HomeMy WebLinkAboutAGENDA BACKUP 09-21-95
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
PAGE 1 OF
2
BOARD MEETING OF
September 21, 1 995
NO.
4. CONSENT CALENDAR a.
AUTHORIZATION FOR P.A. 95-15 (ALAMO) TO BE
INCLUDED IN A FUTURE FORMAL ANNEXATION TO
THE DISTRICT
DATE
September 13, 1995
TYPE OF ACTION
SUBJECT
ACCEPT ANNEXATION
FOR PROCESSING
SUBMIIJED B't H II
uenms a
Associate Engineer
INITIATING DEPT-lDIV.
Englneenng Departmentl
Infrastructure Division
PARCEL
NO.
95-15
AREA OWNER/ADDRESS
PARCEL NO. & ACREAGE
REMARKS
LEAD
AGENCY!
CCCSD
Alamo G.A. and S.A. Neighbors
(77D1) 20 Mt. Rushmore Place
Clayton, CA 94517
(187-120-022) 0.29 AC.
Existing house with a
failing septic system;
must connect to the
public sewer system.
Project is exempt from
CEQA.
RECOMMENDATION: Authorize P.A. 95-15 to be included in a future formal annexation.
REVIEWED AND RECOMMENDED FOR BOARD ACTION
INITIATING DEPT.IOIV.
d)t(
00
1302A-7/91 DH
JSM
RAB
, \
, \
,
,
,
,
, '
, ,
\ \ ,
\-1.-.....' ,
'''' \ ,
"1>' ,
, \,~ \ ,
"9" ,
, ,..... \ ,
, ,<",
, " ,
, ,\
, \
, , \ \
, ,\
, \ , \
\ \ 6'\
\ \~\
\ \ \
, , \,
, \ ,
\ , ,
, \ ,
\ " \
\ .,
\,' ,~\
\i ,~,
1\ \ '.
'. ,
, \,
\ \
\
\
,
,
\
\,
\
\
\
\
,
,
,
,
.'~~
\
I
PROPOSED ANNEXATION
P.A. 95-15
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
PAGE 1
OF
1
BOARD MEETING OF
September 21, 1995
NO.
4. CONSENT CALENDAR. b.
DATE
SUBJECT
ACCEPT CONTRACT WORK FOR CSOD FACILITY
RECONFIGURATION PROJECT, DP 9023, AND
AUTHORIZE FILING OF THE NOTICE OF COMPLETION.
Se tember 18 1995
TYPE OF ACTION
ACCEPT CONTRACT
WORK
SUBMITTED BY
INITIATING DEPT.lDIV.
Tom Godsey, Associate Engineer
Collection System Operations
ISSUE: Construction has been completed on the CSOD Facility Reconfiguration Project, DP 9023,
in Walnut Creek, and the work is now ready for acceptance.
I
BACKGROUND: The District initiated a capital project to reconfigure the CSO Yard in 199q in
anticipation of the loss of approximately 1 acre (22 % of the usable of corporation yard area) due
solely to the CAL Trans 1680/24 Project. The District's project included the purchase of additioral
property and the design of replacement facilities including a Vehicle Maintenance Shop, retaining
walls, grading, paving, fencing, and landscaping. Negotiations are underway with CAL Trans
regarding reimbursement of the District for its costs. CAL Trans has paid $798,000 as part df a
I
negotiated settlement for the Right of Entry.
The CSO Yard was an existing, non-conforming use, under the City of Walnut Creek's Gen~ral
Plan. The magnitude of the Reconfiguration Project, which is occasioned solely by the CAL Tr~ns
work, triggered the need for obtaining a General Plan Amendment and a Conditional Land Use
Permit. The planning and design work has been completed under the City of Walnut Creek plan
and Design Review processes adding both time and cost to the project. Additional information
on the project is presented on pages GI-12 and GI-13 of the Capital Improvement Budget.
On February 28, 1994, the Board of Directors authorized the award of a contract for constructjon
of the project to N. E. Carlson Construction Co, of Brentwood. The Notice to Proceed was issued
on April 26, 1994, with a specified completion date of August 24, 1994. The project scope was
revised and the completion date extended to November 10, 1994. Inclement weather
subsequently delayed completion of the additional work until June 6, 1995 when the work was
substantially completed. The remaining work consists of maintenance items which do not affect
the project acceptance.
The total authorized budget for the project including the cost of engineering design, contr~ct
construction and administration, inspection, community relations and testing services is
$1,537,000. A detailed accounting of the project cost will be provided to the Board at the time
of project closeout. It is appropriate to accept the contract work at this time.
RECOMMENDATION: Accept the contract work for the construction of the CSOD Facility
Reconfiguration Project, DP 9023, and authorize the filing of the Notice of Completion.
RE~EWEDANDRECOMMENDEDFORBOARDAcnON
INITIATING DEPT.lDIV.
u7v
1302A-7/91
TG
JAL
~
Central Co~tra Costa Sanitary District
BOARD OF DIRECTORS
PAGE 1
OF
,2
B..QARD MEE11NG Of
::septemoer "L 1, 1 995
NO.
7. ENGINEERING a.
SUBJECT
AUTHORIZE THE GENERAL MANAGER-CHIEF ENGINEER TO
EXECUTE A $200,000 CONSTRUCTION CONTRACT CHANGE
ORDER ON THE PLEASANT HILL RELIEF INTERCEPTOR
PROJECT, PHASE 3 (D.P. 5031), FOR DIFFERING SITE
CONDITIONS NEAR K-MART
August 21, 1 995
TYPE OF AGTJQti. '
AU I HORIZE CHAN~E
ORDER
DATE
SUBMITTED BY
Charles A. Canepa, Assistant Engineer
INITIATING DEPT./DIV.
Engineering Department/Infrastructure Divisici>n
ISSUE: Authorization by the Board of Directors is required for the General Manager-Chief Engineer
to execute a construction contract change order in an amount greater than $50,000.
I
BACKGROUND: Phase 3 of the Pleasant Hill Relief Interceptor Project (D.P. 5031) includes the
construction of 4,900 feet of 48-inch sewer line and 5,200 feet of reclaimed water line. The
majority of the sewer line is to be installed by microtunneling. The alignment of the pipeline' is
generally along the west bank of Grayson Creek from Chilpancingo Parkway to Taylor Boulevard.
The Notice to Proceed for construction was issued to the Contractor (McGuire and Hester) on
June 5, 1995, and construction commenced at the site next to the K-Mart Shopping Center parking
lot. Towards the end of July, a problem developed due to differing site conditions resulting in
increased costs and delays .to the Contractor's work. A brief chronology is as follows~
On July 28, 1995, the tunneling machine encountered wood debris approximately 400 feet into ~he
725-foot bore and for approximately 70 feet thereafter as evidenced by the presence of wqod
fragments in the soils removed during the tunneling operation.
On July 29, 1995, the cutting head of the machine became clogged, causing the Contractor to Iqse
all ability to control the machine. The cause of the clogging was thought to be wood debtis.
Various attempts by the Contractor to re-start the tunneling operation failed. The operation ""as
discontinued until a resolution could be determined. The boring head was located approximately 2:50
feet from the receiving pit (near the McDonald's Drive-thru) underneath the K-Mart parking lot
adjacent to Grayson Creek.
I
On July 31, 1995, the Contractor and District staff decided to excavate to the boring head,
approximately 25 feet deep, to confirm the nature of the obstruction. During the excavat,on
process, the Contractor encountered groundwater, large tree roots and stumps, and numerous latge
boulders below the surface. It has been learned that a rock quarry occupied the site before it vjtas
abandoned to accommodate the Shopping Center. It appears that a small side stream from ~he
quarry site crossed the interceptor alignment at the approximate location of the boring head. The
former small stream bed was apparently backfilled with rocks and debris many years ago. The
removal of the boulders, tree roots, stumps, and copious groundwater made the excavation process
extremely slow and arduous.
REWEWEDAND RECOMMENDED FOR BOARD AcnON
CAC
f/If
w
INITIATING DEPT.lDIV.
(3tF2-
1302A-7/91
JSM
RAB
AUTHORIZE THE GENERAL MANAGER-CHIEF ENGINEER TO
EXECUTE A $200,000 CONSTRUCTION CONTRACT CHANGE
ORDER ON THE PLEASANT HILL RELIEF INTERCEPTOR
PROJECT, PHASE 3 (D.P. 5031), FOR DIFFERING SITE
CONDITIONS NEAR K-MART
SUBJECT
PAGE 2 OF 2
DATE
AUTHORIZE CHANGE
ORDER
On August 1, 1995, the Contractor uncovered the boring head and confirmed that pieces of
wood had accumulated on the face of the boring machine, clogging the slurry recirculation
system. The Contractor removed wood fragments and mud from the cutting face and attempte~
to re-push the pipe. The attempt was unsuccessful. Apparently, material had squeezed and
hardened around the boring head and nearby sections of pipe, preventing any further movement~
The Contractor and District staff then decided to remove the boring head and to complete the
remaining 250 feet of pipe using a conventional open cut method.
Because of the differing site conditions (unknown boulders, roots, and stumps) and the need tq
minimize disruptions of the K-Mart Shopping Center and the nearby McDonald's Restaurant, the
Contractor agreed to continue the work expeditiously. Records of all extra costs were kept on
a time and material basis. The total cost for this change order is $200,000. The Contract will
also be extended by 22 calendar days.
RECOMMENDATION: Authorize the General Manager-Chief Engineer to execute a $200,00Q
contract change order with McGuire and Hester for extra costs associated with differing site
conditions encountered in the K-Mart Shopping Center parking lot.
13028-7/91
Central Contra Costa Sanitary District
BOARD OF DIRECTORS
PAGE 1 OF
1
BOARD MEETING OF
September 21, 1995
NO.
7. ENGINEERING b.
SUBJECT
DATE
September 18, 1995
AUTHORIZE $57,000 FROM THE SEWER CONSTRUCTION
FUND TO THE GENERAL IMPROVEMENTS PROGRAM
CONTINGENCY ACCOUNT
TYPE OF ACTION
SUPPLEMENTAL
AUTHORIZATION
SUBMITTED BY
John J. Mercurio, Administrative Analyst
INITIATING DEPT./DIV.
Engineering Dept.lPlanning Division
ISSUE: Budget authorizations from the Sewer Construction Fund to Capital Improvement Prog~am
accounts may only be made by the Board of Directors.
BACKGROUND: The recently approved allocation from the General Improvements Contingercy
Account for completion of the Emergency Operations Centers will deplete the account. Sinoe it
is early in the fiscal year, it is likely that other contingency allocations will be needed. .
In the past, the contingency account has been funded at five percent of projected bu~get
allocations for the fiscal year . However, since budgeted allocations in the Generallmprovem~nts
Program have declined over the past few years, the five percent criterion results in a very s~all
amount ($43,000 this year). It is proposed that in the future the balance of program contingency
accounts be set at the five-percent-of-projected-allocations level or $100,000, whichever is
greater. To achieve this balance for the current fiscal year, staff recommends a suppleme~tal
authorization of $57,000.
RECOMMENDATION: Authorize $57,000 from the Sewer Construction Fund to the Genieral
Improvements Program Contingency Account.
JMM
DJC
RAB
RE~EWEDANDRECOMMENDEDFORBOARDAcnON
v lJf~