HomeMy WebLinkAboutAGENDA BACKUP 11-04-92
~ Centra~ ~g~~~ g~~~R~~~~a~~ Jistrict
POSITION PAPER
BOARD MEETING OF
PAGE 1 OF 2
SUBJECT
NO.
3. CONSENT CALENDAR a.
DATE October 26, 1992
AUTHORIZATION FOR P.A. 92-9 (ALAMO)
TO BE INCLUDED IN A FUTURE FORMAL ANNEXATION TO
THE DISTRICT
TYPE OF ~PT
ANNEXATION
FOR PROCESSING
SUBMITTED BY
INITIATING DEPT./DIV.
Dennis Hall, Associate Engineer
Engineering Dept./lnfrastructure Division
Parcel Area Owner/Address Remarks Lead
No. Parcel No. & Acreage Agency
92-96 Alamo Joe Henley, etux Existing house with a CCCSD
7702 1475 Vine Lane failing septic
Alamo, CA 94507 system;must connect to
( 187-130-009) the public sewer system.
0.83Ac. Project is exempt from
CEOA.
RECOMMENDATION: Authorize P.A. 92-9 to be included in a future formal annexation.
~
~
yJffJ
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INITIATING DEPT./DIV.
1302A-9/85
DH
JSM
RAB
~
\
o
/.
~\,~~~~
PROPOSED ANNEXATION
P .A. 92-9
~ Central ~g~~~ g~~~R~~~ba~~ Jistrict
PAGE 1 OF 2
POSITION PAPER BOARD MEETI1<IcWember 4, 1992
SUBJACCCEPT THE CONTRACT WORK FOR THE SEWER
REHABILITATION PROJECT AT SOARES LANE,
SOUTH TRAIL, AND DALEWOOD DRIVE IN LAFA VETTE
AND ORINDA (DP 4294) AND AUTHORIZE THE FILING
OF THE NOTICE OF COMPLETION
NO.
3. CONSENT CALENDAR b.
D"t)'ttober 26, 1992
TYPE OF ACTION
ACCEPT CONTRACT
WORK
SUBMITTED BY
Tom Trice, Engineering Assistant
INITIATING DEPT./DIV.
Engineering Department/
ISSUE: Construction has been completed on the Sewer Rehabilitation Project at Soares Lane,
South Trail, and Dalewood Drive in Lafayette and Orinda (DP 4294), and the work is now ready
for acceptance.
BACKGROUND: During the winter of 1982-83, the sewers on Soares Lane in Lafayette and South
Trail and Dalewood Drive in Orinda were damaged. The general locations of these project sites
are shown in Attachment 1. The Sewer Rehabilitation Project at Soares Lane consisted of
relocating approximately 500 feet of 8-inch sewer pipe and adding three new manholes. At South
Trail a new 105-foot pipe truss system was installed replacing the damaged creek crossing.
Additional work at these two sites included installing concrete riprap to protect the existing creek
banks. At Dalewood Drive a new pipe support was installed. This project is described in more
detail on Page CS-41 of the 1992-93 Capital Improvement Budget.
On March 19, 1992, the Board authorized the award of a contract for construction of the project
to D.E. Bianchini, Inc., of San Ramon. A Notice to Proceed was issued on May 6, 1992, with a
specified completion date of September 8, 1992. This completion date was extended to
October 9, 1992, by change orders. The contract work was substantially completed on
September 30, 1992, and the new sewers were under full operation as of that date. The
remaining work consists of minor punch list items which do not affect the project acceptance.
The total authorized budget for the project, including the cost of engineering design, consultant
services, District forces, testing services, etc. is $464,823. A detailed accounting of the project
costs will be provided to the Board at the time of project close out. It is appropriate to accept the
contract work at this time.
RECOMMENDATION: Accept the contract work for the construction of the Sewer Rehabilitation
Project at Soares Lane, South Trail, and Dalewood Drive in Lafayette and Orinda (DP 4294) and
authorize the filing of the Notice of Completion.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INITIATING DEPT./DIV. tr (}fjfJ
---r71T '11
1302A-9/85
TT HT JSM RAB
:~:~::~!!!!!!~:;:::.: .::: ;.. :::ill!!! ~::::~
Orinda
Alamo
6)
t::::::::::::::::::::::::::~:~:::::t: p rOJ" ect Locat ion (s)
..:~: :::::::;:~:~ :~:~:~:~::.:::: ::::.:.,
1 Dalewood
2 Soares Lane
3 South Trail
Central Contra Costa
Sanitary District
District Project No. 4294
Sewer Rehabilitation Project
Area Map
Attachment
1
PAGE 1 OF 2
BOARD MEETING OF
November 4, 1992
NO.
3. CONSENT CALENDAR c.
SUBJECT
DATE
October 30, 1992
ADVISE THE BOARD OF THE CLOSE OUT OF THE
MT. DIABLO SIPHON SLlPLlNING PROJECT,
WALNUT CREEK (DP 4535B)
TYPE OF ACTION
INFORMATIONAL
Ronald Klimczak, Senior En ineer
INITIATING DEPT.IDIV.
Engineering Department/
Plant Engineering Division
SUBMITTED BY
ISSUE: All work has been completed on the Mt. Diablo Siphon Sliplining Project (DP 4535B) in
Walnut Creek, and this project can now be closed out.
BACKGROUND: This project was designed to permit year-round operation of the recently
completed Walnut Creek Downtown Bypass Interceptor (Bypass), rather than operate solely
during periods of high flow. To implement this operational change, it was necessary to reduce
the size of one of the two existing 42-inch siphon barrels at Mt. Diablo Boulevard, thereby
creating an adequate cleansing velocity during periods of low flow. The work accomplished
under this project involved installing approximately 400 linear feet of 24-inch diameter liner pipe
in the east barrel of the siphon at Mt. Diablo Boulevard. The project location is shown on
Attachment 1.
The Board of Directors awarded a construction contract to D'Arcy & Harty Construction, Inc. of
San Francisco on February 6, 1992. The contractor commenced work on March 16, 1992. The
specified contract completion date was July 13, 1992. However, due to the diligent efforts of
the contractor and the timely delivery of the liner pipe, the work was completed on April 18,
1992, approximately two and one half months early. The Board of Directors accepted the
project on May 7, 1992.
D'Arcy & Harty's original construction contract was for $58,400. There was one change order
issued for $200. The total contract amount paid to D'Arcy and Harty was $58,600.
The total authorized budget for the project was $152,000. The total completed project cost is
$129,500. Staff is closing out the project account, which will result in $22,500 being returned
to the Collection System Program Contingency Account.
RECOMMENDATION: This item is presented to the Board of Directors for information only. No
action is necessary.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
RSK
WEB
RAB
INITIATING DEPT.lDIV.
1?;i-
WL{)
jJ1Jfb
1302A-7/91
APARTMEHT
COMPLEX
~
.
~z-
PLAN
.ProJect Location(s)
Central Contra Costa
Sanitary DiStricf
MT. DIABLO SIPHON SLIPUNING PROJECT
DP 45358
Vicinity Map and Site Plan
Attachment
1
~"W. _.....,~'........."_,,.. ._."_,,_..~~ ~,_,"_'._.__. _..__..._~....._._.~"",,_, .,h.->..._'"''__''''' _.~
~ Centra~ ~ontra Costa Sanitary .Jistrict
~d~"1k BOARD OF DIRECTORS
PAGE 1 OF 1
POSITION
PAPER
BOARD MEETING OF
November 4, 1992
NO.
3.
CONSENT CALENDAR d.
October 9, 1992
SUBJECT
DATE
AUTHORIZE THE ATTENDANCE OF HENRY THOM, SENIOR
ENGINEER, AT THE JANUARY 19-20, 1993 ASCE TRENCHLESS
TECHNOLOGY SEMINAR IN FOSTER CITY, CALIFORNIA,
AT A COST OF $790
TYPE OF ACTION
AUTHORIZE
ATTENDANCE
INITIATING DEPT./DIV
Engineering Department
r
ISSUE: Approval by the Board of Directors is required for attendance of an unbudgeted
seminar if the expense will exceed $500.
BACKGROUND: The American Society of Civil Engineers is offering a seminar entitled
"Trenchless Technology" on January 19 and 20, 1993, in Foster City, California. This
seminar presents technology currently being used in trenchless pipeline construction work. .
Henry Thom, Senior Engineer, is responsible for the construction activities in the Infrastructure
Division of the Engineering Department. Attendance at this seminar will expose him to the
latest engineering and construction advances in this new field and will increase his general
knowledge in this area. Funds are available in the Infrastructure Division Training and
Conference budget by deferring other budgeted training.
RECOMMENDATION: Authorize the attendance of Henry Thom, Senior Engineer for the
Infrastructure Division, at the January 19 - 20, 1993 ASCE Seminar in Foster City, California
at a cost of $790.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
WJj
1302A-9/85
JSM
RAB
~ Central ~~~~~ g~~~R~~~::~~ .Jistrict
PAGE 1 OF 6
POSITION PAPER BOARD MEETING OF November 4, 1992
NO.
5. BIDS AND AWARDS a.
DATE
October 26, 1992
SUBJECT
AUTHORIZE AWARD OF CONTRACT FOR THE HAP MAGEE PARK
SEWER REPLACEMENT IN DANVILLE, DISTRICT PROJECT
NO. 4921 TO D.R. LEMINGS CONSTRUCTION COMPANY
TYPE OF ACTION
AUTHORIZE AWARD
SUBMITTED BY
INITIATING DEPT.lDIV.
Engineering Department/
ISSUE: On October 23, 1992, bids for the Hap Magee Park Sewer Replacement Project, District
Project No. 4921, were received and opened. The Board of Directors must authorize award of
the contract or reject bids within 50 days of the opening of the bids.
BACKGROUND: The District has an 8-inch existing public sewer running through the Town of
Danville's proposed Hap Magee Park. A portion of this sewer including a manhole has settled
approximately three feet, causing a continuous maintenance problem. The remaining segment
of line is very flat, which reduces the natural cleansing of the sewer pipe. In order to raise the
depressed section of pipe and manhole, and increase the slope of the flat section, approximately
735 feet of 8-inch sewer will have to be replaced. Exhibit A shows the project's location.
The Town of Danville is planning to improve Hap Magee Park. The park improvement project
has been bid and construction is expected to start in the first week of November of this year.
The specifications for the park improvement project provide sufficient time for the sewer work
installation, after the initial grading work is completed and before any other park improvements
are started, so that potential construction conflicts and damage to new park improvements by
the sewer work will be avoided.
Plans and specifications for the project were prepared by the District's Infrastructure Division.
The project was advertised on October 11 and 18, 1992. The engineer's pre-bid estimate for
the construction contract was $105,000. Six bids ranging from, $86,785 to $116,140 were
received on October 23, 1992. A summary of bids is presented on Exhibit B.
The Infrastructure Division conducted a technical and commercial review of the bids and
concluded that the lowest responsible bidder is D.R. Lemings Construction Company, for the
amount of $86,785.
A Post-Bid Preconstruction Cost Estimate, based on the bid of $86,785, is presented in Exhibit
C. The total estimated project cost is $143,946. Funds previously authorized were $24,000.
An additional allocation of $119,946 is required from the Collection System Program
Contingency Fund to complete the project, including the construction contract, construction
management and consultant services during construction. The project funding summary is
shown in Exhibit D.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
;1)1/
;wP
INITIATING DEPT.lDIV.
1302A-9/85
DH
JSM
RAB
SUBJECT
POSITION PAPER
AUTHORIZE AWARD OF CONTRACT FOR THE HAP MAGEE PARr
SEWER REPLACEMENT IN DANVILLE, DISTRICT PROJECT PAGE
NO. 4921 TO D.R. LEMINGS CONSTRUCTION COMPANY DATE
2
OF
6
AUTHORIZE AWARD
Staff has determined that this project is exempt from the California Environmental Quality Act
(CEQA) under District CEOA Guidelines Section 18.3, since it involves the replacement of an
existing sewer facility with negligible or no expansion of capacity. The Board of Director's
approval of this project will constitute a finding of agreement with this determination unless
otherwise indicated.
RECOMMENDATION: Authorize award of contract in the amount of $86,785 to D.R. Lemings
Construction Company as the lowest responsible bidder.
13078 9,8"
PROJECT LOCATION
..
Central Contra Costa
Sanitary District
.
HAP MAGEE PARK
EXHIBIT
SEWER REPLACEMENT
"A"
2523-1/87
EXHIBIT B
Central Contra Costa Sanitary District
SUMMARY OF BIDS
PROJECT NO. 4921 - HAP MAGEE SEWER REPLACEMENT DATE OCTOBER 23, 1992
LOCATION Danville
ENGR. EST. $ 105,000
Order BIDDER (Name, telephone & address) BID PRICE
1 D.R. Lemings (510) 686-1300 $86,785
1717 Solano Way, Concord, CA 94520
2 Mountain Cascade, Inc. (510) 736-8370 $105,765
P.O. Box 116, San Ramon, CA 94583
3 Manuel C. Jardim, Inc. (510) 487-0444 $109,977
P.O. Box 677, Union City, CA 94587
4 Ranger Pipelines, Inc. (415) 822-3700 $110,150
1296 Armstrong Ave., San Francisco, CA 94124
5 Silva's Pipeline, Inc. (510) 786-2722 $115,295
P.O. Box 751, Hawyard, CA 94543
6 MJB Pipeline (510) 785-5805 $ 1 1 6, 140
P.O. Box 192, Mt. Eden, CA 94557
BIDS OPENED BY Jovce E. Murohv
DATE October 23, 1992 SHEET NO.1 OF 1
EXHIBIT C
HAP MAGEE SEWER REPLACEMENT PROJECT
DISTRICT PROJECT NO. 4921
POST -BID/PRECONSTRUCTION ESTIMATE
ITEM DESCRIPTION TOTAL PERCENT OF
ESTIMATED
CONSTRUCTION
COST
1 . Construction Contract $ 86,785
2 . Contingency @ 15 % 13,018
SUBTOTAL $ 99,803 100.0
3 Construction Management
. Project Management 5,500
I Administration
. Inspection 7,500
. Survey 2,000
. Legal 500
. Field Office Support 300
. Engineering Assistance 2,500
SUBTOTAL $ 18,300 18.3
4 Consultant Contractors
. Geotechnical (OCM Joyal) $ 4,000
. Resident Engineer (JMM) 3,000
SUBTOTAL $ 7,000 7.0
5 Miscellaneous
. Record Drawings $ 500
SUBTOTAL $ 500 0.5
6 Total Allocation of Funds to $ 125,603 126.0
Complete Project
7 Preconstruction Expenditures 18,343 18.4
8 TOTAL PROJECT COST $ 143,946
EXHIBIT 0
PROJECT FUNDING SUMMARY
FOR THE PERIOD 10/7/92 - 11/9/92
Sewer Construction Fund Balance as of
September 30, 1992
$ 66,373,871
Minus Unspent Prior Allocations
$ < 38,639,317 >
Plus Dependable Revenue
$ 22.403,000
$ 50,137,554
$50,137,554 > $119,946 (Allocation Required)
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
PAGE 1
OF 6
BOARD MEETING OF
November 4, 1992
NO.
6. ADMINISTRATIVE a.
SUBJECT DATE
RECEIVE THE 1991-1 992 ANNUAL REPORT OF THE DEFERRED October 26 1992
COMPENSATION PLAN ADVISORY COMMITTEE TYPE OF ACTION
RECEIVE ANNUAL
REPORT
SUBMITTED BY
Walter N. Funasaki, Finance Officer
INITIATING DEPT./DIV.
Administrative/Finance and Accounting
ISSUE: The Deferred Compensation Plan Advisory Committee (Committee) respectfully
submits its 1991-1992 annual report to the Board of Directors and Plan participants.
BACKGROUND: The Board of Directors approved the establishment of the Committee in
January 1982. The scope of activities of the Committee includes submission of an annual
report to the Board of Directors and Plan participants. The annual report of the
Committee for 1991-1992 is submitted herewith.
RECOMMENDATION: Receive the annual report of the Deferred Compensation Plan
Advisory Committee for 1991-1992.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
1302A-7/91
W.F.
P.M.
fR/HIEF ENG.
V~
ROGER J. DOLAN
Papers #2/AnnRpt.PP
Central Contra Costa Sanitary District
DEFERRED COMPENSATION PLAN ADVISORY COMMITTEE ANNUAL REPORT
JULY 1991 -JUNE 1992
The Deferred Compensation Plan Advisory Committee (the Committee) was established
by the Board of Directors to facilitate the internal administration of the District's Deferred
Compensation Plan. The scope of the Committee's activities encompass the following:
. Establish internal District administrative procedures within the provisions of the
Deferred Compensation Plan document.
. Educate participants regarding the Plan provisions by issuing a handbook which
summarizes the Deferred Compensation Plan, and responding to questions from
participants.
. Review accountability by the Program Administrators, Hartford Life Insurance
Company (Hartford) and Great Western Bank (Great Western), and respond to
participants' queries regarding accuracy or propriety of account balances.
. Review participants' requests for emergency withdrawal of funds.
. Review investment performance of the Deferred Compensation Plan on an annual
basis.
Committee Accomplishments
The following activities were completed by the Committee during July 1991 through June
1992.
. Internal District Administrative Procedures
As required by new federal regulations, a separate Deferred Compensation Plan
program for part-time, student, and temporary employees was approved by the
Board of Directors for implementation effective July 1991. Contributions to
participants' accounts in this program are made by payroll withholdings. The
program is administered by Great Western Bank.
The Committee sent federal lawmakers a letter urging passage of HR2906 which
would raise the $ 7,500 contribution limit of Section 457 Deferred Compensation
Plans.
. Education of Particioants
An updated Deferred Compensation Plan handbook data sheet was reprinted and
distributed to Plan participants in September 1991.
Representatives of Hartford and Great Western have been available on-site on a
designated day each month to assist participants by providing information and
responding to questions.
A representative of Great Western held District-wide meetings on June 17 and 18,
1992 to inform participants of the provisions of the new renewal contract which
was implemented July 1, 1992. The features of the existing Hartford contract
were reviewed by a Hartford representative at the same meetings.
. Review of Great Western Renewal Contract
The three-year term of the Great Western contract had an expiration date of April
30, 1992. The Committee met with Great Western representatives in the course
of reviewing the terms of the renewal contract and obtained an extension of the
existing contract to June 30, 1992. A new, open-ended contract was negotiated
beginning July 1, 1992. The provisions of this contract were less favorable than
the previous contract, particularly in the area of savings account rates and options,
but provides a significantly expanded selection of stock and bond mutual funds.
. Review Accountabilitv bv Program Administrators
Monthly confirmation statements and quarterly account statements are submitted
to the District by Hartford and Great Western. Quarterly account statements are
distributed to all participants. Notification by the District of account errors has
been satisfactorily resolved by Hartford. Great Western experienced problems in
processing the large volume of transactions during July and August 1992,
following implementation of the new renewal contract; these problems have been
satisfactorily addressed after being reported by the District.
. Review Requests for Emergency Withdrawals of Funds
Seven emergency withdrawal requests were reviewed by the Committee, and five
were recommended for approval by the Board of Directors.
. Review Investment Performance
A summary which presents the investment performance of the Hartford and Great
Western programs for the calendar year 1991, and the first six months of 1992,
is provided on Attachment I.
Current Committee Activities
. The District's Deferred Compensation Plan document is undergoing a careful
review by the Committee to ensure conformance with the current governing tax
codes and to improve accuracy and completeness.
. The Committee will review other administration companies to assess the
competitive standing of the District's two administration firms.
. An information sheet is being developed by the Committee for the benefit of
participants separating from the District which will provide information regarding
distribution requirements, payout options, and tax considerations.
Conclusion
During the period July 1991 through June 1992, the Committee addressed all of the
activities included in its scope of responsibilities through the conscientious efforts of all
of the Committee members.
The performance of Hartford and Great Western in administering the Deferred
Compensation Plan during the 1991-1992 report period is considered to be satisfactory.
While Great Western has experienced a significant increase in the number of processing
errors due to the large volume of transactions following implementation of the new
renewal contract, reported errors have been satisfactorily resolved.
The performance results of the Hartford and Great Western stock and bond investments
for the calendar year 1991 and the first six months of 1992, as shown on Attachment I,
are as follows:
Hartford
The gain on the stock and bond accounts for the 1991 calendar year of 24.6
percent and 16.4 percent, respectively, exceeded the general market indices, as
measured by the Dow Jones Industrials and the Shearson Lehman Bond Index,
which registered gains of 24.2 percent and 16.1 percent, respectively; the stock
account underperformed the Standard & Poors 500 which gained 30.4 percent.
Through the first six months ended June 30, 1992, the .7 percent loss on the
stock account underperformed the Dow Jones Industrials which gained 6.3
percent, and was equal to the loss registered by the Standard & Poors 500; the
gain of 2.1 percent on the bond account underperformed the Shearson Lehman
Bond Index, which gained 2.5 percent.
Great Western
For the 1991 calendar year, the gain on the three stock accounts (Investment
Company of America, 26.5 percent; Growth Fund of America, 35.8 percent; and
Fidelity Retirement Growth Fund, 44.8 percent) exceeded the Dow Jones
Industrials and Standard & Poors indices; the Bond Fund of America gained 21.0
percent, which exceeded the Shearson Lehman Bond Index.
Through the first six months ended June 30, 1992, the Investment Company of
America loss of .2 percent outperformed the Standard & Poors 500 and
underperformed the Dow Jones Industrials; the Growth Fund of America loss of
4.3 percent underperformed both market indices; the Fidelity Retirement Growth
Fund loss of 2.2 percent underperformed both market indices; and the Bond Fund
of America gain of 5.1 percent exceeded the 2.5 percent gain registered by the
Shearson Lehman Bond Index.
Committee Members:
~ -
, /"/
(Z~~~ /
Walter N. Funasaki, Finance Officer
)~~vf~~
Nadine Schumacker, Secretary III
Administrative Department
()~ ~ rJ~
David R. Williams, Planning Division Manager
Engineering Department
~~
Tom Godsey, Assistant Engineer
Collection System Operations Department
P S4 L---
Phil Snyder, Senior Chemist
Plant Operations Department
C:WP51 \DefComp\9192 Anul.Rpt
...
~
I
...
.,.
tJ~
ti~
E~=
w"'~
"'e-a
a..
><fi!a
1I:e-:i
Cw
e-!!'w
"'i=
~...~
:!ii
e-:J~
w",...
S.w
~oa
e-~~
C
.8~O:
..,.
a~=
.a~
l:lS=
~lil
101101
aa
.
.c
....
"
o
...
^
.
.
S
v
C
004.
c1'g
~1:
ft:
l8
004
I~
~i
='
.
.I
.
i
o
...
"
l
.
0:;: ~~
o~o~:
004s......C
~Ie ~....
11:101 .
.
>0
........ .
OI"CU
..='C
"....0.
."U...
..U.
C &C lD
C
00.,.
~:: G\ .,;
8,8 \0 ...
,,004
ft :b
C .
. 004
... a
.
lD
....
C
g
U
~
= I! ] M
= C =!
III III
"
.
:.
"
.
1
...
~
=
"
~
.
-=8 "
1:'" .a
. .....
3 ." =
! ~ !~ 3
.... I .
J to Ul g
" = ~-3 ·
~ ; J~ j
N
t"" 0: ~
EI ~ ~
~~
"
110
....;:;
c- ... N
I.; ~ ~
..5 ~ i
= e VI'" '"
....
..
... ~
'" .
\0 ...
..; ~
~ CD
~ ~
,
. ...
WI
1ft ...
.... ... N
C 1ft 1ft
='
j
,
N .,.
N CD
o CD
.,; .;
VI
"
"
o
...
....
"
.
=
~ ~"': ..
1ft .0 \0
N'" ...
.
o
\0
.. Q r:
~ ~ :
1 E
: ~
I"
WI ...
.
.
\0
...
~ ; E
~ E :
WI ...
.
\0
\0
~ 1
~ ~
.
.,
'g
.g
...
...
004
lD
I
to
>0
.
a
o
.,.
.
~ 8
004 1ft
"
.... .
f J
..
.
! 1l
~ -3
J ~
'"
.
1ft
N .
. .
. 0
N '"
--
~
~
1ft CD CD 0
.
\0 1ft . ...
... '" . N
\0 ...
o .
o .
... .,.
... '"
. . . .
.,. '" '" ~
1ft CD CD ~
I ; ~
.;. =
Ii
VI
.,.
1ft
CD
,
N
~
~
,
\0
...
~ E : ~ ~
5 E ~ ~ ~
I"
..
~ ~ ~ N ~
01 ... S
...
...
'"
,
'"
'"
o
,
~
.
go
004
=
III
..
~ :: i
'i' ~ r:- ~
M M M I
g g g 'g
~ ~ ~ .g
....C
."
..
"'....
0.
r
=
'g
...
'g
.g
C
J
3
C
o
.
"
.
.!
III
...
.
\0
...
.,. 1ft
... .
~ ...
,
Q \0
... '"
... .,.
,
~ ...
o
'" ~
. C M
! i !
'Ill III
I
.
~ II
i ~
....
II "
004 .
III =
.
-=8 'g
0041ft 0
" lD
.....
.'" =
:: i~ .!
iiI ..... 3
I .
to !1l g
~ ~-3 C
a C.
o !~ .!
.,. alii lD
^
III "'~ 1ft
..; ~. N
V
-
^
\0 ~
..;
^
o .,.
1ft ~
~ 1ft
o N
.,. N
...
. \0
.
01 1ft
\0 N
. ~
.. CD
CD ...
,
\0 ..
o 1ft
'" .,.
.n ..;
v
v
.
.,.
...
Ie
~
C
...
.
... 0
~ ~
'"
.... .
:: t J
004 ...
lD ..
I .
e- ! 1l
= ~ ~
Q :a ~
00....
01 Q lD
^
CD '" ~
.
... \0
v
---
...
..;
^ ^ ^
N N '" N ...
v
~ N ~
V V
~ : $
\G ~ \0
p ~
VI VI
.
N
'"
~ ~
~ ;..
~ ~ ~ a :
~ ~
..;
5 ~ 5 ~ ~
'" c '" . !:
... 1ft ~
WI
. . . .
o ... N .,.
'" . . '"
t,Q ... .. rot .. \D
~ ~ ~ : 0 ~
:;; ~
C C 1ft ~ CD ~
It ~ ;: \0 .,.
~ ~ ~ ; ~
, : ~ ~ ~
,.;: ~
VI VI
J
..
~ ~ E ::
~ I I I lD
C M M M I
~g88'g
: ~ ~ ~ .g
C
"
.
....
.
r
....
.
.
"
o
:;l ! ~
0: ~ ill
~ ~ ~
. 0
CII
..
,. c
.. 2
~
=
'g
...
.
.
....
.
.
= i ~ ~ s
..; .,. \0 ,,; ..
= :!! . 0. ~
a:
VI N WI
01
..
...
c:
J
.!
.
01
C
004
C
'"
.
.
....
.... U
1; .:l
"0 .......
004 U C.
.... U :I
:. 8.!
"11 ~....
~.B "....
.::" .Bc g
U c: ~
C. ,,004
004M c::a
.u ..
~B M:I
='. u....
8 c: .B:
u" .
.. ....
.... ca
". ".
Ca'. .
.B:S~~.
,,~ U~
C. C
.".....
MO~:...
ual"o
.B~....03.
· "n.
ll~=.~
~Coo4llft
....1 co s.'"
",ll 0'"
.. ....
=::~.
aCo=
.c004.... .
.... a.
C".c
~00""1
"':.5~""
eo.....~
6.... 01 :I
.c"1~~
· o..~.
. Coo4. u
:r-;.: e e
004 OIa :I
e" '" ft....
.aace
.""e
004='
............ ';l
C U.2....
1"'004" 0 .
t:; s.....~
:"!a!~
cc.c.c.c.c
.....e-.u
>0
c:
.
"
C
.g
...
o
C
o
.
"
.
.!
lD
1ft
..;
CD
CD
~
:;
-
... ...
.
.
....
g
....
8
..
"
C
. ,
U
004 .c
i. !
a.;! '"
2'... ~c:I
030004.....
",c:u
~~JI1:
='. J
8t...~
u80....
C ,,:0:;
>0.... C
....C:I>O"
0041......c
&.....c::,
...!.
. ""
C. 004 C
~.9~".il
.... I
. I I I
. ..
:a~::i::
~"'O"lD
.
'"
o
~
t
~
I
~
~
~ Centra. ~g~~~ g~~~R~~~~a~~ Jistrict
PAGE 1
3
OF
POSITION
PAPER
BOARD MEETING OF
November 4, 1992 NO.
7. ENGINEERING a.
DATEOctober 30, 1992
SUBJECT
COMMENT ON PROPOSED ANNEXATION OF 675 ACRES
IN THE SAN RAMON AREA, KNOWN AS NORRIS
CANYON BOUNDARY REORGANIZATION
TYPE OF ACTION
PROVIDE COMMENTS
ON PROPOSED
ANNEXATION.
SUBMITTED BY
Dennis Hall, Associate Engineer
INITtA TING DEPT./DIV.
Engineering Department/
Infr r ivi .
ISSUE: Developers have requested that the District Board comment on a proposed boundary
reorganization prior to the processing of the reorganization by the Local Agency Formation
Commission (LAFC).
BACKGROUND: On March 19, 1991, acting upon a request by several property owners, the
County Board of Supervisors adopted a Resolution of Application to the LAFC for a
Reorganization and Amendment of Spheres of Influence, Norris Canyon Area. The proposal
includes 675 acres of land which are owned by the following property owners: WIEDEMANN
RANCH INC., JEFFREY C. and NANCY A. WIEDEMANN, JOSEPH M. and ARLENE R. GRANT,
LESLIE E. THOMAS, KATHERINE APODACA, RANDOLPH D. and ROXANNE W. LINDSAY,
SANDRA W. LA VIOLETTE, STEPHEN FREITAS, EDWARD FREITAS, SUSAN CHRISTENSEN,
VERNON W. and LEANNHA P. RODES, and MARY L. WOLLGREN. There are 15 parcels of land
affected by this action, 8 complete parcels and portions of 7 other parcels. The proposed
action by the LAFC includes changing the District's sphere of influence and annexing the 675
acres to this District. LAFC is scheduled to hold a public hearing on this matter on November
18, 1992.
Contra Costa County is the lead agency in this proposal. The Board of Supervisors of the
County has determined that the proposal is consistent with the County's General Plan. Owners
representing approximately 89% of the total acreage in the boundary reorganization area have
signed a petition in favor of the proposal. The property owned by Leslie E. Thomas is not
included in the petition. There are currently two subdivisions (Nos. 7575 and 7578) in the
planning process which include 370 residential lots. All of the proposed lots can be served by
a gravity sewer system. The offsite sewer will be installed by the developer within Norris
Canyon Road and will flow by gravity to the District's existing sewer at the intersection with
Bollinger Canyon Road.
During the project's EIR process, District staff determined that the downstream public sewer
system has sufficient capacity for the planned development of the proposal area. The
applicants were informed of this District's requirements for providing sewer service, i.e. public
sewer easements, access to all sewer facilities, source control requirements, District fees and
charges due at time of connection, and our hillside and creek area policy.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INITIA TING;{EPT./DIV.
1302A-9/85
DH
JSM
RAB
SUBJECT
POSITION PAPER
COMMENT ON PROPOSED ANNEXATION OF 675 ACRES
IN THE SAN RAMON AREA, KNOWN AS NORRIS
CANYON BOUNDARY REORGANIZATION
PAGE
DATE
2 OF 3
October 30, 1992
The project applicants have requested that the District Board be informed of the proposed
boundary reorganization and provide any comments that the Board may have. It is appropriate
for the Board to support the requirements which staff has previously placed on the proposed
development and to comment on the annexation of the property to the District.
RECOMMENDATION: The recommended Board comments are as follows:
. The requirements which District staff has placed on the development of
Subdivision Nos. 7575 and 7578 are necessary and proper.
. Similar requirements will be placed on other developments within the area which
is proposed for annexation to this District.
. The Board has no objections to the annexation of the 675 acres of land to this
District.
130?8 q...Wi
ALAMED/.
~
t-
~
::..
tT\'
~\
8\
~,
~
~
>-
a:
~
~
o
Q)
d
(Jj
(;)
(;)
(;)
C!J
~
I-
C/'J
><
UJ
"
""
~
/ "
/ "
/ "
....
PROPOSED NORRIS CANYON
BOUNDARY REORGANIZATION
--1 .
---
;,
I
-.
g
t
Ii
I
I
K
--.
~ Central ~g~:~ g~~:R~~~~~~ Jistrict
1 3
PAGE 1 OF
POSITION
PAPER
BOARD MEETING OF
November 4, 1992
NO.
SUBJECT
7. ENGINEERING b.
DATE
October 30, 1992
APPROVE GRANT OF SURPLUS DISTRICT LAND
TO THE CITY OF CONCORD FOR HIGHWAY 680 OFF
AND ON RAMPS AT BURNETT AVENUE
TYPE OF ACTION
DECLARE LAND
SURPLUS. APPROVE
GRANT DEED.
SUBMITTED BY
Dennis Hall, Associate Engineer
INITIATING DEPT./DIV
Engineering Department
ISSUE: Board approval of all disposition of District real property is required. Board 'approval
is also necessary to determine that District land is surplus and eligible for sale.
BACKGROUND: The State of California (CaITrans), in conjunction with the City of Concord,
has designed new off- and on-ramps at Burnett Avenue. This project is separate from the
widening of Highway 680 and is needed to relieve congestion at Concord Avenue. The new
off-ramp will eliminate the existing north bound off-ramp to Concord Avenue. The City of
Concord must acquire all the land rights prior to construction. The City of Concord, after
acquiring the land for the Burnett Avenue ramps, will transfer the land to CalTrans. Please see
attached map for the location of the proposed work.
The off- and on-ramps are designed to cross over a 20-foot wide fee strip of land owned in fee
by the District located on the east side of Highway 680. The District has a 78-inch diameter
interceptor sewer (A-Line) within this strip of land that will remain in service. After the work
on the ramps is completed, the District's sewer will be under the ramps, but will remain clear
of the through lanes of Highway 680. District staff proposes to sell only the fee area
necessary for the proposed location of the off- and on-ramps and to grant temporary easements
for their construction on adjoining District property. The District will retain an easement over
the entire area for our existing interceptor sewer and for future facilities.
The property which is being granted to the City is technically surplus land of the District, since
the District does not require fee title, but only an easement. CalTrans, conversely, does require
f~e litle for highway purposes including off- and on-ramps. Surplus land must normally be
offered for sale or lease to various entities prior to disposal unless the surplus land is exempt
from the procedures set forth in Government Code Section 54221 et sea. Staff has determined
that the land which is being granted to the City is exempt, because it is being sold to an owner
of contiguous land (the City) and meets the access, area, use and location criteria set forth in
said Government Code section.
Staff has been in discussions with the City regarding the sale of the District property for over
one year. Staff has negotiated a deed and a Right-of-Way Contract which staff concludes
protect the District's rights. The District will be paid $42,977 for the fee area and
REVIEWED AND RECOMMENDED FOR BOARD ACTION
(1f(
w
INITIATING DEPT./DIV.
1302A-9/85
DH
JSM
RAB
SUBJECT
POSITION PAPER
APPROVE GRANT OF SURPLUS DISTRICT LAND
TO THE CITY OF CONCORD FOR HIGHWAY 680 OFF
AND ON RAMPS AT BURNETT AVENUE.
PAGE
DATE
2
OF
3
October 30 1992
temporary easements. This amount includes $34,434 for the fee area (5,739 square feet at
$6.00 per square foot), $4,180 for the temporary easements, and $4,363 for damage to
remaining property due to the acquisition by the City. These values are based on an
independent appraisal which was reviewed by the District's consultant. The City will pay for
a new manhole on our 78-inch sewer at the north end of the project and concrete encasement
of the sewer in the project area. The City will pay for any future relocation or upsizing, if
needed. The District will be allowed to close the off- and on-ramps in the case of an
emergency or for purposes of upsizing the existing sewer.
Environmental review and approval of this project is the responsibility of the City of Concord
and CalTrans.
RECOMMENDATION: 1) Make a finding that the land to be granted is surplus land which is
exempt from the Government Code requirements regarding offering for sale or lease to
designated entities. 2) Adopt a resolution authorizing the President of the District Board of
Directors and the Secretary ot the District to execute a Grant Deed and Right-ot-Way Contract
and direct staff to take such other actions as may be required to complete the transaction.
130:?8 9- B:,
o
CO
CO
>-
~
w
w
cr
u.
z
o
>-;:: ..:
O:Of-lA:
<(~zo
O:o:wen
Of-~C\/
Q,enwen
~Zeno
WO<(~
f-ow_
co~o
co~
.......
o
0:
t 5?
~ >-
o ~
o -J
cJ ~
cJ ~
en
f-
Z
W
~
w
en
<(
w
..:
en
z
o
o
-
>-.
o:f-
<(lA:
0:0
Oct)
Q,Q)
~o
wQ)
f-_
lC:-
<(0
W-J
Q,-J
o!:!!
~z
-
..:
IL.
d
en
en
C")
""
.0
"-
........
" .........-
'- ON
........
-
-
-
BURNETT AVE.
o _
0: /'
8 /~.-
z /./- /"
8 / ((<<- ./
IL. 0/
o
>-
f-
o
o
f-
W
W
IL.
cJ
o
en
Ct)
<(
Z
o
ir
o
.
>-
><
<(
-J
<(
CJ
GRANT DEED FOR HIGHWAY 680
ON & OFF RAMPS AT BURNETT AVE.
CITY OF CONCORD