HomeMy WebLinkAboutAGENDA BACKUP 11-14-95
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
PAGE
OF 1
BOARD MEETING OF
November 14, 1995
NO.
4. CONSENT CALENDAR a.
ADVISE THE BOARD OF THE CLOSE OUT OF THE
PREAERATION ODOR CONTROL PROJECT (DP 7108)
DATE
November 7, 1995
TYPE OF ACTION
SUBJECT
INFORMATIONAL
SUBMITTED BY
Munawar Husain, Associate Engineer
INITIATING DEPT.lDIV.
Engineering Department/
Plant En ineerin Division
ISSUE: All work has been completed on the Preaeration Odor Control project, and this project can
now be closed out.
BACKGROUND: Work completed under this project provides odor control in the primary area for
the preaeration tanks, distribution channels, effluent channels, and the chemical feed building. A
new Calvert scrubber unit has been added along with associated tanks, equipment, fiberglass ducts,
and piping. The tanks and channels have been provided with removable flat aluminum covers that
contain the foul air beneath the covers. The foul air is conveyed in fiberglass ducts to the scrubber
unit where the odors are removed prior to release to the atmosphere. Details of the project were
included in the Fiscal Year 1993-94 Capital Improvement Budget (CIB).
The construction contract was awarded to Monterey Mechanical Company of Oakland, California,
on July 15, 1993, by the District Board of Directors. The contractor was issued a Notice to Proceed
on August 18, 1993. The contract completion date was August 31, 1994. The contract work was
completed on time, with the District taking beneficial occupancy of the new facilities on August 26,
1994.
Monterey Mechanical Company's original construction contract was for $850,000. There were 15
change orders issued on the project totalling $36,285. The total contract amount paid to Monterey
Mechanical Company was $886,285.
The total budget for the project was $1,343,000. The total completed project cost is $1,273,000.
Staff is closing out the project account, which will result in $70,000 being returned to the
Treatment Plant Program.
RECOMMENDATION: This item is presented to the Board of Directors for information. No action
is necessary.
RE~EWEDANDRECOMMENDEDFORBOARDAcnON
MH
RAB
1302A-7/91
RSK
{);[iJ
WEB
~
~
PAGE OF 2
BOARD MEETING OF November 14, 1995
NO.
6. BIDS AND AWARDS a.
SUBJECT
DATE
November 3, 1995
REJECT All BIDS FOR PURCHASE OF REDUNDANT CASCADE TYPE OF ACTION
UNINTERRUPTIBlE POWER SUPPLY (UPS) REJECT BIDS
SUBMITTED BY
INITIATING DEPT./DIV.
Cheri Arstani, Principal Buyer
Ad m in istrative/Purc hasing
ISSUE: On October 18, 1995 sealed bids were received and opened for the purchase of one
redundant cascade uninterruptible power supply (UPS) for Capital Improvement Project No. 6110.
The Board of Directors must award purchase or reject all bids within 60 days.
BACKGROUND: The District treatment plant's main UPS supplies continuous electrical power to
critical process control equipment, radio and telephone systems, MIS computer equipment, and
the new network server even during a complete power failure. The UPS has been well maintained
and has operated continuously for nearly 20 years with minimal downtime. However, replacement
parts are now obsolete and no longer available, and the last of on-hand spare parts have been
used. Recent UPS failures have caused subsequent failures to many of the critical loads. Because
of this, the UPS is no longer redundant or reliable, and it is necessary to replace the UPS.
Bids were sent to four suppliers. Two bids were received and publicly opened on October 18,
1995, as follows:
Cyberex
International Power
$102,728.60
91,952.00
Technical evaluation revealed that by proceeding with the purchase and installation of the UPS
as bid, an unanticipated construction expense and a potential safety hazard would result.
Technological changes in the UPS industry have favored reducing the input current requirement,
which increases the input voltage and the number of batteries required. In our case, the number
of batteries increased from 20 to 108 cells. The size and configuration of the battery racks would
create a safety hazard for maintenance personnel if installed in the existing battery room.
Expansion of the battery room would be a costly and impractical solution.
By reducing the emergency backup time requirement from four hours to one and one half hours,
the battery size (physical dimensions) can be reduced such that modification of the battery room
would be unnecessary and safety would not be compromised. With the availability of
cogeneration and standby power, the backup time would be sufficient even at full load. This
change should result in an approximate equipment savings of $20,000, and more bidders may
~
GEN5f{fHIEF ENG.
/fJJ5 )L
ROGER . DOLAN
INITIATING DEPT./DIV.
1302A-7/91
CA
KFl
PM
ADS/PosPapers1/UPS-Bids.pp
--------------_."--------------+._._-------'~--_._--_._~-_.".._~._-_..__._--,_._--_.__._,_.__."-_._----_.".~.-,.------.-..---.--------.-..-.-.
SUBJECT
POSITION PAPER
REJECT ALL BIDS FOR PURCHASE OF REDUNDANT CASCADE
UNINTERRUPTIBLE POWER SUPPLY (UPS)
PAGE
DATE
2 OF 2
November 3, 1995
be motivated to submit competitive bids. Staff believes it is in the best interest of the District to
reject all bids, incorporate changes in the design criteria and rebid the project.
RECOMMENDATION: Reject all bids for District Project No. 6110, purchase of a Redundant
Cascade Uninterruptible Power Supply.
1302B-7/91
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
PAGE 1
OF 5
BOARD MEETING OF
November 14, 1995
NO.
9. ENGINEERING a.
SUBJECT
ADOPT A RESOLUTION APPROVING DIRECTIONAL DRILLING
DEMONSTRATION PROJECT AND AUTHORIZE THE GENERAL
MANAGER-CHIEF ENGINEER TO EXECUTE A CONTRACT WITH
UTI LX CORPORATION FOR THE MARTINEZ DOWNTOWN
TRUNK SEWER PROJECT, DISTRICT PROJECT NO. 4950
DATE
November 8, 1995
TYPE OF ACTION
AUTHORIZE RESOLUTION/
AUTHORIZE AGREEMENT
SUBMITTED BY
Curtis W. Swanson
Principal Engineer
INITIATING DEPT./DIV.
Engineering Department/
Infrastructure Division
ISSUE: Board authorization is required for the General Manager-Chief Engineer to execute
construction contracts over $10,000 and to exempt projects from public bidding for field testing
purposes.
BACKGROUND: The trunk sewer serving the eastern part of downtown Martinez is deteriorated
and undercapacity. The sewer was installed in the 1920's. Overflows from this sewer
occurred during the winter of 1995 near Court, Jones and Pine streets. Currently, the District
is designing a new 3,500-foot-long trunk sewer that will be constructed during 1996.
However, staff is concerned that additional overflows may occur during the 1996 winter
season. Staff feels an urgency to protect the neighborhood and proposes to install a 550-foot-
long section of new parallel sewer to alleviate a hydraulic bottleneck before the rainy season.
Staff determined that installation of a new sewer along a new alignment using a trenchless
technology construction method called directional drilling is the most practical alternative for
this project because of the potential for minimizing construction and traffic impacts on the
neighborhood. The new parallel sewer will be installed in two phases. An 8-inch sewer will
be installed by directional drilling during 1995. (An 8-inch sewer is the maximum size that can
be installed by directional drilling.) This sewer will be enlarged to 12-inch diameter by pipe
bursting during 1996. This approach provides near-term overflow protection, eliminates open-
cut construction, and allows an opportunity to use newer directional drilling technology. The
project location is shown in Attachment 1.
In 1988 and 1989, the District conducted demonstration projects with Flow Mole Corporation
involving directional drilling. While the results of these demonstration projects were generally
favorable, there were problems maintaining vertical alignment using the directional drilling
technology. During the last six years, there have been significant improvements and
developments in the UTILX (successor to Flow Mole Corporation) directional drilling technology.
Staff is proposing to conduct a new and separate demonstration project using improved
directional drilling technology developed by UTILX Corporation of Kent, Washington.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INIT8'\r; ~DIV
1302A-7/91
141
~
CWS
JSM
RAB
ADOPT A RESOLUTION APPROVING DIRECTIONAL DRILLING
DEMONSTRATION PROJECT AND AUTHORIZE THE GENERAL
MANAGER-CHIEF ENGINEER TO EXECUTE A CONTRACT WITH
UTILX CORPORATION FOR THE MARTINEZ DOWNTOWN
TRUNK SEWER PROJECT, DISTRICT PROJECT NO. 4950
SUBJECT
PAGE
DATE
2
OF
5
November 8, 1995
Earlier this year, the District conducted adirectional drilling demonstration under the Knox Drive
Sewer Project, DP 4602. This demonstration project used proprietary directional drilling
equipment and methods developed by Underground Construction Company, Inc. Although this
project was eventually successful, there were installation problems associated with differing
site conditions and the drilling fluid system. Staff has made changes or improvements to the
proposed project to address these types of problems. These improvements include more
extensive specifications and shop drawing requirements for pipe materials, reaming operations,
and monitoring and operation of the drilling fluid system.
The directional drilling system now used by UTILX Corporation is different in several aspects
from the directional drilling systems used in the previous demonstration projects, including the
project conducted earlier this year. The principal differences are: 1) a different shaped boring
head, and 2) an enhanced control system within the boring head. The new control system
allows installation of sewers on a 1 percent slope. Previously, District staff has used directional
drilling only on sewers with slopes greater than 2 percent.
Demonstration projects, in general, have risks associated with them. The directional drilling
technology has advanced to a point where the risks associated with this project have been
minimized. The proposed method has a significant installation advantage by limiting impacts
to the travelling public and neighborhood businesses. Staff concludes that there is sufficient
justification to try this improved method of installing gravity sewers by drilling, rather than open
cut.
Staff conducted a review of potential firms capable of performing this project and has
determined that only UTILX Corporation has the capability to perform the proposed work with
directional drilling. Other firms use directional drilling equipment with less sophisticated control
and guidance systems. These firms are not able to install a gravity sewer with a 1 percent
slope.
Exemption from bidding for this project is allowed under Public Contract's Code, Section 3400.
Staff believes that this project is exempt from bidding as a field test or experimental project
because: 1) sewer pipelines have not been installed at the District using the improved
directional drilling technology, and 2) one of the primary objectives of the project is to
demonstrate the applicability of using directional drilling technology on future sewer
construction projects.
13028-7/91
ADOPT A RESOLUTION APPROVING DIRECTIONAL DRILLING
DEMONSTRATION PROJECT AND AUTHORIZE THE GENERAL
MANAGER-CHIEF ENGINEER TO EXECUTE A CONTRACT WITH
UTILX CORPORATION FOR THE MARTINEZ DOWNTOWN
TRUNK SEWER PROJECT, DISTRICT PROJECT NO. 4950
SUBJECT
PAGE
DATE
3
OF
5
November 8, 1995
A unit price contract with a cost ceiling of $49,500 has been negotiated with UTILX
Corporation. The scope of this contract includes mobilization and demobilization, installation
of approximately 550 feet of 8-inch sewer by directional drilling, modification of two manholes,
and temporary bypass pumping.
The total estimated construction cost for the demonstration project will be $83,000. This
estimate includes the work by UTILX Corporation, staff labor for public information,
construction management and inspection, and a contingency for unforeseen conditions. A
summary of these project costs is presented in Attachment 2. Construction of the Martinez
Downtown Trunk Sewer Project is included in the fiscal year 1995-96 Capital Improvement
Budget (CIB) on pages CS-51 through CS-53. The total project cost included in the CIB is
$1,986,000. This demonstration project is a part of the Martinez Downtown Trunk Sewer
Project.
This project has been evaluated by staff, and it has been determined to be exempt from the
California Environmental Quality Act (CEQA) under District CEQA Guidelines, Section 18.2,
because it involves only minor alterations of existing facilities with negligible or no expansion
of dry-weather flow capacity. Board of Directors' approval of this project will constitute a
finding that the project is exempt from CEQA.
RECOMMENDATION:
1 . Adopt a resolution finding that pursuant to Public Contract Code, Section 3400 (b) that
entering into a contract for use of UTILX Corporation's directional drilling technology is
required so that the District may perform a field test or experiment to determine the
suitability of the technology for future District use.
2. Authorize the General Manager-Chief Engineer to execute a contract with UTILX
Corporation in the amount of $49,500 for construction of the Martinez Downtown Trunk
Sewer, DP 4950.
13028-7/91
,/ .,
f:
'"
g
200
FEET
<
Central Contra Costa
~ Sanitary District
o
ATTACHMENT
"'
g;
DIRECTIONAL DRilliNG
DEMONSTRATION (OP 4950)
1
I
>
o
Z
I
~
Page 5 of 5
ATTACHMENT 2
COST ESTIMATE
Construction:
UTILX Corporation
Utility Pothoring
Contingency (20%)
SUBTOTAL
$ 49,500
1,500
1 0.000
$ 61,000
Construction Management:
Project Management
I nspection/ Ad ministration
SUBTOTAL
$ 5,000
8.000
$ 13,000
Services During Construction:
Engineering
Survey
Legal
Community Relations
Collection System Operations
Encroachment Permit/City Inspection
$ 2,500
2,000
500
1,000
1,000
2.000
SUBTOTAL
$ 9,000
TOTAL DEMONSTRATION PROJECT COST
$ 83,000
FUNDS ALLOCATED TO DATE
FOR DEMONSTRATION
$
o
ALLOCATION REQUIRED
FOR DEMONSTRATION
$ 83,000
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
PAGE 1
OF
2
BOARD MEETING OF
November 14, 1995
NO.
9. ENGINEERING b.
SUBJECT
DATE
November 8, 1995
AUTHORIZE THE GENERAL MANAGER-CHIEF ENGINEER
TO ALLOCATE $35,000 FROM THE COLLECTION SYSTEM
PROGRAM CONTINGENCY ACCOUNT FOR THE LAS TRAMPAS
CREEK STORM DAMAGE REPAIR PROJECT, DP 5080
TYPE OF ACTION
AUTHORIZE
ALLOCATION
SUBMITTED BY
Curtis W. Swanson
Principal Engineer
INITIATING DEPT./DIV.
Engineering Department/
Infrastructure Division
ISSUE: The Board must authorize allocations greater than $25,000 from the Capital
Improvement Program contingency accounts.
BACKGROUND: The interceptor sewer serving Orinda, Moraga, and Lafayette is located along
the former Sacramento Northern Railroad right of way in Lafayette and Moraga. The interceptor
sewer is reinforced concrete pipe ranging in size from 27 inches to 45 inches in diameter.
Certain reaches of the interceptor sewer are located next to Las Trampas Creek. During the
winter of 1995, high flows in Las Trampas Creek caused erosion of the creek bank at three
locations. Continued erosion at these three locations threatens to undermine the interceptor
sewer.
Under an initial allocation of $25,000 from the General Manager-Chief Engineer, preliminary
engineering and interim stabilization of the erosion areas have been accomplished prior to the
upcoming winter. An additional allocation is necessary to complete geotechnical engineering
and design of the long-term creek bank stabilization to protect the District interceptor sewer.
An allocation of $35,000 from the Collection System Program Contingency Account is
requested for this effort. A summary of the estimated design costs is listed in Attachment 1.
The estimated total project cost will range from $160,000 to $200,000.
RECOMMENDATION: Authorize the General Manager-Chief Engineer to allocate $35,000 from
the Collection System Program Contingency Account for the Las Trampas Creek Storm Damage
Repair Project, DP 5080.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INITIATI~ ~IV.
fr;4D
CWS
JSM
RAB
1302A-7/91
ATTACHMENT 1
LAS TRAMPAS CREEK REPAIRS
BUDGET SUMMARY
Geotechnical Engineering and Testing
Design/Drafting
Legal
Survey
Permits/Right of Way
SUBTOTAL
Preliminary Engineering/Interim Stabilization
Total Design Phase Cost
Funds Previously Authorized
Funds Requested
ESTIMATED
COST
$ 9,000
1 7,000
1,000
3,000
5,000
$35,000
$25,000
$60,000
$25,000
$35,000
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
PAGE 1 OF 1
BOARD MEETING OF
November 14, 1995
NO.
10. HUMAN RESOURCES a.
SUBJECT
DATE
November 3, 1995
DIRECT STAFF TO SECURE THE SERVICES OF AN
ARBITRATOR IN ACCORDANCE WITH THE DISTRICT'S
GRIEVANCE APPEAL PROCEDURES
TYPE OF ACTION
HUMAN RESOURCES
SUBMITTED BY
Paul Morsen, Deputy General Manager
INITIATING DEPT./DIV.
Administrative
ISSUE: In accordance with the Memorandum of Understanding (M.O.U.) between the District
and the Central Contra Costa Sanitary District Employees' Association, Public Employees'
Union, Local No. One, the Board of Directors shall employ an arbitrator to render a
recommendation when grievances are appealed to the Board level.
BACKGROUND: Mr. Russell Leavitt, Planning Assistant, applied for a promotional
reclassification under the M.O.U., Article III, Section 7.1, Emolovee Reclassification Reauests.
Following staff review, Ms. Chris Casey, a consultant for Shannon & Associates specializing
in classification and recruitment, was engaged to make a recommendation regarding Mr.
Leavitt's request. After considerable study, Ms. Casey found: (1) Mr. Leavitt was working
within the scope of his classification; (2) the salary of the Planning Assistant is appropriate
for the assigned duties and responsibilities; and (3) the title of Planning Assistant is outdated
and could be modified. Mr. Leavitt filed an appeal under the relevant grievance procedures
of the M.O.U. to the General Manager-Chief Engineer. The General Manager-Chief Engineer
conducted a hearing and upheld the recommendation of the consultant. Consequently, Mr.
Leavitt is now appealing this matter to the Board in accordance with the M.O.U., Article III,
Section 2.4.
In matters that are appealed to the Board, the M.O.U. reads as follows:
A. "In the event such differences are not settled and the grievant desires the grievance.to
be considered further, it shall be presented, in writing, to the Secretary of the District
within five (5) days of receipt of the General Manager-Chief Engineer's decision. The
Secretary shall calendar the agenda item at the next regularly scheduled Board Meeting
in keeping with established guidelines for calendaring an agenda item."
B. "The Board shall employ a neutral third party to hear the appeal and to recommend action
to the Board."
C. "The Board may adopt, reject, or modify the recommendation of the Board-appointed
neutral third party. The decision of the Board is the final action of the District."
RECOMMENDATION: Authorize staff to secure the services of an arbitrator in accordance
with the District's appeal procedures in the grievance of Planning Assistant Russell Leavitt.
RE~EWEDANDRECOMMENDEDFORBOARDAcnON
PM
L