HomeMy WebLinkAboutAGENDA BACKUP 10-01-92
~ Centra. Contra Costa Sanitary ..listrict
Ma~"1h BOARD OF DIRECTORS
POSITION PAPER
SUBJECT
BOARD MEETING OF
NO.
3 .
CONSENT CALENDAR a.
September 23, 1992
DATE
AUTHORIZATION FOR P.A. 92-8 (ALAMO AREA)
TO BE INCLUDED IN A FUTURE FORMAL ANNEXATION TO
THE DISTRICT
SUBMITTED BY
TYPE OF ACTION
PAGE 1
OF 2
ACCEPT ANNEXATION FOR
PROCESSING
Dennis Hall, Associate Engineer
INITIATING DEPT./DIV.
Engineering Dept./lnfrastructure Div.
Parcel
No.
92-8
Area
Alamo
78A1
and
76A7
Owner
Address
Parcel No. & Acreage
Paul Peterson
859 San Mateo Drive
San Mateo, CA 94401
187-260-006 (64.08Ac.)
Remarks
Proposed subd. 7601,
containing 93 lots. A
draft E.I.R. entitled
"Alamo Estates-Sch
#91033039" was
prepared by Contra
Costa County in March
1992, and approved
August 5, 1992
Lead
Agency
Contra
Costa
County
RECOMMENDATION: Authorize P.A. 92-8 to be included in a future formal annexation.
1302A-9/85
DH
REVIEWED AND RECOMMENDED FOR BOARD ACTION
JSM
RAB
-------------,-
P .A. 92-8
PAGE 1 OF 1
October 1, 1992
NO.
3. CONSENT CALENDAR b.
DATE
AUTHORIZE THE ATTENDANCE OF ROBERT A. BAKER,
DEPUTY CHIEF ENGINEER AT A SEMINAR ON TOTAL
QUALITY MANAGEMENT IN SAN FRANCISCO, AT A
COST OF $865
tember 17 1992
TYPE OF ACTION
AUTHORIZE
ATTENDANCE
S.!.!B~ITTED ijY
Kooert A. Baker
Deputy Chief Engineer
INITIAT,It.IG DEPTJDIV.
t:nglneerlng Department
ISSUE: Approval by the Board of Directors is required for education expense over $500, if not
covered in the O&M Budget.
BACKGROUND: The District is about to enter into a Total Quality Management program. The
University of California has recently scheduled a two day TQM seminar entitled "How to Apply
Deming's Quality Improvement Principles to Public-Sector Services and Administrative
Operations." The seminar topic is particularly pertinent because of its emphasis on public sector
application of TQM. Most programs on TQM use the industry approach which is only partially
applicable to the public sector.
Robert Baker, Deputy Chief Engineer of the District would benefit from this training and would
use the information from the seminar to assist in the development of the District program. Funds
are available in the Engineering Department Education and Training Budget to cover the cost of
this training.
RECOMMENDATION: Authorize the attendance of Robert Baker, Deputy Chief Engineer, at the
October 13-14, 1992 seminar "How To Apply Deming's Quality Improvement Principles To
Public Sector Services and Administrative Operations" at a cost of $865.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INITIATING ~
1302A.7/91
RAB
C:\WP51 \WPFiles\RAB\TQM.PP
...-.-.----.----..,--..-..-..-....--.........-.--..----..-------..--......--.-.--....----.---..-..--...
PAGE 1 OF 9
NO.
5. BIDS AND AWARDS a.
SUBJECT
AUTHORIZE AWARD OF CONSTRUCTION CONTRACT FOR
THE STANDBY POWER FACILITY PROJECT, DP 20121,
TO ALBA Y CONSTRUCTION COMPANY; AUTHORIZE
CONSULTANT AGREEMENTS
DATE
September 25, 1992
TYPE OF ACTION
AUTHORIZE AWARDI
AUTHORIZE AGREEMENTS
SUBMITTED BY Donald E. Berger
Assistant Engineer
INITIATING DEPT/DIV. Engineering Departmentl
Plant Engineering Division
ISSUE: On September 22, 1992, sealed proposals were received for construction of the Standby
Power Facility Project, District Project No. 20121. The Board of Directors must authorize award
of the contract or reject bids within 50 days of the bid opening.
Authorization by the Board of Directors is required for the General Manager-Chief Engineer to
execute a professional services agreement in an amount greater than $50,000. There are two
professional services agreements associated with the construction of the Standby Power Facility
Project which are greater than $50,000.
BACKGROUND: In January 1991, the Emergency Power Facility Study was completed. The
study recommended that an on-site standby power facility be constructed to provide electrical
power to the treatment plant during a PG&E power outage. The study compared on-site standby
power facilities with reliability improvements to the existing PG&E electrical feed system. On-
site standby power was found to be more cost-effective and reliable.
The new standby power facility will consist of two 1 ,600-kilowatt diesel engine generators; a
building enclosure with provisions for a third generator in the future; and electrical equipment
necessary to connect the generators to the plant electrical distribution system. Also included
is a load-inhibition system to disconnect non-essential plant loads from the plant electrical
system during a power outage. The project site is shown in Attachment I.
The plans and specifications for this project were prepared by John Carollo Engineers (JCE). The
project was advertised for construction on August 18 and 27, 1992. The adjusted engineer's
pre-bid construction cost estimate was $2,700,000. This estimate was reduced by District staff
from the original engineer's estimate of $3,000,000 to reflect a favorable bidding climate. Ten
sealed bids ranging from $2,199,000 to $3,181,212 were received and publicly opened on
September 22, 1992. A summary of the bids received is shown as Attachment II.
The Plant Engineering Division staff conducted a technical and commercial review of the bids and
concluded that the lowest responsible bidder is Albay Construction Company with a bid of
REWEWEDANDRECOMMENDEDFORBOARDAcnON
1302A-7/91
DEB
DJC
WEB
RAB
INITIATING DEPT/DIV.
B/ e ~~
&~ (;v[6
/)1JfJ
SUBJECT
POSITION.PAPER
AUTHORIZE AWARD OF CONSTRUCTION CONTRACT FOR
THE STANDBY POWER FACILITY PROJECT, DP 20121,
TO ALBA Y CONSTRUCTION COMPANY; AUTHORIZE
CONSULTANT AGREEMENTS
PAGE
DATE
2
OF
9
September 25, 1992
$2,199,000. The additional funds required to complete the project are $3,039,500, as shown
in Attachment III. The current total estimated project cost is $3,507,500. The estimated total
project cost listed in the 1992-93 Capital Improvement Budget (CIB) is $3,917,000. The current
balance of the sewer construction fund, less unspent allocations, plus projected dependable
revenue will be adequate to fund this project. A funding summary is presented in Attachment
IV.
An agreement has been negotiated with CH2M Hill California Inc. for construction management
services with a cost ceiling of $ 1 65,000. These services include administration of the
construction contract and general construction management and administration duties, including
inspection of the contractor's work. Electrical and instrumentation inspection, however, will be
provided by JCE.
An agreement has been negotiated with JCE for engineering services during construction with
a cost ceiling of $195,100. These services include evaluation of contractor submittals and
preparation of design clarifications; electrical/instrumentation inspection as noted above;
preparation of record drawings; and start-up and training assistance. JCE will also produce the
software for the standby power facility computer control and load inhibition system costing
$58,800, which is included in the cost ceiling amount. This software development includes
preparing display screens for the standby power control system and programming the
programmable logic controllers. District staff will coordinate with JCE on the PLC programming
and modify the main (Modcomp) computer system to communicate with the standby power
facility.
The CEOA requirements for the Standby Power Project were addressed in the Negative
Declaration prepared for the Headworks Facilities Improvement Project. The Negative
Declaration was approved by the Board on December 21, 1989.
RECOMMENDATION:
Construction Contract: Authorize award of the construction contract to Albay Construction
Company as the lowest responsible bidder in the amount of $2,199,000 for the construction of
the Standby Power Facility Project (DP 20121).
1302B-7/91
_.._____.__.._..__~,._._.___".__..,_._.....~,__,,'__.._.,_~__~-..o..-.--~~_>__-..._____~,.-.---~'-.-.^---"'.-.-~.-~--...----.-..---.--.-------
SUBJECT
AUTHORIZE AWARD OF CONSTRUCTION CONTRACT FOR
THE STANDBY POWER FACILITY PROJECT, DP 20121,
TO ALBA Y CONSTRUCTION COMPANY; AUTHORIZE
CONSULTANT AGREEMENTS
POSITION PAPER
PAGE
DATE
3
OF
9
September 28, 1992
Consultant Contracts: Authorize the General Manager-Chief Engineer to execute the following
cost reimbursement agreements for engineering services during the construction of the Standby
Power Facility Project:
1 . Agreement with CH2M Hill for construction management services with a cost ceiling of
$165,000.
2. Agreement with John Carollo Engineers for engineering services during construction with
a cost ceiling of $195,100.
1302B-7/91
. ---..---.--.---r---'-----.---'-'------.-"---.--------.--'------"---
Page 4 of 9
ATTACHMENT I
I ----------------J ----------------
II
"
I I
I I
~' ,----------------- ---------------...-...........
cBS
~
/'
,/'
/
/'
/'
)'
/'
/'
,
/
/'
, ---
L__________-
Page 5 of 9
ATTACHMENT II
Central Contra Costa Sanitary District
SUMMARY OF BIDS
PROJECT NO. 20121
- STANDBY POWER FACILITY PROJECT
DATE Seotember 22. 1992
ENGR.EST. $ 2.700.000
LOCATION Martinez. California
# BIDDER BID PRICE
(Name, telephone & address)
1 Albay Construction Co. 510-228-5400 $ 2,199,000
P. O. Box 2569, Martinez CA 94553
2 Auburn Constructors 916-387-0344 $ 2,402,000
5580F Power Inn Road, Sacramento, CA 95820
3 Humphrey Construction Inc. 510-229-5820 $ 2,422,000
P. O. Box 907, Woodinville, WA 98072
4 Amos & Andrews 707-422-4844 $ 2,432,731
P. O. Box 250, Fairfield, CA 94533
5 D. W. Nicholson, Inc. 510-887-0900 $ 2,590,000
P. o. Box 4197, Hayward, CA 94540-4197
6 Amelco Electric 510-895-2040 $ 2,637,803
1777 Neptune Drive, San Leandro, CA 94577
7 Alan A. Bradford, Inc. 707-437-5484 $ 2,645,000
4970 Peabody Road, Fairfield, CA 94533
8 Dalzell Corporation 415-835-6732 $ 2,820,000
2434 Chestnut Street, Oakland, CA 94607
9 Echo West 415-285-2404 $ 2,876,000
1500A Davidson Avenue, San Francisco. CA 94124
10 Monterey Mechanical 510-632-3173 $ 3,181,212
8275 San Leandro Street, Oakland, CA 94621
BIDS OPENED BY /s/ Paul Morsen
DATE 9-22-92
SHEET NO. -1- OF -1-
PED/Misc/20121Sum.DEB
ATTACHMENT III
STANDBY POWER FACILITY PROJECT
DISTRICT PROJECT NO. 20121
POST BID, PRECONSTRUCTION ESTIMATE
ITEM
Direct Construction Costs
.
Construction Contract
.
Construction Contingency
.
Software Programming by JCE
(PLCs and Operator Interface Station)
.
Software Programming by POD
Subtotal
Construction Services
. CH2M Hill California
Construction Management and
Inspection
. John Carollo Engineers
Engineering During Construction
Electrical and Instrumentation
Inspection
. District Forces
Construction
Engineering
Plant Operations
Survey
Subtotal
TOTAL
$2,199,000
330,000
58,800
1 5.000
$2,602,800
$165,000
86,900
17,200
45,000
1 5,000
25,000
3.000
$ 3 57, 1 00
1
Page 6 of 9
PERCENTAGE OF
CONSTRUCTION COST
100.%
13.7%
ATTACHMENT III (continued)
STANDBY POWER FACILITY PROJECT
DISTRICT PROJECT NO. 20121
POST BID, PRECONSTRUCTION ESTIMATE
Soecialtv Services
. Construction Materials Testing, Inc.
Testing Services
. DCM/Joyal Engineering
Geotechnical Services
. John Carollo Engineers
As-Built Drawings
Subtotal
Startuo and Trainina
. Dan Cortinovis
O&M Manual and Operator Training
. John Carollo Engineers
Training and Start-Up
. District Forces
Start-up and Performance Testing
1.
2.
Engineering
Plant Operations
Subtotal
------.-.--------------,---
$ 6,000
9,300
10.500
$25,800
$23,100
21,700
3,000
6.000
$53,800
2
Page 7 of 9
1.0%
2.1%
Pre bid Exoenditures
.
Facility Plan
.
Final Design
.
Bid Period Services
A IT ACHMENT III (continued)
STANDBY POWER FACILITY PROJECT
DISTRICT PROJECT NO. 20121
POST BID. PRECONSTRUCTION ESTIMATE
$ 64.000
380.000
Subtotal
24.000
$468.000
TOTAL PROJECT COST
$3.507.500
FUNDS EXPENDED TO DATE
$468.000
ADDITIONAL FUNDS REQUIRED TO COMPLETE $3.039.500
THE PROJECT
PED/PP/2012ATT3.DEB
DEB/kg September 23, 1992
3
Page 8 of 9
17.9%
134.8%
A IT ACHMENT IV
PROJECT FUNDING SUMMARY
Sewer Construction Fund Balance as of
August 31, 1992
- Unspent Prior Allocations
+ Dependab~ Revenue*
$46,618,999 > $3,039,500 (Allocation Required)
* Includes 40% reduction in ad valorem tax
PED/PP/2012Att4.DEB
DEB/kg September 23, 1992
-.-..------,.,-.....---..-,..-.-..-......-.----"...,-,--.--.--.---r-----....
Page 9 of 9
$ 67,585,278
< 39,358,229 >
18.391.950
$46,618,999
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
PAGE 1 OF 4
BOARD MEETING OF
October 1, 1992
NO.
6. SOLID WASTE a.
SUBJECT
DATE
Se tember 25, 1992
CONSIDER ISSUES PRESENTED BY VALLEY WASTE
MANAGEMENT RELATED TO THE FULL-SCALE
IMPLEMENTATION OF THE AUTOMATED CURBSIDE
COLLECTION SYSTEM
TYPE OF ACTION
PROVIDE DIRECTION TO
REFUSE COLLECTOR
SUBMITTED BY
INITIATING DEPT./DIV.
Walter N. Funasaki, Finance Officer
Administrative/Finance & Accounting
ISSUE: In a report on the full-scale implementation of the automated curbside collection system
by Valley Waste Management at the September 16, 1992 Board Meeting, a number of related
issues were presented for consideration by the Board of Directors.
BACKGROUND: At the September 16, 1992 Board Meeting, Harriette Heibel, Recycling
Manager of Valley Waste Management, reported on the program to fully implement the
automated collection system in its entire service area, with the exception of the City of
Lafayette. The following summarizes the four matters reported on, and the issues for which
direction by the District is requested. District staff recommendations to address each issue are
provided for the Board's consideration.
Delayed Implementation of Automated Collection System
Summary of Matter:
The full-scale implementation of the automated curbside collection system beyond the
7,350 pilot program customers in Danville was originally scheduled for September 1992.
Because of a delay in delivery of the wheeled refuse containers, implementation will
begin in October 1992. Implementation will occur on a phased basis over a six-week
period, with notification to customers ten days prior to delivery of the refuse container.
Issue:
Valley Waste Management wishes to determine whether the District considers the
delayed implementation schedule acceptable.
Staff Recommendation:
The delayed implementation schedule is based on reasonable cause and should be
considered to be acceptable. As planned, a $1.85 per month per household rate
decrement should be provided to customers as the automated service is obtained.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
WNF PM
---~",-,-~~-,'--------~---'--~._'."...,--".._,.."-"--'--'---'~-'---~-----'-'r-"+-'----'-- .'- ----"'---~----_.--_.-_.----.,.---.-.-,-----------..-.----,.,-.-----
CONSIDER ISSUES PRESENTED BY VALLEY WASTE
MANAGEMENT RELATED TO THE FULL-SCALE
IMPLEMENTATION OF THE AUTOMATED CURBSIDE
COLLECTION SYSTEM
SUBJECT
PAGE
DATE
2
OF
4
September 25, 1992
Hard-To-Serve Customers
Summarv of Matter:
Residential customers who reside in the hilly areas of Danville and Lafayette and require
service by a small collection vehicle are supposed to be charged a higher hilly service
collection rate. However, most of the 800 Danville and 1,050 Lafayette customers
currently being serviced by a small vehicle are not being charged the hilly rate. Of the
800 Danville customers, 570 must continue to be serviced by the small vehicle and are
unable to participate in the automated collection program; the balance of 230 Danville
customers can be serviced by the automated collection vehicle, and will be provided the
option of continuing to be serviced by the small vehicle or to receive automated service
at a lower collection rate.
Issues:
Valley Waste Management wishes to foreadvise the affected Danville and Lafayette
customers by letter and to adjust their collection rates to the hilly service rates; at the
same time, those Danville customers who are able to obtain the automated collection
service would be advised of the availability of this option.
Staff Recommendation:
An application for a rate increase effective January 1, 1993 has been filed by the refuse
collector. It would be appropriate to incorporate the correction to the affected
customers' collection rates, and to effect the change to automated service for those
electing such service, with the January 1, 1 993 effective date for the general rate
adjustment. This would avoid rapid and successive increases in collection rates for
these customers. A letter should be drafted by the refuse collector for issuance in
November 1992 to foreadvise the affected customers; the draft letter is to be submitted
for review to the District.
Capacity Limitation at Waste Fibre Recovery
Summarv of Matter:
Waste Fibre Recovery (WFR) currently processes the separately-collected green waste
from the 7,350 residential customers in the original pilot program at a cost of $9.90 per
ton. The contract between WFR and Waste Management requires that green waste
1302B-7/91
-.. --"~-'~"'--'.'-"-_.'~--'-r--'-"'"_."------------~----.-.,-------.--...----.,-.---
CONSIDER ISSUES PRESENTED BY VALLEY WASTE
MANAGEMENT RELATED TO THE FULL-SCALE
IMPLEMENTATION OF THE AUTOMATED CURBSIDE
COLLECTION SYSTEM
SUBJECT
PAGE
DATE
3
OF
4
September 25, 1992
comprise no more than 25 percent of the total green waste and wood waste delivered
to WFR. Recently, WFR notified Valley Waste Management that it will not accept
additional green waste over current levels because of less than anticipated wood waste
volumes from Waste Management companies. While Valley Waste Management is
attempting to increase deliveries of wood waste to WFR, the volume increase will
probably not be sufficient to guarantee acceptance of the increased green waste from
the full-scale automated collection program. The lower green waste disposal cost was
a major component of the economic benefit of the automated collection program.
Subsequent to the September 16, 1992 Board Meeting, Valley Waste Management
negotiated a $55 per ton charge for green waste to be delivered to the demonstration
compost project at the Acme landfill. The current Acme Transfer Station fee for solid
waste is $77.07 per ton.
Issues:
Valley Waste Management wishes to obtain direction from the District regarding its
efforts to obtain increased green waste capacity at WFR, and the disposal alternative
negotiated with the Acme demonstration compost project.
Staff Recommendation:
Valley Waste Management should continue separate collection of green waste and
deliver the maximum volumes possible to WFR, with the balance being deposited at an
alternative location. Valley Waste Management should continue to seek better green
waste processing alternatives. The effect of the higher resulting expense due to use of
the Acme compost project compared to the disposal expense projected during the pilot
program will be incorporated in the current review of collection rates effective
January 1, 1993.
Changed Schedule for Seasonal Clean-up Collection
Summary of Matter:
The refuse collector currently performs the three seasonal clean-up collections on
Saturday, with each community being serviced over two or three Saturdays. With the
conversion to automated collection vehicles, a large number of the rear-end loader trucks
would have to be retained only for use during the seasonal clean":ups. If the clean-up
collection were to be provided to customers three times per year on the same day as for
refuse collection, the number of rear-end loader trucks required would be significantly
reduced, and payment of overtime wages would be avoided.
1302B-7/91
-.---....-------......---.-----.-.....--.------,----....---
CONSIDER ISSUES PRESENTED BY VALLEY WASTE
MANAGEMENT R~LA TED TO THE FULL-SCALE
IMPLEMENTATION OF THE AUTOMATED CURBSIDE
COLLECTION SYSTEM
SUBJECT
PAGE
DATE
4
OF
4
September 25, 1992
Issue:
Valley Waste Management requests the District's approval to revise the schedule for
seasonal clean-ups to be coincident with the refuse collection day.
Staff Recommendation:
The change reque,sted in the seasonal clean-up schedule should be approved, as it will
remove underused vehicles from the fleet and reduce operating expenses. The revised
seasonal clean-up schedule should be implemented effective the 1993 calendar year.
The summary of the issues and the related staff recommendations contained in this Position
Paper have been reviewed with the refuse collector, who concurs with the staff
recommendations.
RECOMMENDATION:
Consider the issues presented by Valley Waste Management related to the full-scale
implementation of the automated curbside collection system and approve the staff
recommendations following each issue, as described above.
1302B-7/91