ~ .....r.....
~ ~ ~: > 0) to c:( OJ -1 OJ to ~
0 c (; C 0. ...... s- c:( s- u c
- ...... III ......... or- III U OJ U OJ or- or-
3 ~ (\J ~ 0:: ~ ...... ~ c OJ
c ~ I........ ~ ~ I..LJ or- Z or- ..c:: 0::
0 r- s- ~ ~ III :r: III u
::I III s- o 0 U OJ L.() :E c u c OJ
.. s- ~ 3: c OJ 0 0: 0 I..LJ 0 I-- Cl
:! OJ +-' I-- or- e 1.0 u u I-- u ........
E III ~i
I..LJ OJ
3: l~ .j..J
t 0 ; l 0
-l i -1
I I i r
~- Ii 0 , 0
. I .-t N ("I')
,..-,
\::11
\:!I'
..ow
~!l
~f
..w
fY
~f
> l.O
O"l
(]) ~w .
:;::; ..~ 0 l.O
;:0 a ef l.O O"l
C'\J Xl :::l ~ M
~ M " 0
..... q f- 'o::j- l.O
~ I :::l t 00 M
U s::: 'l :l s... ..w "
r-... (]) I- Z i~ Ul Ul o::j-
C'\J - j.c (]) 0 (]) 0 00
0 ;: ::IlL >- Z >- Z
0
:s f-C'\J
. j.J
2 1.0
i s::: ~w o::j-
e~ ..~ l.O 0
~ ip ef " 0
l.O .
n:s ~ ?;: 00 1.0
(]) ~ o::j-
s... ~ / s... l.O
- :::l i .... Ul 0 Ul "
~ s... i~ I (]) 0 s::: (]) l.O
s... f- ::IlL I >- Z or- >- 00
~ ~ I :E:
I~ 00
~.. O"l
.
l"tr 5~ C'\J 00
~ ..lL 0 O"l
~ 1:2 1.0 .
(]) ~ - " C'\J
s... Vj .~ Ie l.O 0
n:s ~ ~ 1.- l.O 1.0
15 ..w I "
~ f--l f- I iY I Ul Ul l.O
l/J ::Ill: I (]) 0 (]) 0 l.O
I~ lL
>- Z >- Z
Ul
(])
> l.O
.r- ~g C'\J
s... 0 0
Cl " 0
~ I~ e.. 1.0 .
~ i=l It l.O l.O
s::: ;:: ~ C'\J
s::: 0 1= I~ 0
(]) rrt "- f-.J ~ s... "
:::l I-' I~ (]) 0 1.0
c::r ~ t s::: Ul e Ul l.O
(]) ::Ill I 0 (]) or- (])
..
s... t Z >- :E: >-
I 1.1..
(]) 4- ~
~ Ul I 0
..0 !~ (]) '~
n:s > ><
or- i ~ I z wa: 'r- to ~
I s... e o- s... (]) .j-)
n:s I B w l:! . 1 ~ 8i -0
::> i ~ lL -0 Ul !
g . ~
d .J c = ~ ~ (])
... w
> 0": 0 S (]) ~
.. s::: .r- n:s
.. (]) 4- Ul
a 5- C'-. C'-.
4- -0 V') (]) (]) ,g
(]) 0 e z > V') >
s... n:s 0 .r- Z .r-
4- Ul ...... Ul 0 Ul ~
tit (]) Ul l- s::: ...... s:::
a (]) u .j-) 0- 0 I- 0 =
- I ~ 'r- s... L.LJ 0. 0- 0. ~
. ..0 > n:s u Ul L.LJ Ul
II. n:s s... 0. x (]) u (]) ~
.r- (]) L.LJ 0::: X 0:::
0 - s... Ul (]) L.LJ .--.
Z .. n:s g s... ...J -0 -0 ~!O
!C > n:s c::c: (]) ...J (])
0 0 0. ...... s... c::c: s... .~ s:::
3 ,........ .r- III U (]) U OJ .r-
C'\J -0 a::: "0 ...... "0 ~ OJ
........ :::l " L.LJ 'r- Z 'r- a:::
~ s... ~ :E: Ul :::r:: Ul ]
:::a 0 u (]) l.O :E: s::: u s:::
. ::: s::: (]) . 0 0 L.LJ 0 Cl
:! I- 'r- e 1.0 u u f- u '-
i.
~ !~
I ; i .j-)
a-= 0
...J
I I .. 0
s z
..,- .
Ii Ei .
. ....-t N M
.. ,
ATTA(}lMENT 2
FURNACE INWCED mAFT
Y ARIABLE FRBWENCY mIYES
Authorization of Funds
Cost SlII1mary
Prepurchase:
Two 200 hp variable frequency drives
Manufacturer's recommended spare parts
Sales tax 6.5 percent
Equipment startup services
Total Prepurchase
Force Account:
Engineering/Design Review
Contingency
TOTAL. AUTHORIZATION
$ 43,468
2,558
2,992
1, 800
$ 50,818
$ 8,000
3,000
$ 11,000
--. -
$ 61,818
.
Centra.. Contra Costa Sanitar. District
BOARD OF DIRECTORS
PAGE 1 OF 2
POSITION
PAPER
BOARD MEETING OF
J ul Y 3, 1986
NO.
VI.
CONSENT CALENDAR 1
SUBJECT
AUTHORIZE THE EXEQJTION OF A (X)NSENT TO DEDICATION TO
CONlRA (X)STA (X)UNTY (JCB 1379-PARCEL 2) SUB. 6559,
(x)N(x)RD AREA
DATE
June 25, 1986
TYPE OF ACTION
APPROVE roNSENT TO
DEDICATION
SU.E!MITTI;D BY.
Uenn1s Hall, Associate Engineer
INITIATING DEPT./DIV.
Engineering Dept./Construction Dept.
ISSUE: The County requires a "Consent to Dedication" whenever an area dedicated
for public road purposes encroaches upon an existing easement.
BACKGROUND: Two new roads, Laura Alice Way and Nel son Avenue, will be dedi cated
for public use when the map of Subdivision 6559 is filed with the County Recorder.
Portions of an existing CCCSD sewer easement lie within these two roads. A
standard consent to dedication document has been prepared through which the
District retains prior rights.
RE(X)MMENDATION: Approve the Consent to Dedication to Contra Costa County, Laura
Alice Way and Nel son Avenue, Subdivisi on 6559, Job NO. 1379, authorize the
President of the District Board of Directors and the Secretary of the District to
execute said document and authorize its recording by Contra Costa County.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
w
INITIATING DEPT./DIV.
1302....-9/85
~
~
::CIi
~
,
" ,
.......
, "'.....
,,,"
~ ~ ~
...~...
~ ""
..... "
"" '"
,
""
p(J "t7.9r
:g.-S5g/
~
,:.~ $-;; J'P~",
i '.M7 .,(';-Pr///YI':.Jf~
r p:rAf2. .. ;;(~-
.- U . ~'//yj;).o;
AREA OF
CONSENT
I
VICINITY MAP
NTS.
CONSENT TO DEDICATION
LAURA ALICE WAY & NELSON AVENUE
SUB 6559 - CONCORD AREA JOB 1379
~
f\')
-\.0
U")
~
i'
o;w
- ::>
0: a::
C> I-
.
Centr... Contra Costa Sanitar.. District
BOARD OF DIRECTORS
PAGE 1 OF
POSITION PAPER
NO.
VII. ENGINEERING
SUBJECT DATE
AUTHORIZE $5,000 FROM THE SEWER CONSTRUCTION FUND FOR
FINAL DESIGN OF HILLCREST DRIVE LANDSLIDE REPAIRS, DISTRICT TYPE OF ACTION
PROJ ECT 3886; AUTHORIZE THE GENERAL MANPGER-CHIEF ENGINEER AUTHORIZE FUNDS
TO EXECUTE A J OINT LANDSLIDE REPAIR PGREEMENT WITH MR. AUTHORIZE PGREEMENT
LOUIS SAULACICH AND MR. WILLIAM HAM
SUBMITTED BY
Robert A. Simmons
Associate En ineer
ISSUE: Board authorization is required for the General Manager-Chief Engineer to
execute an agreement with Mr. Louis Saulacich and Mr. William Ham, the homeowners
on whose properties the subject landslide occurred.
BACKGROUND: In the winter of 1982 a landslide displaced and damaged approximately
200 linear feet of 6-inch vitrified clay sewer pipe between the residences at 114
Hillcrest Drive and 139 Meadow View Road in Orinda (see Fig. 1). As an emergency
acti on, the sewer 1 ine was repl aced with temporary above-ground PVC sewer pi pe
which crosses the slide uphill from the District's sewer easement. To prevent the
slide from enlarging, plastic sheeting was placed over the slide area and has been
maintained for the past three rainy seasons.
A predesign study was undertaken to determine the cause of the slide and establish
the available alternatives for restoring permanent sewer service to the properties
affected by the slide. It was concluded that the slide was caused by soils which
lost strength due to saturati on by surface and subsurface water. The predesi gn
study identified two alternatives for restoring permanent sewer service. The
alternatives involve either repairing the slide and reconstructing the sewer or
relocating the sewer away from the sl ide. The sl ide repai r was estimated to be
approximately $15,000 more costly than the sewer rel ocati on. Di stri ct staff
entered into negotiations with the owners of the land where the slide occurred
after having been informed of their desire to have the slide repaired. An
agreement was negotiated which provides for each homeowner to contribute a fixed
amount of $7,500 toward the proj act. The agreement is reasonabl e from the
District's point of view.
Desi gn work w ill be performed by a proj ect team consi sti ng of Di stri ct staff and
personnel from Woodward-Clyde Consultants (WCC). The work by wee will be
performed under a purchase order agreement. Di strict staff will be responsi bl e
for proj ect management, the desi gn of sewer repl acement work, and pl ans and
specification preparation. WCC will be responsible for the slide repair design.
A breakdown of the estimated costs associated with the authorization is presented
in Attachment 1 to this position paper. The total authorization being requested
is $5,000. Funds for construction of the landslide repair will be requested at
the time of award of the constructi on contract. The total proj ect cost is
estimated to be $120,000.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
;J~1~
1302A.9/85 RAS
DRW
RAB
INITIATING DEPT./DIV.
.(]Pcu
mE
SUBJECT
AUlliORIZE $5,000 FROM lliE SEWER CONSTRUCTION FUND FOR
FINAL DESIGN OF HILLCREST DRIVE LANDSLIDE REPAIRS, DISTRICT
PROJ EeT 3886; AUTHORIZE THE GENERAL MANPGER-CHIEF ENGINEER
TO EXEaJTE A JOINT LANDSL IDE REPAIR ~REEt.ENT WITH toR.
LClIIS SAULACIQ-I AND MR. WILLIAM HAM
POSITION PAPER
PAGE 2 OF 4
DATE
June 30, 1986
RECOMMENDATION: Authorize $5,000 from the Sewer Construction Fund to design the
Hillcrest Drive Landslide Repair Project, District Project 3886. Authorize the
General Manager-Chief Engineer to execute the joint landslide repair agreement
with Mr. Louis Saulacich and Mr. William Ham.
1..._______..
13028-9/85
- CCCSD ENGINEERING DIVISION
PROJECT ...... ......1.~.?~..~.T.9.Rt1...I?M1A.G.~..R~p.A.~RS...........................:........... ...... .... ...... SHEET. 3... ." OF..... 4~ ...."
SUBJECT. ......... J~V(:.:-.~ U?lJ.L.. .... ................... .............. ..... .............. ......................... BY.. .REC...... DATE.. 4/261
....... ..................9fF..JU.tJ.CRES.r..OR......:QRINDA..7.1B.5..... ................... .'. ..... ... ........ CHK'D........... DATE..
~rl'IH
/
zlfr
p~~ 96~
,A'
I
\
4
-
." /
~",-
r' tt4
,912
\ .
,z'-
,,~ 1,t4
,91
t-\'
f'~!J 9 ~t4
p" .
/
f
O'~
~& f~1&
~C &'
,0'
j\ ."
,&\"1\
~~f,)f,) /'
/
ff~
Off
,&
.,q.
.
'Jib
FIG. I
ATTAOiMENT 1
HILLCREST DRIVE SLIDE REPAIR
Di stri ct Proj ect No. 3886
BREAKDOWN OF COSTS
District Forces:
o
Proj ect Management
o
Engineering Design/Drafting
Consultant:
o
Woodward-Clyde Consultants
o
Contingencies
Total Funds Required $15,000
$ 500
4,500
9,000
1,000
General Manager-Chief Engineer Authorization 10,000
Total Authorization Requested $ 5,000
Page 4 of 4
.
Centrt..__ Contra Costa Sanitar:, District
BOARD OF DIRECTORS
PAGE 1 OF 5
POSITION
PAPER
BOARD MEETING OF
Jul
3, 1986
NO.
VIr.
ENGINEERING
2
SUBJECT
AUTHORIZE GENERAL MANJlGER-CHIEF ENGINEER TO EXECUTE AN
AGREE~NT WITH J AMES K.)NTGO~RY CONSULTING ENGINEERS
AND AUTHORIZE $488,110 IN SEWER CONSTRUCTION FUNDS FOR
PRELIMINARY DESIGN OF THE SAN RAMON VALLEY SEWER
IMPROVEMENT PROJ ECT
DATE
June 30, 1986
TYPE OF ACTION
AUTHORIZE AGREEMENT
AUTHORIZE FUNDS
SUBMITTED BY
Curtis W. Swanson, Principal Engineer
INITIATING DEPT./DIV.
Engineering Dept./Planning Division
ISSUE: Board of Directors' authorization is required for the General
Manager-Chief Engineer to execute consulting engineering agreements and to expend
sewer construction funds.
BACKGROUND: The District is pl anning to construct a new l2-ml1e trunk sewer to
serve the San Ramon Valley. Portions of the existing trunk sewer are at capacity.
The remainder of the existing sewer is projected to reach capacity by the late
1980's or early 1990's. Staff proposes to begin construction of the new trunk
sewer in 1987. More information about the project is included in Attachment 1.
Design of the trunk sewer will be accomplished in two steps: a preliminary design
of the entire l2-mlle sewer followed by a detailed final design of each of the
proposed three phases of the sewer. Final design of the first phase of the sewer
(approximately five miles) is scheduled to be completed by March 1987.
District staff formally requested proposals from seven consulting engineering
firms with experience in design and construction of large trunk sewers. After
evaluating these proposals, three firms (John Carollo Engineers, CH2M-Hill, and
James M. Montgomery) were invited for an oral interview. Based on the proposal,
interview, and a reference check, staff has selected James M. Montgomery to
provide the prel iminary design services for the San Ramon Valley Project. Upon
satisfactory completion of the prel iminary design, Montgomery will be asked to
submit a proposal for final design of the trunk sewer. Montgomery has been
invol ved with sewer proj ects throughout the western United States. Personnel for
the District project will be provided from Montgomery's Walnut Creek office which
has a staff of 90.
Montgomery will provide preliminary design services on a cost reimbursement basis
at a cost not to exceed $343,110. Costs for final design of the trunk sewer wil 1
be negotiated at the completion of preliminary design.
The total funds being requested for preliminary design are $488,110. A summary of
the funds bei ng requested is 1 i sted in Attachment 2. Thi s request i ncl udes
$86,000 for force account costs for project management, engineering, public
participation, and survey activities. Staff proposes to continue the pub' ic
REVIEWED AND RECOMMENDED FOR BOARD ACTION
13021'.9/85
()ztJ
DRW
SUBJEQT
p,uTIiORIZE GENERAL MAN~ER-CHIEF ENGINEER TO EXECUTE AN
,AGREEMENT WITH JAMES K>NTGOM:RY CONSULTING ENGINEERS
AND AUTHORIZE $488,110 IN SEWER CONSTRUCTION FUNDS FOR
PRELIMINARY DESIGN OF THE SAN RAMON VALLEY SEWER
IMPROVEM:NT PROJ ECT
POSITION
PAPER
PAGE
DATE
June 30, 1986
2
OF
5
information and participation program started during the EIR process for this
purpose. This effort will be accomplished by both District staff and the services
of Urban Alternatives. A budget of $10,000 is proposed for the work by Urban
Alternatives. A legal budget of $15,000 is proposed for legal assistance related
to material prepurchases, easement conditions, and permit acquisition. A
contingency of $34,000 is also included in this request, which will be used for
additional force account effort or to issue contract change orders to the
consultants to expand their scope of work, if necessary.
RECOMMENDATION: Authorize the General Manager-Chief Engineer to execute an
agreement with James M. Montgomery and authorize $488,110 in sewer construction
funds for preliminary design of the San Ramon Valley Sewer Improvement Project.
----------
13028-9/85
Page 3 of 5
ATTACH~NT 1
SAN RAMON VALLEY SEWER IMPROVEMENT PROJ ECT
PROJECT DESCRIPTION
The San Ramon Valley Sewer Improvement Project consists of the
install ation of approximately ten mil es of 1 arge di ameter gravity trunk
sewer and two mil es of force mai n (see follow ing page, Fi gure 1), The
trunk sewer and force main will be constructed from Larwin Pump Station
north to a point near the intersection of Danville Boulevard and Rudgear
Road in southern Walnut Creek. At the northern point, the proposed trunk
sewer will connect with both the existing 36-inch diameter trunk sewer
that now serves the San Ramon Vall ey and the proposed 60-inch di ameter
downtown Walnut Creek bypass sewer.
The preferred sewer al ignment is the Southern Pacific right-of-way. This
alignment will cause the least disruption to traffic, commercial, and
other activities in the valley communities. The District entered into an
agreement in December 1985 with Contra Costa County to purchase, in
general, a 20-foot-wide surface easement and a l2-foot-wide subsurface
easement within the railroad right-of-way. The cost for the San Ramon
Valley portion of the sewer easements was $2,959,900.
Because of the size of the proj ect, the trunk sewer is pl anned for
construction in three phases, as shown in Exhibit A. The first phase is
a five-mile section from La Serena Avenue in Alamo to Greenbrook Drive in
Danville. The second phase is approximately three miles long from La
Serena Avenue north to a point near Rudgear Road where the sewer will
connect with the new Wal nut Creek downtown trunk sewer. The thi rd phase
will extend four miles from Greenbrook Drive south to the Larwin Pump
Station. The third phase includes two miles of force main. The first
phase of constructi on will take care of the secti ons of exi sti ng sewer
with the most severe capacity problems.
Construction of the first phase sewer will be during 1987. The second
and third phases of the sewer are currently scheduled for 1988 and 1989.
As these two phases are not needed as soon as the first phase,
construction may be deferred for two to three years if effort must be
devoted to other higher priority District projects.
The current planning-level project cost estimate for the San Ramon Valley
Sewer Improvement Project is $28.5 million <1985 cost basis). This cost
estimate is based on a 54-inch diameter sewer. It includes engineering
and construction management costs, but excl udes the $2,959,000 al ready
committed for easement acquisition.
Page 4 of 5
r - -
I
:+Gtj,
~..
150\\
E.
o
'- -j
!
i
..~.LAS_IRAUPAS _n_"
PfAI(
0': -
. ROUNC
I-~
I
"
c:, CANYOtV
tJ<r.."''''
~
.'
E
:
~
Base Map: By permission California
Automobile ^ssociation
FIGURE 1
Regional Location-Study Area
and Project Area
)age 5 of 5
ATTACHM:NT 2
CENTRAL CONTRA roSTA SANITARY DISTRICT
SAN RAK>N VALLEY SEWER IMPROVEM:NT PROJ ECT
PRELIMINARY DESIGN roST ESTIMATE
Desc r1 ot 1 on
Funds Reouested
Consultants
James M. Montgomery
Urban Alternatives
Legal
$343,110
$ 10,000
$ 15,000
Force Account
Project Management/Engineering
Public Information
Surveying
Supplies/Services
$45,000
15,000
30,000
6.000
$96,000
$ 96,000
$ 34.000
$498,110
Contingency* (10% of Montgomery contract)
Total Funds Required
Previous General Manager-Chief Engineer
Authorization for Force Account
$ 10.000
$488,110
Total Funds Requested
*If necessary, staff will use this contingency for additional force
account effort or to issue contract change orders to the consul tants to
expand their scope of work.
.
Centr~ Contra Costa Sanitar) District
BOARD OF DIRECTORS
PAGE 1 OF 3-
POSITION
PAPER
BOARD MEETING OF
J u 1 Y 3, 1986
NO.
VIII. SOLID WASTE
SUBJECT
DISPOSITION OF PENDING MATTER RELATED TO VALLEY DISPOSAL
SERVICE, INC.'S REFUSE COLLECTION RATE INCREASE
APPLICATION
DATE
June 27, 1986
TYPE OF ACTION
INFORMATIONAL
SUBMITTED BY
INITIATING DEPT./DIV.
Walter N. Funasaki, Finance Officer
Administrative/Finance & Accounting
ISSUE: At the public hearing held on June 19,1986 to consider the refuse
collection rate increase application submitted by Valley Disposal Service, Inc., the
Board of Directors requested additional supporting information to justify an
increase in the Zone 4 hilly rate from $9.25 to $11.25 per month.
BACKGROUND: The refuse collection rates for Valley Disposal Service, Inc. have been
standardized over the past three years from three separate rate schedules to a
single uniform rate schedule, except for the hilly rate for Zone 4. After
application of the 3.2% across-the-board increase effective July 1, 1986 granted by
the Board at the conclusion of the June 19 public hearing, the Zone 4 hilly rate was
increased to $9.25, and compares with the new $11.25 hilly rate for Zones 2 and 5.
The refuse collector requested that the Board authorize increasing the Zone 4 hilly
rate an additional 21.6% to be made common with the other hilly rate. The Board
deferred acting on this request until the July 3, 1986 Board Meeting in order that a
cost analysis could be provided and reviewed.
Valley Disposal Service, Inc. has advised the Board by a letter dated June-27, 1986
that it intends to incorporate its request to conform its hilly rates in its next
general rate increase application. District staff will coordinate the distribution
of individual public hearing notices to affected Zone 4 hilly rate customers at that
time, in addition to the customary general notices of a public hearing to consider
an application for rate increase.
RECOMMENDATION: This Position Paper disposes of the remaining pending matter
related to the refuse collection rate increase application submitted by Valley
Disposal Service, Inc., without action required by the Board.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INITIATING DEPT./DIV.
1302,0.9/85
WNF
PM
McCUTCHEN, DOYLE, BROWN 6. ENERSEN
FORMERL Y
VAN VOORHIS & SKAGGS
COUNSELORS AT LAW
SAN FRANCISCO
18SS OLYMPIC BOULEVARD, THIRD FLOOR
WALNUT CREEK OFFICE
SAN ,JOSE
POST OFFICE SOX V
TELEX 34-0817
FACSIMILE GI. II AND III
(415) 937-8004
CABLE ADDRESS MACPAG
WASHINGTON. D,C,
SHANGHAI
WALNUT CREEK, CALIFORNIA 945945-1270
TELEPHONE (415) 937-8000
June 27, 1986
Mr. Walter N. Funasaki, Finance Officer
Central Contra Costa Sanitary District
5019 Imhoff Place
Martinez, CA 94553-4392
Valley Disposal Service, Inc.
Our File No. 70453-037
Dear Mr. Funasaki:
This is to confirm our telephone conversation
yesterday during which I told you that valley Disposal Service
has decided not to pursue its request in its rate application
for equalization of rates in the three special service (hilly)
zones it services. Therefore, the new rates effective July 1,
1986, for the three hilly zones should be as stated in the new
rate schedule I sent to you earlier this week. Those rates are:
Zone 2 $11.25 per month
Zone 4 $ 9.25 per month
Zone 5 $11.25 per month
As I indicated to you, Valley Disposal has developed
cost of service data which supports equalizing the rates among
the three zones. However, Valley Disposal has decided that the
additional benefit to be gained for the upcoming fiscal year by
equalizing the rates is not worth the additional time and cost
of preparing for and appearing at another noticed public
hearing, which the Board's counsel believes is required.
Mr. Walter N. Funasaki
June 27, 1986
Page 2
valley Disposal intends to again seek equalization of the hilly
rates when it submits its next rate application.
JBE:jwc2:12
cc: Francise C. Fiorentino
Anne Grodin
Sanford M. Skaggs
ruly yours,
~~
---
Ellis
.
Centr" Contra Costa Sanita~ w District
BOARD OF DIRECTORS
POSITION PAPER
BOARD MEETING OF
July 3, 1986
PAGE 1 OF 2
NO.
IX. PERSONNEL 1
DATE
June 27, 1986
TYPE OF ACTION
ADOPT M.O.U.
SUBJECT
ADOPT MEMORANDUM OF UNDERSTANDING (M.O.U.) WITH THE
MANAGEMENT GROUP, EFFECTIVE JULY 3, 1986 THROUGH
APRIL 30, 1988
SUBMITTED BY
Joyce E. McMillan
Secretary of the District
INITIATING DEPT./DIV.
Administrative
ISSUE: On May 29, 1986, a letter was received from the managers of Central Contra
Costa Sanitary District requesting to meet and confer to specify details of salaries,
wages, and working conditions. Board representatives and representatives of the
Management Group have agreed to a Memorandum of Understanding. Members of the
Management Group have ratified the agreement; accordingly, presentation to the
Board of Directors for final adoption is now appropriate.
BACKGROUND: For the past month, Board representatives and representatives of
the Central Contra Costa Sanitary District Management Group have met and conferred
in an effort to agree upon a Memorandum of Understanding to cover those positions
designated as Management positions. The Memorandum of Understanding reflects
compensation levels and benefits previously granted by the Board of Directors
to the Management Group and, in general, documents in the form of a Memorandum
of Understanding, the agreement referenced in the attached April 29, 1985, position
paper. The document parallels the Memoranda of Understanding previously adopted
by the Board for the Management Support/Confidential Group and the General Employee
Group.
RECOMMENDATION: Adopt the Memorandum of Understanding between the District and
the Central Contra Costa Sanitary District Management Group, covering all positions
designated as Management, effective July 3, 1986 through April 30, 1988.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INITIATING DEPT./DIV.
1302....9/85
ATTACHMENT
ce<SD
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
No.VIII. PERSONNEL
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATji: '1 2
APrl 9, 1985
TYPji: QF ....CT,tON
AOOp't L.ompensation
Changes for
Management Group
SUBJECT
MANAGEMENT GROUP COMPENSATION ADJUSTMENTS
SUBMITTED BY
Management Group
INITIATING DEPT./DIV.
ISSUE: The Management Group requests the Board of Directors to consider the
following Management compensation proposal.
BACKGROUND: The Board of Directors has received a Memorandum of Understanding
(M.O.U.) covering the General Employees Group. In recognition of its responsi-
bilities to the Board, the public, and to the District employees, the Management
Group proposes the following changes in management compensation which parallel
the general guidelines of the General Employees Group M.O.U.
1. The Managers will receive the following general increases:
o 5%
o 5%
o 3-8%
effective May 1, 1985
effective May 1, 1986
effective May 1, 1987 (depending upon the Consumer Price Index)
2. The Managers will accept the two tier benefit plans for managers hired by
the District after May 1,1985, in the areas of vacation, sick leave policy,
medical plans, and retirement program.
3. The Managers will receive the same benefit changes as stated in the General
Employees Group M.O.U. in the areas of holidays and longevity compensation.
RECOMMENDATION: Adopt salary and benefit adjustments as set forth in this
position paper for employees designated as Management and for the Secretary
of the District. This action would encompass members of the Management Team
except for the General Manager-Chief Engineer, who requests that no change
be made in his compensation or benefit package.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
f
.
Centrl Contra Costa Sanitar. District
BOARD OF DIRECTORS
PAGE 1 OF 2
POSITION PAPER
BOARD MEETING OF
NO.
July 3, 1986
IX.
PERSONNEL 2
SUBJECT
DATE
June 24, 1986
APPROVE AND AUTHORIZE EXECUTION OF EMPLOYMENT CONTRACTS
FOR THE GENERAL MANAGER-CHIEF ENGINEER AND THE SECRETARY
OF THE DISTRICT
TYPE OF ACTION
APPROVE AND
EXECUTE CONTRACTS
SUBMITTED BY
Roger J. Dolan
General Mana er-Chief En ineer
INITIATING DEPT.lDIV.
Administrative
ISSUE: Final Board approval and execution of the Employment Contracts for the
General Manager-Chief Engineer and the Secretary of the District are now
appropriate.
BACKGROUND: The General Manager-Chief Engineer and the Secretary of the District
have met with the Board's representative and have agreed upon Employment Contracts
for those two Executive Management positions. The Employment Contract for the
Secretary of the District provides for salary adjustments and benefits consistent
with the decisions made in the attached April 29, 1985, position paper. The
Employment Contract for the General Manager-Chief Engineer does not include any
adjustments in the salary that has been in effect since May 1, 1984, but does
provide for buy-back of credit for previous public service to the Contra Costa
County Employees' Retirement Association in an amount that is somewhat less but
generally consistent with the percentage increase approved for the Management
Group and the Secretary of the District in the April 29, 1985, position paper.
RECOMMENDATION: Approve and authorize execution of Employment Contracts for the
General Manager-Chief Engineer and the Secretary of the District, effective May 1,
1986 through April 30, 1988.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INITIA TING DEPT.lDIV.
ATTACHMENT
<C<SD
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
NO.VIII. PERSONNEL
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATApri 1 29, 1985
TYPii: 9F "CTJ.ON
AOOpt ~ompensation
Changes for
Management Group
SUBJECT
MANAGEMENT GROUP COMPENSATION ADJUSTMENTS
SUBMITTED BY
Management Group
INITIATING DEPT./DIV.
ISSUE: The Management Group requests the Board of Directors to consider the
following Management compensation proposal.
BACKGROUND: The Board of Directors has received a Memorandum of Understanding
(M.O.U.) covering the General Employees Group. In recognition of its responsi-
bilities to the Board, the public, and to the District employees, the Management
Group proposes the following changes in management compensation which parallel
the general guidelines of the General Employees Group M.O.U.
1. The Managers will receive the following general increases:
o 5% effective May 1,1985
o 5% effective May 1,1986
o 3-8% effective May 1, 1987 (depending upon the Consumer Price Index)
2. The Managers will accept the two tier benefit plans for managers hired by
the District after May 1,1985, in the areas of vacation, sick leave policy,
medical plans, and retirement program.
3. The Managers will receive the same benefit changes as stated in the General
Employees Group M.O.U. in the areas of holidays and longevity compensation.
RECOMMENDATION: Adopt salary and benefit adjustments as set forth in this
position paper for employees designated as Management and for the Secretary
of the District. This action would encompass members of the Management Team
except for the General Manager-Chief Engineer, who requests that no change
be made in his compensation or benefit package.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
f