HomeMy WebLinkAboutAGENDA BACKUP 03-18-93
~ Central ~~~~~ g~~~R~~~g-~~ ..listrict
PAGE 1 OF 2
POSITION
PAPER
BOARD MEETING OF
March 18, 1993
NO.
3. CONSENT CALENDAR 1.
SUBJECT
DATE
March 9, 1993
QUITCLAIM SEWER EASEMENT TO THOMAS c. O'HIGGINS,
EX UX, JOB NO. 4119, ORINDA AREA
TYPf:.QF ACTIOr:i,
At"PROVt:: QUITCLAIM
OF SEWER EASEMENT
SUBMITTED BY
Dennis Hall, Associate Engineer
ISSUE: Mr. and Mrs. O'Higgins, owners of Lot 1 0 of Subdivision 5649, have requested the
District to quitclaim the subject easement.
BACKGROUND: The subject easement was granted at no cost to the District for a future
sewer main in 1986 shortly after the subdivision map was filed. Subsequently, the sewer was
redesigned and a new sewer easement was created. The public sewers have been constructed
in the replacement sewer easement. Therefore, the easement on the O'Higgins' property, Lot
10, is no longer required and can be quitclaimed. The property owner has paid the District's
processing fee.
This project has been evaluated by staff and determined to be exempt from the California
Environmental Quality Act (CEQA) under District CEQA Guidelines Section 18.6, since it
involves a minor alteration in land use limitations.
RECOMMENDATION: Approve Quitclaim Deed to Thomas C. O'Higgins, et ux, Job No. 4119,
authorize the President of the District Board of Directors and the Secretary of the District to
execute said Quitclaim deed, and authorize the Quitclaim Deed to be recorded.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INITIATING DEPT./DIV.
1302A-9/85
JOt(
DH
RAB
5649
\J\S\ON
SUf:,.J\ "-
J v '-'=
/.. r-, ,,-_
It I ',,,-..-
LOT 8 \ ~ ""-0'-..-
REPLACEMENT \ \9j//<5.7'/"II::;', "....co
EASEMENT ~ \ LOT 10 '2; ",<:.
~\ .,(ffr, "
,,\ ~/' ,,"-
-' A!~/':. ""-
\ ,f.''' "'\
;,,4fP" UITCLAIM '\
.'. Q ASEMENT \ \
E" '\
"I Q i'/J ::J
LOT 9
NEW SEWER MAIN
" "
PAl'tZt ;4
'pARtCL "8~
~..t'''cL '17"
MRCct 21"
1
QUITCLAIM EASEMENT
JOB 4119
ORNIDA AREA
L-
I
~ Central :ontra Oosta Sanitary Jistrict
h{d~~]h BOARD OF DIRECTORS
PAGE 1 OF 2
POSITION
PAPER
BOARD MEETING OF
March 18, 1993
NO
3. CONSENT CALENDAR m.
SUBJECT
DATE
APPROVE SEWER EASEMENT AGREEMENT WITH EAST BAY
MUNICIPAL UTILITY DISTRICT, JOB NO. 4782,
PLEASANT HILL AREA
March 8 1 993
TYPE OF ACTION
APPROVE AGREEMENT
SUBMITTED BY
INITIA TING DEPT.lDIV.
Thomas Cheng, Assistant Engineer
Engineering Dept./lnfrastructure Div.
ISSUE: Easements which are granted by other public agencies require specific approval by the
Board of Directors.
BACKGROUND: In connection with Caltrans 1-680 widening, this District must realign the
existing sanitary sewer crossing EBMUD's aqueduct in North Main Street in Pleasant Hill which
is a part of the District's 1-680/SR-24 Sewer Relocations, Phase III Project. A 15-foot wide
replacement easement, contained in an easement agreement, for the realigned 30-inch diameter
sewer has been executed by EBMUD and is being offered to this District in exchange for
quitclaiming of the original sanitary sewer easement. The quitclaiming of the original 10-foot
wide easement is being submitted to the Board for approval under a separate position paper.
The replacement easement is shown on the attached map, Exhibit A.
In accordance with the California Environmental Quality Act (CECA), a Notice of Exemption for
the 1-680/SR-24 Sewer Relocations, Phase III Project was filed with the Contra Costa County
Clerk on February 25, 1993.
RECOMMENDATION: Approve Easement Agreement with EBMUD, Job No. 4782, and authorize
the President of the District Board of Directors and the Secretary of the District to execute said
Easement Agreement, and authorize the Easement Agreement to be recorded.
~cc
t(?
INITIA T1NG DEPT./DIV
11D2A-9 85
TCC
TJP
JSM
RAB
Orinda
LOCATION MAP
G)
QUITCLAIMED
10' WIDE
, ,~EWER EASEMENT - - - - - - - f
-"', - - - - - -
- -
- -
- -
---
--
, '"
Central Contra Costa
Sanitary District
G
~
I~
10
:~
I
"
f---...
- EXIST.
N.:. ~IN ST.
- ....
\
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
\
\
EXIST. 680 ON RAMP '....
-
...--
PROPOSED
N. MAIN ST.
CONTRA
COSTA
BLVD
...
I
Grant of Sewer Easement
Job No. 4782
Pleasant Hill Area
A
Exhibit
~ Central ;ontra Oosta Sanitary
Md~~]k BOARD OF DIRECTORS
istrict
PAGE 1 OF 2
POSITION
PAPER
BOARD MEETING OF
March 18, 1993
NO.
3. CONSENT CALENDAR n.
SUBJECT
DATE
QUITCLAIM SEWER EASEMENT TO EBMUD, JOB
NO. 1536, PLEASANT HILL AREA
March 9 1 993
TYPE OF ACTION
APPROVE QUITCLAIM
SUBMITTED BY
INITIATING DEPT.lDIV.
Thomas Cheng, Assistant Engineer
Engineering Dept./lnfrastructure Div.
ISSUE: East Bay Municipal Utility District (EBMUD) has requested the District to quitclaim the
subject easement in' exchange for a new easement across property which. EBMUD owns in
North Main Street, Pleasant Hill.
BACKGROUND: The subject easement was granted to the District by EBMUD on June 8,
1956. In connection with Caltrans 1-680 widening, this District must realign the existing
sanitary sewer crossing EBMUD's aqueduct in North Main Street in Pleasant Hill which is a part
of the District's 1-680/SR-24 Sewer Relocations, Phase III Project. A replacement 15-foot wide
easement for the realigned 30-inch diameter sewer is being submitted to the Board for approval
under a separate position paper. The original 10-foot wide easement is no longer needed and
may now be quitclaimed. The original easement is shown on the attched map, Exhibit A.
In accordance with the California Environmental Quality Act (CEQA) a Notice of Exemption for
the 1-680/SR-24 Sewer Relocations, Phase III Project was filed with the Contra Costa County
Clerk on February 25, 1993.
RECOMMENDATION: Approve Quitclaim Deed to EBMUD, Job No. 1536, and authorize the
President of the District Board of Directors and the Secretary of the District to execute said
Quitclaim Deed, and authorize the Quitclaim Deed to be recorded.
REVIEWED AND RECOMMENDED FOR:e: ~~D ACTION
TCC
TJP
JSM
RAB
-rc-c
INITIA TING DEPT.lDIV
1102A-9 85
"-----'-'-..- '"--,._~-,,_._."---_._,,~-_.._,-~..,".__._,._-,-,-"._~-,.---~_."-,_._.,.__._.__._---~-_._-_..__.>~._,-'- ..-......."-.-.--.--.-.....---....-.-...-..---.------.-_.-,--~_._-_...-_..~--,...__.._----'~_..." ~-""'---"--"'-~------"---
Orinda
G
/''"''
''"''
, f/iMUD ~",
....,--, PROPERTY '"" PROPOSED
"~ ' 30' 55
''"'' PROPOSED '""',""
'..... 15' WIDE SEWER '
......, EASEMENT '""
'"", '"",
'""
G)
o
<
10
a:
10
1>-
Jg
I
/
,
f --
- ExiST.
_ N.:. ~~\ 51
I
I
I
I
I
J
I
J
I
I
I
I
I
I
I
I
I
I
,
\
\
EXIST. 680 ON RAMP ,
- ....
.' '
-.' ---i
_ _ __ u _ _ - _ - -~~~~-~';: - - - - - ~~~-_~- --
EXIST. N. MAIN ST. - - - '"
- - - - ':::.: - - -;..:;- it>.~~ - - - - -
-" _--i~U" _-----
_ >-<.. ~~\s. ~ PROPOSED
- -~ -
- _ -:" N. MAIN ST.
PROPOSED
N. MAIN ST.
"
Central Contra Costa
Sanitary District
Quitclaim of Sewer Easement
Job No. 1536
Pleasant Hill Area
'--
CONTRA
COSTA
BLVD
,-
I
Exhibit
A
~ Central ~g~~~ g~~~R~~~ba~~ Jistricl
PAGE 1 OF 3
POSITION PAPER
BOARD MEETING OF March 1 , 1
NO.
3. CONSENT CALENDAR o.
DATE March 9, 1993
SUBJECT
AUTHORIZATION FOR P.A. 93-3 (WALNUT CREEK) AND
P.A. 93-4 (DANVILLE) TO BE INCLUDED IN A FUTURE
FORMAL ANNEXATION TO THE DISTRICT
TYPE OF ACTION
ACCEPT ANNEXATION
FOR PROCESSING
SUBMITTED BY
Dennis Hall, Associate Engineer
INITIATING QI:PT./DIV . . .
~nglneering Dept.llnfrastructure DIVIsion
Parcel Area Owner/Address Remarks Lead
No. Parcel No. & Acreage Agency
93-3 Walnut Creek Haist Corporation Property owner will Walnut
(50B7) P.O. Box 33 build three single Creek
Orinda CA 94563 family residences on
139-080-010 (1.48 Ac.) site. Categorical
exemption by city of
Walnut Creek. CEQA
Section 1 5061 (B)
Danville Ernest P. Graham Property owner has CCCSD
93-4 (78D5) 125 Railroad Ave. #202 built one single
Danville CA 94526 family house and
196-042-008 (1. 1 Ac.) must connect to the
public sewer. Project
is exempt from
CECA.
RECOMMENDATION: Authorize P.A. 93-3 and P.A. 93-4 to be included in a future formal
annexation.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
1302A-9/85
/'
l~ [ \',-
DH
RAB
INITIA TING DEPT./DIV.
~~ 1:1 ~130-l-~ \-\'i \~~\\~'l"f'-Y-~ ~~~~7.,\~..\-1 I .\.'~':;:~~il~ /0';S "-"YJ:J.I' ...~.
~~ ~4t1 <.~ =, ~'1" ~ n~ ~\ '!.. ";-;;"-1 1"" 'y.:\ V'''\;. "'I',,'(,;j ~ <7<>J ~/F- .
~H;; .Qi.~. '. "5___/0 ~I-:.V ~:J~!:3 0 ~:-i ~~" Jl; 1~h.fT~.7 -~~~ 11" '" \" \~ A ~r ~ ~lM .ot. ..
'27/ E:II 0 .."..,.....' 0 ~~<'! ~'-C'~FE 0 0-......45 \ ~1 ,1T0h- h/ .0 0 \ 'Yf'\'\fiO.. 28 Ij'Cfil'S "'~ .:.
/1 ' 125 0" , ---. '" j ~:...... till R\..S ~j.. ~. .
, \ .. r.~~ 2S . . \~~ . ...t;;~ 'I" 4 ..~ or 1. .. .2~. 8 ,',.; .
~ ,_ /'2<\ I 20 L. \& ~ ':\.. ~.~ ..<..... Z "
t~.:. 'f:r~.'" ..., WALNUT. ~X~N~E .\~'~jd' ~ :;\ ';~.!~;.. ~~_ '. !lid'I~~'. ·
2~AC
· S...... :ii .' ................. .'v>>. . IT . ... ~',:s: ...... ... '. ..,. J
~ r1.. -/.f..~~~ 2004C .:.:.:.............,ti:.,..;.. ........:et' ~ '4 .18~:\~j4! I '. ; .:..I.
.,.-.,;.;: U of 7 j(; ! l'"-y J .i=ii ',,," ~ ;5': It\c' L$: >.i"':$:'
~ ,\ ~ ~O.,~~;~,: 4: :e;-"-l!..OS LL ~ ., :.~-::.:::.
.; T. 27 .. · IHr~..~~-:IZ:::: :::~:::: .:...:~~::.::~ :'0: ~'li ~ :'.' 3 ) II ~.5 ~ ::~_i~ o~
8 ~~~ ~ll!f";i..~.I'![fr'_. ...t.L:.: ..1 1\ _\0 ~'L 7~>.:~rfffl1f1 I A . C
5 ' ,.'i~~.~' '" Sl4 .. ~B:. - :II _ ~.i~V11: 1110 D
~. ~I ,0" .,...#~ lll'i 'j!"lili 7' . ":' ~ 1;0
'S</ I Jo 'f U DR. E II/COR1IE'afiRi!: ':'- ~ '" '~:" J I
I ~ }5 'i.f~ '2 cba I ~oI,. ~'::5 IT :'-:ClI. :'. .'. .~: ~ ~ ~'~C5 ... OROHARO InUT 5 DR
i!ffi ~IJ~~ ,;. '1~"~.':c it~; ~l~.~...ti_.;Q: . OJ
r:J 38 "~ .. ('I SU. 'f'C~1 1 '.. .... ... < '~Ir.:""';:;'~-..' ...:\ "~
.~vr;t 'II" ~ftgl:~5 iQ-ll-~ ..1'- .A..4l ~l~" .r.:.: 0 J2'IU~ II;!' a: . ..'j;!:f '!$~ :~:J::'" ~ ~'. r "11i
~.... L.....M <.&~c.~ S SNYDfR CT a: .,:.. . ....:. a: I 50) ~ ~ ~ ~ U I ?.. t> ~ -;" 0.....-;:
50 49{ ~ $I> ___ 191/8 .. t> " 10' V51 ~~:UJ >- y -""r-J _ 17
, I ~ ,... dl ~ ,.... Q 'Z "10 Zij")-... _~ '" .... '86 eo \ ~'71 --< =r .
~.: 6 ,......, ZO <' ~ f.:l 5 ~' ~ii.~ 2' ;)\ I Z ~ I- ~ .:. 72 \. 86 /. IS)
P:J.~~'(V 52 - ~ - ... ~\.. l~ ~ 0 en ,r
61' . ~ \I ~ 51 \--~..' I~ ~ s:Js'" 14' en < S7,!IlI 8 "d..J,Q "/!165 10 -j I'
45 ~ 'to... Q ~ 1 I< 26 \ 27 Z 0 7 (
~ 44~ 4~~ 5.: -..!.. T. ;'~ ~ F ).c DR ~ .c- _ -0- 52 51.! 42 4\ ~ 32 I-.-.lil
_ ':' 57' ~ Is;l )} ...:.- <J )j: U ..iN.-. ~ (/" I 50~ ~ ~ :;:~ ~
- I() ('oS;, r/ 7 ~...~ "'" / 4 2 S I ...., I ~ ~ 29 ~ ::II::: ::::;>::.0.4' ~ . ~ .:~ ........:.. ~~ : 1\
6 4~~ ~~c.," . ~""~# n! r.4 Q; :J: NORTH GATE .%.. ~t.e.:.~t~I:~.l. ..~;li.../:l:
~',g~''{ 50'" ~'" a:f: HIGH SCHOOL '. .::', .'. .~: ....."vn. '.s;gJ;J:..~r.:. .:tf;'\'>.
,}'i9 c. ~ 53 ,. ;UJ ;.. :';':.t; .,.
.. . -'-..... J . l_ \ ,0 ......
1... 52 ' ./ :;..l,.' . ::::::::::::.
.n . n ~(Z~'IJ': '11J~ .{{Iilt:'
. 55 It.~ .!~ V '.:. . . - .: p en ~ f!!!!!W.
~ d'SI 4 ~uTi'~#~ . J,I'\ ". T r .~
;_{,yt!;;;$~:'4lu/,:,'f! ~ !n fO~MI~TAS DRIVE J!/IF
~.= :,;;::~ - - - -~I :.__J\ r
I ~. .1~
fL' ~ I~\
-"'""'~t
.___i. ~ \\
. -...~ ,'" ~ -- .
,f:fdff!ff::
,
--
c
MC ADA
27.57
.....:.:..:\.::.\
..,
'. +("
-~Z"l"
~
"AN~,
7.4IAC'
(',,("
~
5.05 AC
1
TYI.~R
54, 14 AC
'--
2.0lAe
4. 88 AC
PROPOSED ANNEXATION
~
93-3
L...---
I
.:.:.;.:.;.;
............
............
;;;IIe41
.f!
VALLEY
74
73
C H IGHT O~
PROPOSED ANNEXATION
93-4
~ Central Contra Costa Sanitary District
, BOARD OF DIRECTORS
POSITION PAPER BOARD MEETI~~;ch 18, 1993
PAGE
OF 3
NO.
3.
CONSENT CALENDAR
p.
SUBJECT
ADOPT RESOLUTION APPROVING THE PURCHASE OF
PARCEL 10254-01-01, APPROXIMATELY 2,702 SQUARE
FEET, CITY OF ORINDA, DISTRICT PROJECT 4898
DATE
March 12, 1993
TYPE OF ACTION
ADOPT RESOLUTION
SUBMITTED BY
INITIATING DEPT.IDIV.
Ad m i nistrative/Purchasi ng
ISSUE: The District's Board of Directors' adoption of a resolution is required for the purchase
of real property by the District.
BACKGROUND: In 1989, Caltrans indicated to the District that it would be starting its process
of decertifying a 2,702 square foot piece of property that lies adjacent to the District's Orinda
Crossroads Pump Station (see Attachment I). When Caltrans completed the real property
release procedure it would be available for purchase.
The District staff has kept in contact with Caltrans during this lengthy process, indicating that
the District was interested in acquiring this parcel. On March 3, 1993, the District received
Caltrans' "Option to Purchase" offer, wherein Caltrans will sell the 2,702 square foot parcel
to the District for $1,000 and applicable recording/escrow fees.
There are two District force mains from the Orinda Crossroads Pump Station that pass through
this parcel. By the District owning this property, it will make it easier to protect and maintain
these force mains. Furthermore, the existing pump station site is narrow and limited. The
purchase of this parcel will give the District an additional space option if the need arises to add
emergency power facilities or additional environmental controls to the pump station.
This project has been evaluated by staff and determined to be exempt from the California
Environmental Quality Act (CEQA) under District CEQA Guidelines Section 5.2(b)(3) since it can
be seen with certainty that there is no possibility that the acquisition will have a significant
effect on the environment. The Board's approval of this project will constitute a finding of
agreement with this determination unless otherwise indicated. A Notice of Exemption will be
filed with the County Clerk. Further appropriate environmental analysis will be conducted if,
in the future, the District considers using the property for other currently undetermined
purposes.
RECOMMENDATION: Approve the purchase of State-owned Parcel 10254-01-01 from the
State of California, Department of Transportation, in the amount of $1,000, adopt the attached
Resolution, and authorize District staff to execute all appropriate documents.
INITIA:;~/
/1/CT
REVIEWED AND RECOMMENDED FOR BOARD ACTION
R 7~ENG _
ROGER J. DOLAN
1302A-7/91
KFL
PM
---_._'---,._--_._-~,--"'-------,~,------,-----.""---~-_..._._._.._,.__.."_._-----,.~_._-----_..._._.,._"--,--_...".,._--_.._-_.*--~--_._-~----
RESOLUTION NO. 93-
A RESOLUTION AUTHORIZING THE PURCHASE OF REAL
PROPERTY BETWEEN THE CENTRAL CONTRA COSTA SANITARY
DISTRICT AND THE STATE OF CALIFORNIA
BE IT RESOLVED by the Board of Directors of the Central Contra Costa Sanitary
District as follows:
THAT, this District hereby consents to the execution of the Option to Purchase
and all applicable legal documents for State's Parcel No.1 0254-01-01, between the Central
Contra Costa Sanitary District and the State of California, Department of Transportation;
THAT, the District is hereby authorized and directed to execute the Option to
Purchase and all required escrow documents;
THAT, the President and Secretary of the District are hereby authorized and
directed to accept the Grant Deed for and on behalf of the Central Contra Costa Sanitary
District; and
THAT, the District staff is authorized and directed to record said Grant Deed.
PASSED AND ADOPTED this 18th day of March, 1993, by the District Board of
the Central Contra Costa Sanitary District by the following vote:
AYES:
Members:
NOES:
Members:
ABSENT:
Members:
President of the Board of Directors,
Central Contra Costa Sanitary District,
County of Contra Costa, State of California
COUNTERSIGNED:
Secretary of the Central Contra Costa
Sanitary District, County of Contra
Costa, State of California
Approved as to Form:
Kenton L. Aim
District Counsel
"0
0 ,- (\.I 0 .
t Z 0 <;to C\J
0 W <n II Z
. Z ~ I I =
~ w -
... 0 ~ ,- CO-a:: 0
- >- a: 0
... ~< 00 0 Wo
~ Zl-zQ. W..J
:.. a:lI:w(f.l en I r-<
ctJ OOOZ "'d" <0
... LL.Q.. < < ''''It" .. o (/) . r<')
III :J~Oa:1- 0: LO . ~
-.J <<zI-9 0 (\J a.. N
olI:u;u.a: lJJ
u. I- ::l o. I- 0
o .0 ~!!? ..... <t W ~
wg;:I:ZO () ,- a.: I-
<w 0 ~ 0 >.0: ""
I-ZZ~ W
(/)u;<a: I >m
'1- ::l < 0: 0 m
CD Q. .00 U
CV w -
0 0 0 a:~O U
oU
E'
.::>
0 0
~ 0
C'l
....
~~ t- 8
w
w co
J.."r' u..
. ~ z
ra"r' w
.{ v 4t ..J
<(
0)& () 0
Vcf C/) 0
o""Jtv ~
I-f
\) I-
"- Z
w
:::E
:J:
U
e:(
0 l-
I-
e:(
e:(
Cl
Z
I-f 0..
O:::::E
or- O~
0.. Z
0 V) 0
- V) I-f
I 1-01-
or- Ue:(e:( oq:
I-f 0 I-
a 0:: 0:: V)
I- V) Cl
I V) V)
I-f 0 <:
~ Cl 0::
LO U .......
C\I a:
0 0 0
~ or-
~ 0
IJ..
I
Cl 0
Cl ~
'tl ......
c:
ctJ .......
- (.)
~
ctJ
0
::. O'X91-~
t
PAGE 1 OF
1
BOARD MEETING OF
March 18, 1993
NO.
3. CONSENT CALENDAR q.
SUBJECT
AUTHORIZE THE ATTENDANCE OF LYNNE PUTNAM, SENIOR
ENGINEER, AT THE MAY 23-26,1993 WEF SPECIALTY
CONFERENCE IN WHIPPANY, NEW JERSEY, AT A COST OF
$950
DATE
March 1 2 1993
TYPE OF ACTION
AUTHORIZE
ATTENDANCE
SUBMITTED BY INITIATING DEPT./OIV.
David R. Williams, Planning Division Manager Engineering Department/Planning Division
ISSUE: Approval by the Board of Directors is required for unbudgeted travel outside of California
and/or if the expense will exceed $500.
BACKGROUND: Lynne Putnam, Senior Engineer, is responsible for Treatment Plant Planning
Projects including the Disinfection Facilities Plan and the UV Pilot Study. Lynne has written a
paper entitled, "Pilot Testing UV Disinfection on Secondary Effluent at CCCSD." This paper has
been accepted for presentation at the Water Environment Federation (WEF) Disinfection Specialty
Conference to be held in Whippany, New Jersey, May 23-26, 1993. The chair of the Specialty
Conference has granted Lynne a complimentary registration which will save the District $350.
Attendance at the conference will allow District staff to exchange current technical information
regarding ultraviolet disinfection with disinfection experts from other parts of the country. Funds
are available in the Disinfection Facilities Improvements budget to cover the remaining costs of
this conference.
RECOMMENDATION: Authorize the attendance of Lynne Putnam, Senior Engineer for the
Planning Division, at the May 23-26, 1993 WEF Specialty Conference in Whippany, New Jersey,
at a cost of $950.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
AlE:
ROGER J. DOLAN
INITIATING DEPT./DIV.
j)AJ
Mf3
1302A-7/91
DRW
RAB
_._._--_._---'"-->--,--_._---~--~-------~-,._.._-_..._..._--+.__.~---------'.~~---_.__._._-------"-~.
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
PAGE 1
OF
1
BOARD MEETING OF
NO.
March 18, 1993
3. CONSENT CALENDAR r.
SUBJECT
REPORT SETTLEMENT OF CHRISTOPHER BOCCARD/
ALLSTATE INSURANCE CLAIM FOR DAMAGES
DATE
March 9 1 993
TYPE OF ACTION
INFORMATION
SUBMITTED BY
INITIATING DEPT./DIV.
Bonnie Allen, Risk Manager
Administrative/Risk Management
ISSUE: District policy requires that claim settlements between $5,000 and $10,000 are
approved by the General Manager-Chief Engineer and reported to the Board of Directors as an
information item.
BACKGROUND: On September 29, 1992, a District driver of a water tank truck misjudged a left
turn causing the trailer's rear wheels to cross the center line damaging the BMW stopped at the
signal light. The total claim settlement was $5,395.97 consisting of repair costs to Christopher
Boccard's 1992 BMW of $4,650.81, and replacement car rental of $745.16 while his vehicle
was being repaired. The District Risk Management Committee approved settlement of the claim.
RECOMMENDATION: Accept informational report on settlement of Christopher Boccard/Allstate
Insurance claim for damages. No further action is necessary.
INITIATING DEPT.lDIV.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
.
...J. ~
.~'.' ,
Centra~ Contra Costa Sanitary District
BOARD OF DIRECTORS
PAGE 1 OF 11
POSITION
PAPER
BOARD MEETING OF
March 18, 1993
NO.
5.
BIDS AND AWARDS a.
SUBJECT
AUTHORIZE AWARD OF CONSTRUCTION CONTRACT TO
D' ARCY & HARTY FOR THE NO DIG UPSIZING PROJECT,
DISTRICT PROJECT NO. 9558
DATE
March 12, 1 993
TYPE OF ACTION
AUTHORIZE AWARD
SUBMITTED BY
INITIATING DEPT./DIV.
Tom Godsey, Assistant Engineer
Collection System Operations
ISSUE: On February 17, 1993, sealed proposals were received and opened for the
construction of the No Dig Upsizing Project, District Project No. 9558. The Board of
Directors must authorize award of contract or reject bids within 50 days of the opening of
bids.
BACKGROUND: Collection System Operations Department (CSOD) has implemented a
comprehensive, multi-year program for the systematic replacement or renovation of small
diameter sewers in order to minimize the number of overflows, to limit the Quantity of
rainfall entering the collection system, to control future maintenance costs, and to improve
the level of service provided to the residents/ratepayers. This project contains
approximately 7,460 feet of 8-inch sewers, 340 feet of 12-inch sewers, 55 feet of 8-inch
creek crossing sewer pipes, and 3 new manholes. Also, lower laterals will be replaced to
near the easement edge or property line and they will be fitted with an overflow protection
device. There are 16 different project locations that are shown in Attachment 1.
Plans and specifications for the project were completed by CSOD staff, and this project was
advertised on January 25 and February 5, 1993. Six bids ranging from $673,380 to
$1,376,628 were received on February 17, 1993. A summary of bids is shown in
Attachment 2. The CSOD conducted a technical and commercial evaluation of the bids,
and concluded that the lowest responsible bidder is D' Arcy & Harty, for the bid amount of
$673,380. The engineers estimate is $950,000.
Miller Pipeline Corporation has submitted a letter of protest (Attachment 3). Staff has
reviewed the letter and found it to be without merit. Staff has invited Miller Pipeline
Corporation to address the Board regarding their concerns (Attachment 4).
The No Dig Upsizing Project is included in the 1992-93 CIB on pages CS-57 through 59.
A post bid/preconstruction cost estimate is shown in Attachment 5. The total project cost
is anticipated to be $1,002,000. An allocation of $ 924,000 from the Collection System
Program is needed to complete the project. The current balance of the Sewer Construction
Fund, minus unspent prior allocations plus projected dependable revenue, will be adequate
to fund this project. A funding summary is presented in Attachment 6.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
TG
BTT
JAL
INITIATING DEPT./DIV.
:AI
BTT
rJh
1302A.9/85
SUBJECT
AUTHORIZE AWARD OF CONSTRUCTION CONTRACT TO
D' ARCY & HARTY FOR THE NO DIG UPSIZING PROJECT,
DISTRICT PROJECT NO. 9558
POSITION PAPER
PAGE 2 OF 11
D"i\narch 12, 1993
Staff has determined that this action is exempt from the California Environmental Quality
Act (CEQA) under District CEQA Guidelines Section 18.2, since it involves repairs to
existing sewage facilities with negligible or no expansion of use. The Board of Directors'
approval of this action will constitute a finding of agreement with this determination unless
otherwise indicated.
RECOMMENDATION: Authorize award of the contract to 0' Arcy & Harty, the lowest
responsible bidder, in the amount of $673,380 for construction of the No Dig Upsizing
Project, District Project No. 9558.
13028-9/85
"
'.:i
'f
:,
ATTACHMENT 1
Page 3 of 11
//-.~
( LL '
\ I
"- ~
~-<,'..'-- ,-........ '1"_1 (~r-- -
, >0.' vUi~"--'Ur\L)
1'--::::
C/ --
Oy~
( "
0" /. -
,- ./ ',"
'{~/ -.'
o EJ-----, '
?~~ , '0/ --:,-~
'0 ./ . ,-,/
\.... /"---' ,'~
/"'---------~ '
" ~~~)
'\.. '.0/'
,,--..:.
MORAGA
&.
" u..;/
~:::'C'
-<0,
\ ,/ 1
\ Iv
, OrtA
\ \. I C'
\0
, \t'"
\'c ,(~ ,j
~ ,,_'V:
WALNUT
LREIEK
s t '~ <
V One ---;
a/IF'" \
- v D
..~ - /\i'"] J--.-
, . -1~'~
:-- \....' -
'-<_. I -, '
('\
'\
I
I
i,_
. ~r .V\ I
"\ AREA MAP ~
o , / / ~
__._..,u___
L \ c': f, I [' -,"--" ,'--:--
f J I~ i_
PROJEC,
I ( 1 :
, OAKLAND
~'~~
~..~~.
'. \\~
:' l/r\_l-;J
,-'
. PROJECT LOCATIONS
"
, t')
\
''\.
\
I
\
""
"'-.,
/~
\0-
NO Dl~ UPSIZING
DP X955B
1
Centrol Contro Costo
Soni,tory District'
. -"'.. ~,...;" ,'f-.'
ATTACHMENT 2
Central Contra Costa Sanitary
SUMMARY OF BIDS
Page 4 of 11
District
PROJECT NO.
LOCATION
9558 NO DIG UPSIZING
DATE ---1 .17-93
ENGR.EST. $-.95n,nnn
Through out Contra Costa - LAF,Wc',DAN,MTZ,ORT,DTA,PH
No. BIDDER BID PRICE
(Name, telephone & address)
1 D'arcy & Harty 415-586-4000 $673,380
425 Monterev St. . San Francisco CA
2 Delta Excavating, Inc 510-634-9600 $ 796,958
PO Box 1179, Brentwood, CA
3 Jardin Pipeline, Inc 510-782-3781 $ 905,604
PO Box 20817 Castro Vrlllpv CA
4 BRH Garver, Inc 713-921-2929 $ 1 ;089 ,772
5102 Lawndale St.. Houston. TX
5 Mountain Cascade, Inc. 510-373-8370 $ 1,131,916
c;c;c; . r.. T ~ r^
,
6 Miller Pipeline, Inc. $ 1,376,628.56
Hunters Point Shinvard #214 Box 104 San Francisco CA
$
..-
$
$
$
$
$
$
$
$
$
$
B IDS OPENED BY
Kffl Laverty
DATE .;( - /7- q3
SHEET NO. -1- OF -L-
Attaclmmt 3
Page 5 of 11
Miller
Pipeline
Corp.
Products and
Services Division
8850 CRAWFORDSVILLE RD.
P.O. BOX 34141 1F<<li;,I8r~U\YI~[Q'
INDIANAPOLIS, INDIANA 46234 FES 2 -; 1993
TELEPHONE: (317) 293-0278
CC('~
FAX: (317) 293-8502
February 19, 1993
Board of Directors
John B. Clausen, President
Central Contra Costa Sanitary District
5019 Imhoff Place
Martinez, CA 94553
RE: Protest Letter - To Be Placed Into Public Record
No-Dig Upsizing - District Project No. X9558 (Central Contra
_Costa sanitary District)
Gentlemen:
The purpose of this letter is to voice protest to unfair
advantage given to resident contractors offering yet unproven no-
dig technologies as a response to the above referenced bid. It
is evident that the District is seeking new technologies that
minimize environmental impact, certainly a proper attitude that
should be commended and encouraged. However, these techniques
are still new and have yet to become prevalent to the point
skilled people and equipment are stationed strategically across
the~S.~herefore, mobilization is a significant consideration.
1. I realize mobilization costs would not normally be of
consequence in a fairness evaluation, but in this bid it should
be as the District specified a test project for all bidders even
though XPANDIT, and perhaps others, had already been through the
evaluation process, paid that price once, and went on to
accomplish several thousand feet of work under contract. Now we
are being required to pay the price once more only this time we
must compete in a bid situation against a local contractor
offering an untried and unproven no-dig method against the
XPANDIT's tried and proven method, thus inflating our bid by
$30,000.00 plus dollars.
2. Contract specification may not be enforced. If this
statement were true, then this document could be considered
rigged in favor of local contractors or contractors that work
with Central Contra Costa Sanitary District or contractors that
did not attend the pre-bid meeting and know or think that the bid
document is not literal and that specifications are negotiable or
not enforced or that extra pay can be made available over and
\ -
Page 6 of 11
Board of Directors
Central Contra Costa Sanitary District
February 19, 1993
Page 2
above the bid price if the contractor claims ignorance in regard
to project specific information that would have been know if a
proper project evaluation had been made 9r the bidder had
attended the pre-bid meeting. Some items that a low bid
contractor that did not attend the pre-bid meeting might attempt
to use to claim extra payor obtain contract completion time
extension without paying the liquidation damages (SC-7 $750.00
per day) .
The contractor might say and we would expect Central Contra Costa
Sanitary District to respond as follows:
A. I did not know that work was limited to four active work
sites at a time (IF-3).
B. I did not know work hours are restricted to 9:00 am to
4:00 pm - five days per week (CG-43) or that I could not launch
pipe if the reach could not be completed by 4:00 pm and no
guarantee of any exception to this rule was made by C.C.C.S.D.
(IF-3) .
These two reauirements alone added 46 workinq days beyond the 180
calendar day limit set (SC-4) and also added $115.000.00 to the
proiect cost. Unless the contract document is not enforced or is
neqotiated by a claim of iqnorance all bids should reflect this
reauirement and 1F-3 should be enforced without additional
consideration.
-
.....c.. ...I- did not know that this proj ect had cast iron pipe in
it. My equipment cannot break cast iron (very fast or at all).
I need more money and time (Volume 1, Section 10-DP#9558, Part
111-17). Our evaluation of the documents and sites indicate that
this proiect has a siqnificant amount of cast iron pipe to be
burst and upsized. We reflect this in our pricinq and expect
that all bidders had the same opportunity and responsibility to
attend the pre-bid meetinq. evaluate and discover this
information. Therefore. no extra compensation to any bidder is
justified.
D. I did not know it was my responsibility to locate and
verify active laterals. Therefore, I need more money and time or
C.C.C.S.D. should do it (1A-14). This is a siqnificant cost time
identified and included in our bid. No extra payor assistance
by the utility should be considered.
E. I did not know we had to internally debead the pipe. We
need more time and money to do this or C.C.C.S.D. could violate
their agreement not to disclose Miller's proprietary method for
accomplishing this task and help. (151600 Plastic Pipe, Page 15-
1.. ,~
Page 7 of 11
Board of Directors
Central Contra Costa Sanitary District
February 19, 1993
Page 3
7. Volume 2). Miller can do this and our bid reflects this task.
Therefore, no extra payor assistance by the utility should be
considered.
F. I did not know that I had to obtain and pay for permits
and city inspection. Therefore, I need more money or C.C.C.S.D.
should do it for me at no cost (IF-9). Miller's bid reflects
accomplishment of this task; therefore. no extra pavor
assistance bv C.C.C.S.D. should be considered.
Protest Summary
Miller Pipeline Corporation is a responsible company with a
history of submitting responsive and competitive bids. When we
were made aware of the significant spread of bid responses to the
bid request for Project No. X9558, we were dismayed and could not
understand how we and others could be so far away from the lower
responsive bidders. Upon investigation, we found that bidders
that work for C.C.C.S.D. on a more frequent basis or did not
attend the pre-bid meeting had a proportionately lower bid
(relatively) and, conversely those that do not work for
C.C.C.S.D. often and did attend the pre-bid meeting tend to have
submitted higher bids.
Upon further investigation, we were told that C.C.C.S.D. bid
specifications were not to be taken literally and could be
negotiated after award at least in some of the areas set forth
above. If this is true, it gives the familiar contractors a
def~te-advantage over the contractor that does not work for
C.C.C.S.~. often. It would be easy to look at or audit a few
contracts to see if any of them allowed any exception to
specifications related to the examples given in this protest
letter. If our concerns are unwarranted, and contract
performance is consistently within the time allocated by the
contract document, projects are completed consistently for the
amount bid (without extra payment), and all other specifications
are held firm, then we withdraw our protest. If you find
substance to our expressed concerns, then we ask that enforcement
of contract documents be upheld as bid or the option to negotiate
specifications and price after award should be made known to all
potential bidders before bids are submitted. I also believe
mandatory pre-bid meetings help ensure that bidders are informed
and bids are responsive to specifications.
In this instance, all bids should be negated.
Page 8 of 11
Board of Directors
Central Contra Costa Sanitary District
February 19, 1993
Page 4
We value Central Contra Costa sanitary District as a customer and
will continue to look for opportunities to work with you. In
testimony of this fact, we invested more than 220 man hours and
over $12,000.00 to prepare this bid, not to mention the man hours
our potential subcontractors invested at our request.
Thank you for your attention to this matter.
Respectfully yours,
#~^
Henry E. Topf, ~.
Vice President of Operations
HET:elb
cc: Roger J. Dolan
John Larson ./
M.C. Jardim, Inc.
Jim Nicholson
Collins Orton
-...-
Attaclmmt 4
Page 9 of 11
Central Contra Costa Sanitary District
fo'1(I)IIi:il"BCJ:illt_ _it:);_"'1(I)~Jm&.Mr1:1
IW(;/oRJ I}(if.l\
(;(,IJ('ral.\JalJ()(j,'/
('hiefFnuillc\'1
I\E:\TO'\ L ,,11.,'/
Cuunsel for the Distric!
(.110) ,4.'18-],1::0
March 10, 1993
JOl'CE E, NIIIPIIl'
Secrelw:lf o( Ihe nisl/iel
Mr. Henry E. Topf, Jr.
Vice President of Operations
Miller Pipeline Corporation
8850 Crawfordsville Rd.
P.O. Box 34141
Indianapolis, Indiana 46234
- -.-
Dear Mr. Topf:
The Central Contra Costa Sanitary District has received your letter dated February 19,
1993 regarding the bid results of the No Dig Upsizing project (District Project No. 9558).
The Board of Directors is scheduled to award the construction contract for this project at
its meeting on March 18, 1993 at 3:00 p.m. You are invited to address your concerns
in person at that time, should you so desire.
Sincerely,
I
.-1
Joh'
CoB 'I:.
,~/
JAL:sm
rson, Manager
on System Operations Department
cc: B. Than
File: DP 9558
c: \prog r ams\d p95 58\bid restt, btt
Iii!+. Recvcled Parer
cso
Page 10 of 11
ATTACHMENT 5
NO DIG UPSIZING PROJECT
DISTRICT PROJECT NO. 9558
POST-BID PRECONSTRUCTION COST ESTIMATE
ITEM DESCRIPTION TOTAL % OF
CONSTRUCTION
. COSTS
1 Construction Contract $673,380
2 Contingency (at 15%) $101,620
Subtotal $775,000 100.0
3 Force Account
M anagement/ Administration $30,000 3.9
Inspection $70,000 9.0
Surveying $ 5,000 0.7
Engineering $ 5,000 0.7
Legal $ 5,000 0.7
As-Builts $ 2,000 0.3
Subtotal $117,000 15.1
4 Miscellaneous
Permit/City Inspection $30,000 3.9
Testing $ 13,000 1.7
Community Relations $ 5,000 0.7
Subtotal $48,000 6.3
5 Prebid Expenditures $ 62,000 8.0
6 TOTAL PROJECT COST $1 ,002,000 129.3
7 Funds Previously Authorized $ 78,000
8 Allocation Funds Required to $ 924,000
Complete Project
6
ATTACHMENT
PROJECT FUNDING SUMMARY
FOR THE PERIOD
Page 11 of 11
3/5/93-4/5/93
SEWER CONSTRUCTION FUND BALANCE
AS OF 2/28/93
MINUS.UNSPENT PRIOR ALLOCATIONS
PLUS DEPENDABLE REVENUE
66,132,509
(37,612,672)
5,672,118
34,191,955
+-------------+
34,191,955 > I $ 924,000 I (ALLOCATION REQUIRED)
+-------------+
........ ~~
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
PAGE 1 OF 4
BOARD MEETING OF
March 18, 1993
NO.
5. BIDS AND AWARDS b.
AUTHORIZE AWARD OF PURCHASE ORDER FOR FURNISHING
ONE GAS TURBINE/GENERATOR TO SOLAR TURBINES,
INCORPORATED
DATE
March 15, 1993
SUBJECT
TYPE OF ACTION
AUTHORIZE AWARD
SUBMITTED BY
David J. Reindl, Associate Engineer
INITIATING DEPT.lDIV.
Plant Operations Department
ISSUE: On March 3, 1993, sealed bids for Bid Request No. B0243T/R1 for furnishing one gas
turbine/generator and switchgear were received and publicly opened. The Board must award the
contract to the lowest responsible bidder or reject all bids within 90 calendar days of the opening
of bids.
BACKGROUND: On November 10, 1992, the Board declared the bids non-responsive and rejected
all bids to furnish one 3,300 kW gas turbine/generator and switchgear for the Cogeneration
Project. Because both bidders conditioned their bids with qualifying language that substantially
changed the project from the contract documents, District Counsel advised staff to revise the bid
request and rebid the project. The Bid Request was revised, and mutually acceptable revisions
were incorporated into the Commercial Terms and Conditions and a five-year Maintenance
Agreement was added.
On February 19 and 24, 1993, the Notice to Bidders was publicly advertised inviting sealed bids
for furnishing the turbine generator and associated equipment. Two bids were received and
publicly opened on March 3, 1993. Both Solar Turbines, Incorporated and U.S. Turbine rebid the
project. A Tabulation of Bids is attached listing the Standard (Bid Item 1 A) and Alternate Turbine
Control Package (Bid Item 1 B) for both bidders. Both bids contain minor technical variances
intended to clarify their bid; however, both are considered commercially and technically responsive.
The Alternate Control System (ModiCon programmable logic controller) is recommended because
it is consistent and compatible with the Equipment Standards throughout the Treatment Plant. The
delivered total bid amount of $2,113,841 from Solar Turbines, Incorporated is slightly above the
Engineer's estimate of $2,085,000 and is the recommended equipment alternate. The low bid in
November, 1992 was U.S. Turbine at $1,994,000. The five-year Maintenance Agreement in the
amount of $150,000 per year was not included in the bid price. This agreement will be entered
into prior to the expiration of the warranty period.
An allocation of $2,200,000 from the Treatment Plant Program is needed at this time for the
equipment purchase. The current balance of the Sewer Construction Fund, minus unspent prior
allocations plus projected dependable revenue, will be adequate to fund this project. A funding
summary is presented in Attachment B. The project is described on page TP-44 of the Fiscal Year
1992-93 Capital Improvement Budget.
RECOMMENDATION: Authorize the award of the purchase order to Solar Turbines, Incorporated
for $2,113,841 as the lowest reso lnsihl irlrlp.rb
REVIEI ED AFJa (J~N ED FOR BOARD ACTION
ATTACHMENT A
Page 2 of 4
:
-
:
N
~
~ c::( 1.0 L.{) 0 1.0 ~
~ u . L.{) (V') 0 L.{)
....... CT'l 0 0 CT'l C
~....... ~ . 0:::
i= -0 - CT'l 0 L.{) <:::t ~
~ (V') I-- (V') ....... ....... L.{)
~ CT'l (V') ....... N ....... N
::) tJj U I <:::t . ~ ~ "
z v. ~ (V') N ~ ~ N ~
~ W I 0 -
as = Ci (V') co
.
.
:
0:::
c:::c
W
~
:c ~
u
I--
........ g >< OJ ....... 0 OJ .......
::s: I-- . L.{) 1.0 OJ (V') <:::t
V) ....... 0 r--. 0 ....... OJ
~ 0::: ..
Cl ~ - N L.{) OJ 0 (V')
:z: ~ (V') I-- OJ OJ N ....... .......
c::( t CT'l (V') : ~ ~ 0 .......
I <:::t "
0::: :7 ~ (V') N ....... ~ N ~
0 I 0 - -
I-- :c (V') co
c:::c
0:::
w
:z:
w
~ .
w
:z:
........
co
0::: .
:::>
I--
zV)
QC:::C ~
li:~ .
5 c: 0
en . I--
w V)
0 Cl i:: Cl .. - w . .
.t. ~ :::>E :z: . :z: :z: ........... 0::: ~ N N
d 0 c:::c c:::c u w c:::c
~ a: ill e :z: If g : C5
w 8 UJ UJ CL ~ ---l ---l 0::: o<:l o<:l
!< a: ~ I- ..0 -< 0::: c:::c 0::: 0... ---l 0
:z: e ~ ~ a: ~
~ ~ d -< ~ 0 ~ 0 w I-- c:::c co
~ ..: ~ I-- I-- :z: V) V) w ....... .......
~ c:::c ~ >< c:::c 0 >< I--
~ 0::: c:::c 0::: U c:::c ::E LL.. ........ V) V)
w I-- w ........ I-- 0 0 V) ::E ::E
~ :z: ---l :z: Cl 0::: W W
-0 W ;;:t &!? w 0 &!? LL.. W V) I-- I--
-0 ~ ~ Cl ~ ::E U - ........ ........
'r- a: . --.: ~I ........ ........ ...oJv I-- c:::c I--
6::: w 0::> co w OJ V) ---l U
en cu ~ :z: 0::: :z: 0::: 0 0... ........ .. ..
e ~ ........ ~ ~ w ........ c:::c ~ U 0::: ---l ---l
r-- c:::l :z: I-- co w :z: 0::: I-- c:::c c:::c
en ..Cl .... e - 0::: ~ ........ c:::c 0::: ~ ........ I-- 0 V) I-- I--
U. 'r- 3 :::> ~ Cl :z: :::> :c Cl :c ........ 0 0
0 III I-- :::> 0::: I-- U :::> ~ I-- Cl I-- I--
g I-- ---l W I-- ---l ........ :z: I I
Z V) ........ U I-- V) ........ u w c:::c w c:::l c:::l
0 ~ c:::c :3: :z: ---l c:::c :3: :z: 0::: ---l :c :::> :::>
!;t ~ ~ V) ........ c:::c ~ V) ........ LL.. 0... I-- V) V)
.~
0::: ~
-I ~ -
::) f ~ /'0 +l
en w /'0 ---l
~ OJ co w
~ ..~ ::: ~ . ....... ....... .......
e 0 >-
; ~ aJ
-1l e -
UJ
~a i ~ t . . .
UJ c:::c co .
a: If ....... ....... N
~.
J;
~
o
CJ'>
........
N
ATTACHMENT A (continued)
Page 3 of 4
:
.
N
~ ~
L..LJ ~
Z - ~ ~
I-< . 0 0
i o:l 0'\ N "
~ 0:: ~
N ~ 0 ~
I- L{') L{')
2 : N 0 ..-
:J ~ Iv . "
Z 0 (V') ~
~ w
i I=" <Xl ~
-
~-
.
.'
0:::
e::(
L..LJ
C!J (5
:c
u L..LJ : ~
I- Z
I-< I-< 0 <Xl ~
3: co . L{') (V')
V> Ie:: ~ -
-
Cl I~ 0 0 ~
Z 0 ~
e::( 0::: : 0 r--.
e::( "
0::: .....J 0 N ~
0 0 L{') --
l- V> -
~
L..LJ
Z
L..LJ
C!J .
L..LJ
Z
I-<
co
0:::
~
I-
z V> .
Q e::( (V') .
..... C!J . (V') .
0- o<:l e::( co
5 - o<:l -
en .
w . L..LJ N ::E . ::E
0 U L..LJ N L..LJ
~ ~ 2 :z: . Z ::E " l- I-
ei 0 e::( 0::: e::( I-< co I-<
a: ffi :z: ~ 3 -
a: w . Z L..LJ - -
w 8 w a.. ~
< a: ~ 0- eD '" L..LJ I- Z Z
:z: 0 ~ g a: ffi
~ ~ ei ... ~ l- V> 0 V> 0
2 ..: ~ Z I- ::E ::E
~ I-< Z L..LJ >< L..LJ ><
e::( L..LJ l- e::( l- e::(
::E ::E I-< l- I-< I-
,...: L..LJ
l..1... L..LJ l..1... &S?- l..1... &S?-
O U 0::: 0 0
. ::E C!J ~I<t ~l<l
en I- ::5 e::( L..LJ <Xl L..LJ <Xl
V> ~ ~
e ~ 0 0::: .....J C!J .....J C!J
u l- e::( e::( Z e::( Z
CD 0 - U L..LJ > I-< > I-<
U. >- e::( >- Cl Cl
0 .....J 0::: .....J ~ .....J ~
0::: I- L..LJ e::( .....J e::( .....J
Z ~ z > I- U I- u
~ 0 L..LJ 0 I-< 0 Z 0 Z
~ >- U l..1... l- I-< l- I-<
~
~ r:.; ....I
::>> ~ to
CD L..LJ
\ ~ .. ~ . -
0 rD ffi
:z: filt-
~ i
~ ~ t . . .
w e::( co
a: a: If (V') o:::t o:::t
lil'
j;
~
o
.0'\
........
N
Page 4 of 4
ATTACHMENT B
PROJECT FUNDING SUMMARY
FOR THE PERIOD
3/5/93-4/5/93
SEWER CONSTRUCTION FUND BALANCE
AS OF 2/28/93
MINUS.UNSPENT PRIOR ALLOCATIONS
PLUS DEPENDABLE REVENUE
66,132,509
(37,612,672)
5,672,118
------------
34,191,955
+-------------+
34,191,955 >1 $2,200,000 1 (ALLOCATION REQUIRED)
+-------------+
..
~ Central ~~~~~ g~~fR~~~g'~~ District
PAGE 1
OF 10
POSITION
PAPER
BOARD MEETING OF
March 18, 1993
NO.
5. BIDS AND AWARDS c.
DAiQiarch 9, 1993
SX~PWOVE RELIEF OF BID REQUEST FROM PRESTON
PIPELINES, INC., AND AUTHORIZE AWARD OF A
CONSTRUCTION CONTRACT TO D. W. YOUNG
CONSTRUCTION COMPANY, INC., FOR THE LEGION
COURT SEWER REPLACEMENT PROJECT, D.P. 4910
TYPE OF ACTION
AUTHORIZE AWARD
SUBMITTED BY
Curtis W. Swanson
INITIATING DEPT./DIV.
Engineering Department!
Infr s ru ure Division
ISSUE: On February 23, 1992, sealed bids for the construction of Legion Court Sewer
Replacement Project, D.P. 4910, were opened. The Board of Directors must authorize award
of the contract or reject bids within 50 days of the opening of bids. The Board of Directors must
decide whether or not to grant a relief of bid request.
BACKGROUND: The sewers in the vicinity of Legion Court, Acalanes Road, and Revere Road
in Lafayette (see Attachment 1) are deteriorated and require a high level of maintenance.
Overflows due to root intrusion and flat sewer slopes have occurred. Access for maintenance
is difficult because some of the sewers are located in backyard easements with steep terrain.
As part of this project, approximately 3,100 feet of new 8 and 1 O-inch sewer will be constructed
in public and private roads. Approximately 2,700 feet of existing 6-inch sewers in backyard
easements will be abandoned and approximately 1,500 feet of house laterals will be relocated
to allow for abandonment of the existing deteriorated sewers.
Plans and specifications were prepared jointly by District staff and Terry Haefner, P.E. The
project was advertised for bids on January 26 and February 2, 1993. The engineer's pre-bid
estimate for construction was $710,000. Eighteen bids ranging from $368,138 to $777,700
were received on February 23, 1993. A summary of bids is presented in Attachment 2. On
February 26, 1993 by facsimile and March 1, 1993 by letter, the District received a request for
relief of bid from the apparent low bidder Preston Pipelines, Inc., of Milpitas, California
(Attachment 3). The request cites an arithmetic error in preparing their bid.
Under California Public Contract Code (Section 5103), a bidder may request relief of bid within
five days of bid opening in the event of a clerical or arithmetic error in preparing the bid proposal.
The law is stringent with regard to relief from bids and allows relief to be granted by the
awarding authority only under specific circumstances. Specifically, the law states that:
"The bidder shall establish to the satisfaction of the court that:
(a) A mistake was made.
(b) He or she gave the public entity written notice within five days after the
opening of the bids of the mistake, specifying in the notice in detail how the
mistake occurred.
(c) The mistake made the bid materially different than he or she intended it to be.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
1302A-9/85
CWS
RAB
fCZ ENG,
ROGER J. DOLAN
SUBJECT
APPROVE RELIEF OF BID REQUEST FROM PRESTON
PIPELINES, INC., AND AUTHORIZE AWARD OF A
CONSTRUCTION CONTRACT TO D. W. YOUNG
CONSTRUCTION COMPANY, INC., FOR THE LEGION
COURT SEWER REPLACEMENT PROJECT, D.P. 4910
...................................................................................
...................................................................................
!!IIIIII'IIIIII~:IIIIII!
PAGE
DATE
2
OF 10
March 9, 1993
(d) The mistake was made in filling out the bid and not due to error in judgment
or to carelessness in inspecting the site of the work, or in reading the plans or
specifications."
The arithmetic error claimed by Preston Pipelines is the omission of costs for paving, imported
backfill, and other restoration of the trench section after sewer installation. According to Preston
Pipeline's representatives, the error was made on the internal work sheets used to compile
construction costs for transfer to the formal bid proposal form that was submitted to the District.
Preston Pipelines was using a new computer spreadsheet program to prepare its bids. The
computer program calculates the quantity of excavation and imported backfill, asphalt paving,
and other miscellaneous restoration required. Unit costs and quantities are listed for materials,
equipment, and labor based on which the program computes a total cost. Preston Pipelines
alleges that due to a software error, the imported backfill, paving, and other restoration costs
were not accurately compiled within the spreadsheet program. After reviewing the
documentation used for preparation of the bid and discussions with Preston Pipelines'
representatives, it appears to staff and District Counsel that Preston Pipelines' explanation of an
arithmetic error is plausible and valid.
As part of the technical and commercial evaluation of Preston Pipelines' bid, District staff
determined that Preston Pipelines had failed to list a subcontractor for pressure grouting. When
this was brought to Preston Pipelines' attention, representatives stated that this specific
subcontractor had been inadvertently omitted in completing their bid. This is a further
complication with the bid but will be eliminated if relief of bid is granted.
The Engineering Department conducted a technical and commercial evaluation of the bids and
concluded that, in the event that Preston Pipelines, Inc., is relieved of its bid, the second low
bidder, D. W. Young Construction Co., Inc., is the lowest responsible bidder for the bid amount
of $467,370.
The Legion Court Sewer Replacement Project is included in the 1992-93 CIB on pages CS-25
and 26. A post bid/preconstruction cost estimate is presented in Attachment 4. An allocation
of $736,200 from the Collection System Program is needed to complete the project. The
current balance of the Sewer Construction Fund, minus unspent prior allocations plus projected
dependable revenue, will be adequate to fund this project. A funding summary is presented in
Attachment 5. District staff will administer the contract and provide inspection services.
Resident engineering services will be provided by Montgomery Watson Consultants (formerly
James M. Montgomery Engineers) based on satisfactory performance on other recent
construction projects.
13028-7/91
SUBJECT
APPROVE RELIEF OF BID REQUEST FROM PRESTON
PIPELINES, INC., AND AUTHORIZE AWARD OF A
CONSTRUCTION CONTRACT TO D. W. YOUNG
CONSTRUCTION COMPANY, INC., FOR THE LEGION
COURT SEWER REPLACEMENT PROJECT, D.P. 4910
/11111111111111/:1/11111/:
PAGE
DATE
3
OF 10
March 9, 1993
Staff has determined that this project is exempt from the California Environmental Quality Act
(CEQA) under District CEOA Guidelines Section 18.2, since it involves minor alterations to
existing sewer facilities. The Board of Director's approval of this project will constitute a finding
of agreement with this determination unless otherwise indicated.
RECOMMENDATION: Approve the request for relief of bid from Preston Pipelines, Inc., and
direct staff to return Preston Pipeline's bid bond. Authorize award of contract to D. W. Young
Construction Company, Inc., the lowest responsible bidder, in the amount of $467,370 for the
construction of the Legion Court Sewer Replacement Project, D.P. 4910.
13028-7/91
I
,
, E I
Hidden 1
I
~
N
~
ORINDA
c:
Cll
1)
Ii
IS>
cr
....
"
IS>
C;
....
"
c-
o
o
"
Cll
+'
'-
L
1)
"
(\J
L
III
~
"
. .
1;"'-'
I-:~
~I::;
-.I'
.>-
>-11-
I-'U
U;W
<(.1-
O'/-
zlW
0:::'>-
0.<(
I~
:-.1
.
.....'"\
- PROJECT LOCATION
Centrol Contro Casto
Sanitary District
"
Nido
?--d
Ran ch
DIABLO
Va II ey
LA FA VETTE
C\'Iopel
Vo;,
Dr01)t0
.
.
\
.-
1
.
.
Corte Rinaldo
I b
. ;:,.
. 55
-..-..-..-..-..-..
"I
-0
0:::
o 200 400
I
600 800
FEET
ATTACHMENT
LEGION COURT SEWER PROJECT
DISTRICT PROJECT 4910
1
ATTACHMENT 2
Central Contra Costa Sanitary District
SUMMARY OF BIDS
PROJECT NO. X4910
LEGION COURT
DATE 2/24/93
ENGR.EST. $710.000
LOCATION LAFAYETTE
# BIDDER BID PRICE
(Name, teleohone & address)
1 Preston Pipelines, Inc. $368,138
151 Bothelo Avenue, Milpitas CA
2 D. W. Young Construction Company, Inc. $467,370
140-A Town & Country Dr., Danville CA 94526
3 L. J. Krzich Pipeline Engineering Co., Inc. $470,056.03
326 Phelan Avenue, San Jose CA 95112
4 Hogue Construction $486,815
701 Arata Lane, Windsor CA 95492
5 McGuire & Hester $496,580
9009 Railroad Avenue, Oakland CA 94603
6 D. E. Bianchini, Inc. $497,324
P. o. Box 2204, San Ramon CA 94583
7 North Bay Construction $506,650
431 Payran Street, Petaluma CA 94953
8 Manual C. Jardim, Inc. $529,470
P. o. Box 677, Union City CA 94587
9 Andes Construction. Inc. ... $547,756
5305 E. 12th Street, Oakland CA 94610
10 P & M Pipelines (415) 759-7069 $549,325
2440 Taraval Street, San Francisco CA 94116
11 Mountain Cascade, Inc. $596,105
P. O. Box 50501 Livermore CA 94550 ."'in_
12 R & E Construction $607,305
130IA Homestead Avenue, Walnut Creek CA 94598
13 Pacific Underground Construction, Inc. $609,955
1817 Stone Avenue, San Jose CA 95125
14 Harty Pipelines, Inc. $611,400
4085 19th Avenue, San Francisco CA 94132
15 Silva's Pipeline, Inc. $689,130
P. o. Box 751, Hayward CA 94543
BIDS OPENED BY /s/ Joyce E. Murohy
DATE
2/23/93
SHEET NO. -1- OF -1-
Central Contra Costa Sanitary District
SUMMARY OF BIDS
PROJECT NO.
LOCATION
X4910
LAFAYETTE
LEGION COURT
DATE 2/24/93
ENGR.EST. $710.000
# BIDDER BID PRICE
(Name, telephone & address)
16 J. Foster Excavating, Inc. $716,500
1020 Shannon Court, Livermore CA 94551
17 Jardin Pipeline, Inc. $731,862
P. O. Box 20817, Castro Valley, CA 94546
18 Palma General Engineering $777,700
1180 Horizon Drive, Ste. E, Fairfield CA 94533
BIDS OPENED BY /s/ Joyce E. Murohy
DATE
2/23/93
SHEET NO. -Z- OF -Z-
."."
~_.._._.__ ,._ '__0 "~___,_,._,,,"'." ...~_..__u,,_,__,_"._..__._"______.._.____.__._.__,_._..__.__.__.,___,...~.__.._~"_,.,._..,_. _, ._.'" ,___"_",_",,,_,,_,_",,~,_,___'__'.. ,___._,_____"___,__~._'"'_..__"__~
ATTACHMENT 3
CARR, MCCLELLAN, INGERSOll, THOMPSON & HORN
PR.OPESSlONAL COR.POllAnON
ALBEllT J. HOllN
DAVID C. CARR
ARTHUR H. BllEDENBECK
NOllMAN I. BOOK. JR.
OUENTIN L. COOK
I(OBERT A. NEB RIG
MAlUON L. BROWN
RlCHAllD C. BEllllA
L MICHAEL TEllEEN
LAGE E. ANDERSEN
KEITH P. BARTEL
MA1lK A. CASSANEGO
LAURENCE M. MAY
PAUL V. SIMPSON
DAVID M. McKIM
MICHAEL J. McQUAID
PENELOP~ C. GtlEENBERG
ROBERT W. PAYNE
KRlSTI COlTON SPENCE
MARK D. HUDAK
~AMES R. CODY
OllDAN W. aEMENTS
AUL A. AHERNE
EDWAllD J. WIllIG III
SARAH J. l>iBOlSE
W. GE01lGE WAlLES
llONALDF.GAllRITY
CAllOL B. SCHWARTZ
LAUllA E. INNES
LORI A. LUTZKER
ATTORNEYS AT LAW
216 PARK ROAD, POST OFFICE BOX 513
BURUNGAME. CAUFORNIA 94011-0513
TELEPHONE (415) 342-9600
FACSIbULE(415) 342-7685
February 26, 1993
STEVEN D. ANDERSON
LINDA R. BECK
JAMES F. BLOOD
lCENNETH M. HURLEY
JEllEMY W. KA. TZ
JANETI'E G. LEONIDOU
CAllOL L. MUSSMAN
TERESE M. llADDIE
USA H. STA.II'Elll
MOIRA C. WALSH
JOHN T. WAU'HlER
1>. KENT WESTERBERG
A. ROBERT llOSIN
SPECIAL COUNSEL
SAN FllANClSCO OFFICE
TWENTY. SECOND FLOOR
ONE CALJllOllNIA STREET
SAN FllANClSCO
CALJllOllNlA 94111
TELEPHONE (415) 362-1400
fACSIMILE (415) 362-5149
VZA PACSZXZLB. CBRTZPZBD KAZL AND PZRST CLASS KAZL
RECEIVED
MAR 1 '993
Roger J. Dolan
General Manager
Central Contra Costa Sanitary District
4019 Imoff Place
Martinez, CA 94533
cc:cso
AC:.:Nl:ilIATION
Re: Central Contra Costa Sanitary District Project
Legion Court Sewer Renovation Project No 4910
Dear Mr. Dolan:
Please be advised that this office represents Preston
Pipeline, Inc. in connection with the above-referenced project.
Preston hereby requests that it be relieved of its bid on the
above-referenced project. Preston's bid contains two
mathematical errors. Enclosed, please find copies of the bid
sheets of Preston Pipeline. You can see that the items included
under the title "Material Keyed to Pipe" were not properly added
and included in the total lump sum price. Further evidence of
the mathematical error is the substantial difference in the bid
submitted by Preston and the others submitted. The unit costs
generated by Preston were much lower than the correct costs due
to the failure to add the amounts for all sub items into the unit
price.
This mistake was not a result of an error in judgment or of
carelessness, but was a mathematical error.
Preston Pipeline hereby asks that it be relieved of its bid
and that its bid bond be returned.
Roger J. Dolan
February 26, 1993
Page 2
If you have any questions, please do not hesitate to contact
the undersigned or Gary A. Menges, Vice President of Preston
Pipeline.
Very truly yours,
~ A. A~f'$-
Paul A. Aherne
PAA: jth
Enclosures
cc: Preston Pipelines, Inc.
Attn: Gary A. Menges
11375.1\dolan.ltr
ATTACHMENT 4
LEGION COURT SEWER REPLACEMENT
DISTRICT PROJECT NO. 4910
POST -BID/PRECONSTRUCTION ESTIMATE
ITEM DESCRIPTION TOTAL PERCENT OF
ESTIMATED
CONSTRUCTION
COST
1 Construction Contract $ 467,370
2 Utility Relocation (PG&E) 20,000
3 Permanent Property Rights 1 ,000
4 Contingency @ 25 % 1 116,830
SUBTOTAL 584,200 100.0
5 Construction Management/Inspection 69,000 11.8
6 Consultant/Professional Services 49,000 8.4
7 Miscellaneous 34,000 5.4
SUBTOTAL $152,000 26.0
8 Pre bid Expenditure
. Right of Way/Utility Location 22,000
. Design/Bidding 146,000
SUBTOTAL 168,000 28.8
9 Total Project Cost Estimate $ 904,200 154.8
10 Funds Authorized to Date $ 168,000
1 1 Total Allocation of Funds needed to $ 736,200
Complete Project
1A 25% contingency is proposed due to the uncertainty associated with the extent of lateral
reconstruction and variable ground water levels.
ATTACHMENT 5
LEGION COURT SEWER REPLACEMENT
DISTRICT PROJECT NO. 4910
PROJECT FUNDING SUMMARY FOR THE PERIOD 3/5/93-4/5/93
Sewer Construction Fund Balance as of 2/28/93
Minus Unspent Prior Allocations
Plus Dependable Revenue
$66,132,509
(37,612,672)
5.672, 118
$34,191,955
$34,368,971 > $736.200 (ALLOCATION REQUIRED)
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
PAGE 1 OF 3
BOARD MEETING OF
March 18, 1993
NO.
7. ADMINISTRATIVE a.
ADOPT AN ORDINANCE AMENDING THE DISTRICT'S
CONFLICT OF INTEREST CODE
DATE
March
TYPE OF ACTION
SUBJECT
ADOPT ORDINANCE
AMENDING CONFLICT OF
INTEREST CODE
SUBMITTED BY Joyce E. Murphy
Secretary of the District
INITIATING DEPT.lDIV.
Administrative
ISSUE: A need exists to update the District's Conflict of Interest Code to conform to a
recent change in the filing date approved by the Contra Costa County Board of Supervisors, the
code reviewing body.
BACKGROUND: In addition to their elected positions, many elected officials serve on County
boards, commissions, and committees and are required to file periodic statements of economic
interests during the month of April. The current filing period for the District's Conflict of
Interest Code is February. In an effort to consolidate the filing period for the annual statements
of elected and non-elected designated filers to one time, on December 10, 1992, the Contra
Costa County Board of Supervisors amended all local Conflict of Interest Codes pursuant to
Government Code Sections 87302 and 87306 et seq. as follows:
"Annual statements shall be filed during the month of April and no later than April 30
by all designated employees. Such statements shall cover the period of the preceding
calendar year."
RECOMMENDATION: Adopt the attached ordinance amending the Central Contra Costa
Sanitary District Conflict of Interest Code to conform to the change in filing date approved by
the Contra Costa County Board of Supervisors.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
,~
INITIATI,NG DEPT.lDIV.
1302A-7/91
EM
ORDINANCE NO.
AN ORDINANCE OF THE CENTRAL CONTRA COSTA SANITARY DISTRICT
AMENDING SECTION 2.20.040 D. OF THE DISTRICT CODE
REVISING OF THE FILING DATE OF ANNUAL STATEMENTS OF ECONOMIC INTERESTS
The Board of Directors of the Central Contra costa Sanitary District does hereby ordain as
follows:
SECTION 2.20.040
PLACE AND TIME OF FILING
Section 2.20.040 of the Central Contra Costa Sanitary District Code is hereby rev!sed and
amended to read as follows:
D. Annual statements shall be filed during the month of April and no later than April
30 by all designated employees. Such statement shall cover the period of the preceding
calendar year.
This ordinance shall be an ordinance and general regulation of the District and shall be
published once in the Contra Costa Times, a newspaper of general circulation, published and
circulated within the Central Contra Costa Sanitary District and shall be effective upon the
expiration of the week of publication.
PASSED AND ADOPTED by the District Board of the Central Contra Costa Sanitary District this
day of
, 1993, by the following vote:
AYES:
Members:
NOES:
Members:
ABSENT:
Members:
President of the Board of Directors,
Central Contra Costa Sanitary District,
County of Contra Costa, State of California
COUNTERSIGNED:
Secretary of the Central Contra
Costa Sanitary District, County
of Contra Costa, State of California
Approved as to Form:
Kenton L. Aim
District Counsel
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
PAGE
OF
1
BOARD MEETING OF
NO.
March 18, 1993
9. LEGAL/LITIGATION a.
SUBJECT
DENY CLAIM FOR PROPERTY DAMAGE FROM
ROBERT C. KENNEDY
DATE
DENY CLAIM
SUBMITTED BY
INITIATING DEPT.lDIV.
Bonnie Allen, Risk Manager
Administrative/Risk Management
ISSUE: Robert C. Kennedy has filed a claim for $1,800 alleging that his vehicle was damaged
by a District vehicle. Claim denials require action by the Board of Directors.
BACKGROUND: Claimant's 1976 Pontiac vehicle was parked at the curb in front of his
residence at 1811 Evergreen Avenue, Antioch. It was struck and damaged by an unknown
vehicle. Investigations by the Antioch Police and by District representatives were unable to
identify the driver or vehicle causing the damage. A neighbor witnessing the accident at
approximately 5:30 a.m. on December 6, 1992, stated that the damage was caused by a blue
Ford pickup, not a District vehicle.
RECOMMENDATION: Deny the claim by Robert C. Kennedy for property damage of $1,800 and
refer to staff for further action as required.
INITIATI,NG DEPT./DIV.
1302A-7/91
BA
PM
KLA
C:\WP51 \BdDir\Kennedy.PP