HomeMy WebLinkAboutAGENDA BACKUP 09-05-85
ce<S
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
NO. IV. BIDS AND AWARDS
1 9 5 85
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
Au ust 30, 1985
SUBJECT
AWARD OF CONTRACT FOR DISTRICT PROJECT NO. 4082, WATERSHED
13-LANCASTER ROAD PARALLEL, WALNUT CREEK, AND AUTHORIZATION
OF $161,449 FROM THE SEWER CONSTRUCTION FUND.
TYPE OF ACTION
AWARD CONTRACT
AUTHORIZE FUNDS
SUBMITTED BY
James L. Hill, Associate En ineer
ISSUE: Sealed bids for District Project No. 4082 were received and opened on
August 27, 1985. The Board of Di rectors must award the contract or reject bids
within 60 days of the opening of bids.
BACKGROUND: A Planning Division study concluded that wet weather overflows in a
6" tributary sewer at Castle Hill Court, Walnut Creek; are due to inadequate
capacity of the downstream 100i nch mai n sewer in Lancaster Road, Wal nut Creek.
The study indicated that a parallel main sewer in Lancaster Road is required to
handle current peak wet weather flows as well as projected peak flows in that
local watershed, and prevent any further overflows at Castle Hill Court.
Attachment 1 to this position paper is a map of the proposed work.
The work consists of constructing approximately 1,500 feet of 12-inch and IS-inch
main sewer from the intersection of Castle Hill Road and Lancaster Road, Walnut
Creek, north along Lancaster Road parallel to the' existing lO-inch and 12-inch
main sewer constructed previously under District Project No. X1566. The project
will include four new manholes along Lancaster Road, as well as modifications to
existing manholes to allow splitting and recombining of the flow. The existing
6-inch sewer along Castle Hill Road, which was constructed under District Project
No. 3977, is also tied into the new parallel force main to prevent future sewage
overflows at Castle Hill Court.
Plans and specification for the project were completed and advertisements inviting
submission of sealed bids were placed in the local newspaper on August 12 and
August 20, 1985. The engineer's estimate for the contract work is $116,142.
Bids were received and opened August 27, 1985. The bid tabulation is included as
Attachment 2 to this position paper. The lowest responsible bidder is Orca
Construction Company at $131,949.
The post bid/preconstruction cost estimate is included as Attachment 3 to this
position paper. The total project cost is estimated at $175,449. $161,449 in
additional funds are required for the construction contract cost, construction
contingencies, and construction management and inspection costs.
This project is included in the Five-year Capital Improvement Plan.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
~
DRW
!lflB
RAB
RECOMMENDATION: Award the contract for construction of District Project No. 4082
to the lowest, responsible bidder, Orca Construction Company. Authorize $161,449
from the Sewer Construction Fund for construction, construction management and
inspection, and contingencies.
It~VIEWED AND ItECOMMEND~D FOIt 80AltD ACTION
INITIATING DEPT ./DIV.
GEN. MGR.lCHIEF ENG.
, ._----,.~~._.~----,._-----_.__._._~._"...,'.._--".~~---~._---",._-~-~._---,._.--,.~_..._..._~-'--'---_.._-----_.~---,--_._--~---,..._---........---,-----------
-
~
'a~
~\
\
}
'\
\
-:;\
.J
u.1 'Sr
~ b\
4. :"1
(.) ~,
~
~ ~
~......"""
" ;.. ....)
-- ~~
. ______ ,~J.
G
-
, S~
,_____~\'ll
r:i
1&1
II::
U
s
I
.1 i
1&1
- :t
.. i z
z 0
1&1 8
~
:x ~
u 9
~
II:: ~
i( II::
i ~
N
!
Do.
a
ATTACHMENT 2~
Central Contra Costa Sanit..ty District
.UMMARV DF .IDS
PROJECT NO. 4082
__ Lancaster Road Trunk Parallel
DATE 8/27/85
ENGR. EST. $ 11 n .14? nn
LOCATION Lancaster Road. Wal nut Creek
~ BIDDER (Name, telephone & address) I BID PRICE
1 Orca Construction Co. (415 ) 449-0222 $ 131.949
1R?fi r.~talina Ct . Li\lennore, CA 94550
2 Mountain Cascade. Inc. (415 ) 837-1101 $ 153,785
P. O. Box 116. San Ramon. CA 94583
3 ManIJe1 C Jttrdim. Inc. (415 )4A7-0444 $ 161,340
P. O. Box 677, Union City, CA 94587
~
4 Fee Construction Inc. (415 )656-0451 $ 178,782
P. O. Box 1727. Fremont. CA 9453A
5 MGM Construction Co. (415 )685-A812 $ 185.440
P. O. Box 5757. Concord. CA 94524
-
6 L&S General Contractors, Inc. (415 )944-1313 $ 254.877
2672 Quiet Place Drive~ Walnut Creek, CA 94598
-
( ) $
( ) $
( ) $
( ) $
( ) $
-
( ) $
( I f ..-
"..A. ~r rYl.11 A
71' ~. III
() U .-
a:
PREPARED BY James L. H,ll
DATE
8/27/85
SHEET NO.
1 OF 1
2503-9/84
"----,_._--~-------_._,-~-_._-_.----~._..__.__.._'--~---,..-._----~_.__._~---_._..,~.....+,-,.,'".._-,._---_._-,_._-~,.,....,...-+-
ITEM
10.
ATTACHMENT 3
POST BID - PRECONSTRUCTION ESTIMATE OF COSTS
FOR
DISTRICT SEWERING PROJECT 4082
DESCRIPTION
ITEM AMOUNT
1.
Construction Contract (As Bid) .
TOTAL
. $ 131,949
19,800
2.
Estimated Construction Contingencies
. . . . . . $
3. Estimated Construction Incidentals to Project Completion
Survey. . . $ 1,500
Inspection . $ 5.600
Engineering . $ 1,500
Total Estimated Construction Incidentals
. $ 8.600
4.
Street Resurfacing or Seal Coat
5.
Total Estimate Required to Complete Project
6.
Pre Bid Expenditures
Survey, Engineering, Printing, Advertising
Special Services
Right-of-Way Acquisition. . . '. . .
. $ 15,100
. $ -0-
. $ -0-
7.
Total Preconstruct ion Incidentals (as of 8/30/85 ). . $ 15.100
8.
Total Estimated Project Cost
(Items 5 & 7)
$ 8 . 600
. $ -0-
.$ 160.349
$ 15 .100
. $ 175,449
14,000
9.
Funds Previously Authorized
. . . . . . . $
Total Additional Funds Required to Complete Project.
(Item 8 minus Item 9)
. $ 161.449
% CONST.
CONTRACT
100
15
7
o
122
11
133
2050-8-78
<C<S
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
NO. IV. BIDS AND AWARDS
5
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
Au ust 30, 1985
SUBJECT
TYPE OF ACTION
AWARD OF CONTRACT FOR DISTRICT PROJECT NO. 4060, STORM DAMA E AWARD CONTRACT
REPAIRS - RAINTREE PLACE, LAFAYETTE, AND AUTHORIZATION OF AUTHORIZE FUNDS
$42,580 FROM THE SEWER CONSTRUCTION FUND
SUBMITTED BY
James L. Hill, Associate En ineer
ISSUE: Sealed bids for District Project No. 4060 were received and opened on
August 22, 1985. The Board of Directors must award the contract or reject bids
within 60 days of the opening of bids.
BACKGROUND: Heavy rains during the winter storms of 1982-83 damaged the District's
8-inch sewer crossing at Las Trampas Creek behind #926 Raintree Place, Lafayette.
It is necessary to replace the sewer line and creek crossing to prevent
interruption of service to approximately 90 properties which are connected upstream
of the sewer creek crossing. Attachment 1 to this position paper is a location map
of the proj ect.
The project consists of reconstructing 75 lineal feet of 8-inch pipe crossing
Reliez Creek in the vicinity of Raintree Place and replacing another 126 feet of
8-inch sewer pipeline and appurtenances, using a new alignment to correct
maintenance problems.
Plans and specifications for the project were completed and advertisements inviting
submission of sealed bids were placed in the local newspaper on August 5 and August
14, 1985. The engineer's estimate for the contract work is $27,300.
Bids were received and opened August 22, 1985. The bid tabulation is included as
Attachment 2 to this position paper. The low bidder is Richard Sawdon General
Engineering Incorporated at $33,550. The reasons for the discrepancy between the
low bid and the engineer's estimate are:
1. The installed cost of the steel pipe for the crossing repair was
significantly higher than what was estimated, and what had been bid on
previous jobs.
2. The majority of contractors who were contacted regarding bidding on this
project had other work in progress and were unable to bid.
The post bid/preconstruction cost estimate is included as Attachment 3 to this
position paper. The total project construction cost is estimated to be $42,580,
and includes the construction contract cost, construction contingency, and
construction management and inspection costs.
This project is included in the Five-year Capital Improvement Plan.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
AJ~
lF$
INITIATING DEPT./DIV.
JLH
DRW
RAB
RECOMMENDATION: Award the contract for construction of District Project No. 4060
to the lowest responsible bidder, Richard Sawdon General Engineering Incorporated.
Authorize $42,580 from the Sewer Construction Fund for construction, construction
management and inspection, and contingencies.
It~VlnIEO "NO It~COMM~NO~O 1'0. 'OAItO ACTION
INITIATING DIEPT ./DIV.
GEN. MGR.lCHIEF ENG.
I
I~
1Cl'\
tl.
~
~
~
.:t:
-
r-
r-
1'\1
~
~
ArrACHMENT 1
DP 4060 - RAINTREE PLACE, LAFAYErrE
PROJECT LOCAnON MAP
6 U B
~
.5 0/6 \ ~
/8 -
/
~IJAJeCr ro t}(8"
5r A..3+ 75'f5 i IAlE A
2.0
19
JACKSOlJ
~
~
I?
. . ~TTACHMENT 2
Central ,__ontra Costa Sanltf 'Y District
SUMMARY DF BIDS
PROJECT NO.
4060 Storm Damage Repairs
DATE August 22, 1 qR5
ENGR. EST.~ 27.300.00
LOCATION
Raintree Place. Lafayette
W BIDDER (Name, telephone & address) BID PRICE
,....:-
Richard Sawdon ( 415) 820-2746 ,$
1 P.O. Box 350. Diablo, CA 94528 33.550.00
-
Roto-Rooter (415 ) 939-3100 $
2 47,395.00
195 Mason Circle, Concord, CA 94520
MGM Construction Co. ( 415) 685-8812 $
3 1785 Arnold Industrial Hwy . , Concord, CA 94520 76.430.00
-
( ) $
~
( ) $
( ) $
( ) $
~
( ) $
( ) $
c.
( ) $ ;
~
( ) $
( ) $
II:
PREPARED BY James t-'. Hill
DATE A'lg ?2, 1925
SHEET NO.
1 OF 1
2503-9/84
ATTACHMENT 3
POST BID - PRECONSTRUCTlON ESTIMATE OF COSTS
FOR
DISTRICT SEWERING PROJECT 4060
ITEM DESCRIPTION ITEM AMOUNT TOTAL
1. Construction Contract (As Bid) . .$ 33,550
2. Estimated Construction Contingencies . $ 5,030
3. Estimated Construction Incidentals to Project Completion
Survey. . $ 2,000
Inspection .$ 1,100
Engineering . $ 900
Total Estimated Construction Incidentals . $ 4.000 $ 4.000
4. Street Resurfacing or Seal Coat .$ -0-
.
% CONST.
CONTRACT
100
15
12
o
5. Total Estimate Required to Complete Project . $ 42,580
6. Pre Bid Expenditures
Survey, Engineering, Printing, Advertising . $
Special Services . $
Right-ot-Way Acquisition. . $
7. Total Preconstruct ion Incidentals (as ot ) . . $ $ -0- *.
8. Total Estimated Project Cost . $ 42,580
(Items 5 & 7)
9. Funds Previously Authorized . $ -0-
10. Total Additional Funds Required to Complete Project. . . $ 42.580
(Item 8 minus Item 9)
* All design work was completed under DP 20008 - Storm Damage, and is
therefore not applicable to this project budget.
127
2050-8-78
District
BOARD OF DIRECTORS
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
NO. V. CONSENT CALENDAR
5
DATAugust 26, 1985
T Y P Ap}:~Rt)\lEo tlu ITo. AIM
OF EASEMENT
SUBJEco.UITo.AIM SEWER EASE~NT, JOO 4065, SUBDIVISION 6292,
SANDERS RANQi, K>RPGA AREA
SUBMIT1..~NBN:tS
UtI 11 HALL, ASSOCIATE ENGINEER
INITltJJ~!N'EER:i~~rDEPT /CONSTRUCTION DIV.
ISSUE: Smith and Wallace Development Canpany, ONner-developer of Subdivision
6292, has requested the 01 strict to qu1tcl aim the sewer easements which lie
within Lots 32 through 39 of Subdivision 6292.
BACKGRa.JND: The subj ect easements were dedicated to th1 s 01 strict when the
subd1v 1 son map was f 11 ed. The al1 gnment of the sewer was subseq uentl y adj usted
to conform to District requ1ranents. A new easement has been granted for the
revised sewer alignment. The subject easements are no longer needed.
RECOMMENDATION: Approve Quitclaim Deed to Smith and Wallace Development Canpany,
Job 4065, authorize the President of the District Board of Directors and the
Secretary of the 01 strict to execute sa1 d Quitcl aim Deed, and authorize the
Quitclaim Deed to be recorded.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
U),
P,t1.
/J!tf
INITIATING DEPT./DIV.
JSMc
RAB
SIT&
(qf, f>J)
,
-+-
I
"
"
"
I ,
"--~--tt--~-
I '
I
-- -- - -- - - + - -- .- --- --
I
I f
1/
,
QUITCLAIM SEWER EASEMENT
JOB 4065 - SUB 6292
SANDERS RANCH - MORAGA AREA
l\t
BOARD OF DIRECTORS
NO. V. CONSENT CALENDAR
5 9/5/85
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
AUGUST 26, 1985
SUBJECT TYPE OF ACTION
ACCEPT THE CONTRACT FOR CONSTRUCTION OF PROJECT 3386,
REROOF 1250 SPRINGBROOK ROAD, AND AUTHORIZE THE FILING OF THE CCEPT CONTRACT WORK
NOTICE OF COMPLETION
SUBMITTED BY
INITIATING DEPT./DIV.
MUNAWAR HUSAIN, ASSOCIATE ENGINEER
ENGINEERING DEPARTMENT/CONSTRUCTION DIV.
ISSUE: Work has been completed on the 1250 Springbrook Road Reroof Project and the
contract is now ready for acceptance.
BACKGRCllND: The contract included ranoval of existing roofing, heating and air
conditioning equipment, and installation of a new 4-ply roofing system covering
approximately 7,000 square feet. Equi pment pl atforms and duct openi ngs for future
HVAC equipment were also added.
Sparks Roofing Company was issued a Notice to Proceed on October 30, 1984.
Unfavorable weather delayed the start of work until June, 1985. On August 15, 1985
the Contractor compl eted the contract work. Thi s contract work shoul d now be
accepted by the District.
REOOMMENDATION: Accept the Contract for constructi on of proj ect 3386, Reroof 1250
Springbrook Road, and authorize the filing of the Notice of Completion.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
RAB
INITIATING DEPT./DIV.
Jjp.
MH
Qk:
RK
flH
JSM
ltJJ3
Central Contra Costa San
BOARD OF DIRECTORS
NO. VI I. ENGINEERING
1 9 5 85
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
AUGUST 30, 1985
SUBJECT
AUTHORIZE $23,500 FROM THE SEWER CONSTRUCTION FUND FOR
DESIGN AND MATERIALS PREPURCHASE FOR HEADQUARTERS OFFICE
BUILDING MODIFICATIONS, DISTRICT PROJECT 20033
TYPE OF ACTION
AUTHORIZE FUNDS
SUBMITTED BY
DAVE REINDL, ASSISTANT ENGINEER
INITIATING DEPT./DIV.
ENGINEERING DEPARTMENT/ENGINEERING DIVISION
ISSUE: Board of Directors approval is required to authorize sewer construction
fUndS for design and prepurchase of materials for modifications to the
Headquarters Office Building (HOB) to accommodate Planning Division staff.
BACKGROUND: The Planning Division was created as a separate unit of the
Engineering Department in April 1984. Since inception, the staff assigned to the
Planning Division has been located in several different areas on the first and
second floors. The decentralized arrangement has proven to be very inefficient
because it inhibits staff communication and impairs productivity. Supervisors
and thei r employees are located on separate floors, a situation that requi res
excessive travel time to give and receive supervision. A simil ar situation
exists with the Division secretary and project files. As the Planning Division
undertakes future projects and expands existing programs, the problems associated
with the decentralized office arrangement are anticipated to become worse.
The office space requirements for the Pl anni ng Divi si on have been investigated.
Based on the current and near-term future workload, a total area of 2,170 square
feet is needed to accommodate the staff equipment and files. Several office
space layouts were evaluated on the first and second floors of the HOB. The best
office location is in the east half of the first floor of the HOO (Attachment 1).
This area is currently unused and is reserved for future offices. After
consolidation of the Planning Division staff on the first floor, there will be
1,860 square feet of future office space avail abl e on the second floor and 330
square feet on the first fl oor.
Modifications will need to be made to the first floor area to allow use as
offices. The accoustical ceiling and lights were previously installed; however,
carpeting, interior office walls, and electrical and telephone wires were not.
Additional modifications include HVAC ductwork, additional fire sprinklers, a
connecting doorway to the Construction Division offices, and the purchase of
permanent office partitions to repl ace temporary partitions which are currently
being rented for Planning Division staff. The proposed modifications will match
the style of the other office areas of the HOB. The preliminary cost estimate of
the proposed modifications is $50,000, which includes prepurchased materials,
construction, and District staff time for design and construction supervision.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
DR
CWS
JMK
DRW
INITlJ {f('/DIV'
'rJ~
.:JMt:
()~
POSITION PAPER
Page 2
District staff wlll perform preliminary design, final design, and construction
management tasks. An outside contractor wlll construct the proposed
modifications. Staff proposes to prepurchase certain materials with a long
delivery time and modify the HVAC ductwork before award of the construction
contract to expedite the project. Staff requests an authorization of $23,500 for
design, materials prepurchase, and HVAC modifications (Attachment 2). This
authorization request incl udes $5,000 authorized by the General Manager-Chief
Engineer to initiate the project.
RECO~NDATION: Authorize $23 ,500 from the Sewer Construction Fund for design
and materials prepurchase for the HOB modifications.
~
.
-
cffiil
I~
"
---
--
llif ~II
~ II,
_. ul
~.~- ----,
I ...": f J I
! If S i" I
I' i! I
I i ~ I
I , I
I~.'" ~'I
i II ~ ~ 1\! I
C:: - -.- I
______ :J
!; I ~~
.lIli..! i
1-'1
.. .
i -'I
~ &
I I I
~
r....'\
c jrtl.
clHh ~~.
A5H I ~ ~;
I !21 i I = III
~~. ~ I ~ i I
1- II:
~
~
I-
Z
w
2
:E:
()
C
~
C
~
ATTACH~NT 2
AUTHORIZATION REQUEST
HEADQUARTERS OFFICE BUILDING MODIFICATIONS
Preliminary and Final Design
$ 7,260
Materials Prepurchase
Hardware
Doors
Hollow Metal Door & Window Frames
Partitions
Subtotal - Materials Prepurchase
960
1,500
1,780
11 ,000
$15,240
Preconstruction
HVAC Modifications
$ 1,000
Total Authorization Request
$23 ,500
<C<SD
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
NO. VI I. ENGINEERING
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
August 30, 1985
TYPE OF ACTION
SUBJECT
AUTHORIZE $80,000 FROM SEWER CONSTRUCTION FUND
FOR Et.ERGENCY CREEK BANK AND SEWER RESTORATION AT
#12 EVERGREEN DRIVE, ORINDA, DISTRICT PROJECT NO. 4000
AUTHORIZE
FUNDS
Division
ISSUE: Authorization of District funds is required for the emergency repair and
restoration of the creek bank, sewer, and sewer crossing at #12 Evergreen Drive,
Orinda, prior to the 1985-86 wet weather season.
BACKGROUND: A landsl ide caused by creek erosion during the 1982-83 winter
damaged a District sewer main at #12 Evergreen Drive, Orinda, and threatens to
damage the property owner's house. As a result, a temporary sewer was installed
to maintain sewer service. Additionally, the sewer creek crossing at the same
address has been damaged, resulting in sagging and cracking of the sewer
pipeline. This pipeline could break in a severe storm and discharge raw sewage
into the creek.
At the August 22, 1985, Board meeting, an emergency condition was declared to
exi st at #12 Evergreen Drive, Orinda. To expedite the needed repai rs, the
General Manager-Chief Engineer was authorized to execute an agreement with SAFECO
(the property owner's insurance company) and Robert Wootten (the property owner)
for renovation work at #12 Evergreen Drive, Orinda. The work consists of repair
to the creek bank and sewer crossing, and replacement of the District's temporary
sewer line with a permanent sewer line.
The total project construction cost, which is presented in Attachment 1 to this
position paper, is estimated at $160,000, and includes the construction contract
cost, a construction contingency, and construction management and inspection
costs. Per the executed agreement with the District, SAFECO will contribute
$80,000 to the total cost of the repair project, leaving $80,000 as the
District's portion of the repair costs.
RECOMMENDATION: Authorize the General Manager-Chief Engineer to expend up to
$80,000 from the Sewer Construction Fund for the emergency repair and restoration
of the creek bank, sewer, and sewer crossi ng at #12 Evergreen Drive, Ori nda,
District Project No. 4000.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
J
DRW
RAB
O,&.J
f!f4--n
/1/ r L)
ATTAa-tMENT 1
CONSTRUCTION COST ESTIMATE
EM:RGENCY CREEK BANK AND SEWER
RESTORATION - #12 EVERGREEN DRIVE, ORINDA
CONSTRUCTION CONTRACT
1.
2.
3.
4.
Jobsite Access/Restoration
Repair of Slide
Replacement of Sewer in Slide Repair
Repair of Creek Crossing
Contingency (25%)
Subtotal Construction Contract
CONSTRUCTION ENGINEERING
1. District Surveying
2. District Inspection
3. District CM & CA
4. Woodward-Clyde Inspection
Subtotal Construction Engineering
Total Construction Cost
SAFECO Insurance Contribution
Total District Contribution*
*Does not include design costs, which were
funded under DP 20008 - Storm Damage.
$ 6,000
80,000
6,000
25,600
$117,600
29,400
$147,000
$147,100
$ 2,200
1,400
1,400
$ 5,000
8,000
$ 13 ,000 $ 13 ,000
$160,000
(80,000)
$ 80,000
((S
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
NO. VI I. ENGINEERING
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
DATE
August 28, 1985
SUBJECT
AUTHORIZE $25,500 FROM SEWER CONSTRUCTION FUNDS FOR RENOVA-
TION AND TESTING OF THE EXISTING M-2 FORCE MAIN CORROSION
PROTECTION SYSTEM TEST STATIONS, DISTRICT PROJECT NO. 4015
TYPE OF ACTION
AUTHORIZE FUNDS
SUBMITTED BY
James L. Hill, Associate Engineer
ISSUE: Funds are requested for the renovation of the existing M-2 force main
corrosion protection system testing stations, and to conduct a testing program
which will provide data needed to develop criteria for design of a new corrosion
protection system.
BACKGROUND: The M-2 force mai n consi sts of approximately 4,000 li near feet of
20-inch steel pipe installed in 1969. It is the only sewer available to handle
sewage flows from the Martinez area and therefore, must be kept operational. At
the time of construction an impressed current system was installed to protect the
line from corrosion. Attachment 1 to the position paper is a map of the M-2 force
main.
Due to the age of the original corrosion protection system for the M-2 and an
upstream force mai n (M-6), there was concern regardi ng the ability of the 01 d
corrosion protection system to adequately protect the M-2 and M-6 force mains. As
a result of this concern, a corrosion engineer was retained to study the existing
corrosion protection system. The study recommended that the old corrosion
protection systems be replaced. The M-6 corrosion protection system has been
replaced. During the predesign phase for the M-2 force main it was found that
several of the electrolysis test stations (ETS's) located in the Industrial Tank
(IT) holding basins were inaccessible. This prevented collection of test data
needed to develop design criteria, and thus precluded completion of the predesign
on the M-2 force main.
In October of 1984, Jose Villalobos & Associates was retained to prepare a plan
for renovating the ETS System, thereby allowing test data to be collected. The
work included preparation of a test station design that would allow all weather
access to all ETS's, as well as to evaluate the ETS's to assure that all testing
stations were appropriately located along the M-2 force main. The plan was
comp 1 eted and recommendati ons for renovati ng the ETS' s were made. The proposed
renovation will consist of:
1. Relocation of 5 existing test stations to allow all weather access.
2. Installation of 2 new test stations.
3. Installation of 7 new reference cells for the above mentioned test
stations.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
DRW
RAB
INITIATING DEPT./DIV.
D?tJ
1Jt~
The renovation of the corrosion protection testing system will be performed by the
Collection System Operations Department (CSOD) in coordination with the
Engineering Division. Once the test station renovation has been completed, a
testing program will be conducted to gather data needed to develop design criteria
for the new corrosion protection system. The estimated cost both to renovate the
ETS's and test the M-2 force main corrosion protection system is $25,500. Once
the design criteria are developed, an additional request for funds to design and
install the new corrosion protection system will be made.
The total cost of the project including the renovation of the ETS System,
conducting the testing program, designing the new corrosion protection system and
construction of the new corrosion protection system is estimated to be between
$85,500 and $115,500. The replacement cost for the M-2 force main is estimated at
approximately $450,000. It is therefore cost effective to expend funds now to
protect the existing M-2 force main from corrosion, thereby avoiding the potential
greater cost and service inconvenience of having to subsequently replace the line
due to failure. This work is part of the 5-year Capital Improvement plan.
RECOMMENDATION: Authorize $25,500 from the Sewer Construction Fund for renovation
and testing of the existing M-2 force main corrosion protection system test
stations, District Project No. 4015.
ItEV'PED ~ND RECOMMENDED 1'0. .O~.D ~CT'ON
INITIATING DEPT./DIV.
GEN. MGR.lCHIEF ENG.
ACME
FILL CORP
58.25AC'
GOTTSCHALK
5&.25AC
LION OIL CO
334.815 AC.
o
17'/1 PIPE PROTECTION
X2032 I S II
X2UIl DRAINAGE
ATTACHMENT 1
ELECTROLYSIS TEST STATION
GENERAL PLAN - LINE M-2
LEGEND:
A" - Existing
G - New
(!) - Reconstructed
SCALE IN FEET
i
300 0 300 600 100
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
POSITION PAPER
VIA: ROGER J. DOLAN
General Manager-Chief Engineer
SUBJECT
ADOPT A RESOLUTION TO REVISE THE LIST OF EMPLOYEES
AUTHORIZED TO HAVE ACCESS TO THE DISTRICT'S SAFE
DEPOSIT BOX
DATE
August 28, 1985
TYPE OF ACTION
ADOPT
RESOLUTION
SUBMITTED BY INITIATING DEPT./DIV.
Walter Funasaki, Finance Officer Administrative/Finance & Accountin
_____= u or za on to a 0 ette S. Mil er, Accounting Technician, and delete
Steven A. Elsberry, Accounting Supervisor, from the list of employees having
access to the District's safe deposit box is requested.
BACKGROUND: The District maintains a safe deposit box at the Wells Fargo Bank in
Pleasant Hill to safeguard developer bonds which are in the form of certificates
of deposits. A desi gnated Accounti ng staff member is given responsi bllity to
deposit and withdraw such bonds, and to maintain records and receipts which serve
as an inventory of the contents of the safe deposit box.
Employees currently authorized to have access to the safe deposit box are:
Joyce E. McMillan, Secretary of the District
Walter N. Funasaki, Finance Officer
Steven A. Elsberry, Accounting Supervisor
Deborah D. Barone, Accountant
Deborah D. Barone is the staff member presently assigned custodial responsibility
for the safe deposit box. She was recently promoted to the position of
Accountant, and has assumed new responsibilities. It is considered desirable to
assign C. Miller the custodial responsibilities, and to have D. Barone provide
coverage in C. Miller's absence.
A previous request to authorize C. Miller access to the safe deposit box was
deferred by the Board of Di rectors to requi re compl eti on of her probati onary
period; the Board also expressed a degree of concern regarding expanding the list
to five employees. C. M1l1er has achieved permanent status, and the number of
employees will be retained at four by deleting the Accounting Supervisor.
A resolution to authorize Colette S. Miller access to the District's safe deposit
box and to remove Steven A. Elsberry from the list of employees having such access
is attached; the resulting list of employees will be as follows:
Joyce E. McMillan, Secretary of the District
Walter N. Funasaki, Finance Officer
Deborah D. Barone, Accountant
Colette S. Miller, Accounting Technician
RECOMMENDATION: Adopt the attached resolution to add Colette S. Miller to, and to
de 1 ete Steven A. El sberry from, the li st of employees authori zed access to the
District's safe deposit box.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
~
INITIATING DEPT./DIV.
~ c. -<..I
WNF
RESOlUTION NO. 85-
A RESOLUTION RESCINDING RESOLUTION NO. 83-165 AND AUTHORIZING
THE SECRETARY OF THE DISTRICT. FINANCE OFFICER.
ACCOUNTANT. AND ACCOUNTING TECHNICIAN AS SIGNATORIES
AND KEYHOLDERS FOR THE DISTRICT SAFE DEPOSIT BOX
BE IT RESOLVED by the Board of Directors of the Central Contra
Costa Sanitary District. a public corporation <hereinafter referred to as
Corporation). as follows:
THAT. th i s Corporati on has entered into a Rental Agreement _< and
renewals thereof) for a Safe Deposit Box in the vaults of Wells Fargo Bank
(hereinafter called Bank); and
THAT. anyone of the fo 11 ow i ng offi cers and employees of th i s
Corporation shall have the right of access to and control of the contents
thereof. and to surrender the said Box. releasing Bank from all liability
with respect thereto:
JOYCE E. McMILLAN. SECRETARY OF THE DISTRICT
WAL TER N. FUNASAKI. FINANCE OFFICER
DEBORAH D. BARONE. ACCOUNTANT
COLETTE S. MILLER, ACCOUNTING TECHNICIAN
BE IT FURTHER RESOLVED, that the certification of the Secretary
of this Corporation as to election or appointment of authorized officers
or employees shall be binding upon this Corporation, and the authority
hereby conferred shall remain in force until written notice of the
revocation or modification thereof shall be delivered to an officer of
Bank at the office at which said Safe Deposit Box is located.
PASSED AND ADOPTED this 5th day of September, 1985. by the
following vote:
AYES: Members:
NOES: Members:
ABSENT: Members:
President of the District Board of
the Central Contra Costa Sanitary
District. County of Contra Costa,
State of California
COUNTERSIGNED:
Secretary of the Central Contra Costa
Sanitary District, County of Contra
Costa. State of California
Approved as to Form:
Jam~s L. Hazard
District Counsel
--------------------------'--