1. CALL MEETING TO ORDER
Chair McGill called the meeting to order at 3 p.m.
2. PUBLIC COMMENTS
None.
3. OLD BUSINESS
a. Contra Costa Lawsuit Regarding Bid Rigging
The County's lawsuit was discussed and staff confirmed that the alleged
bid rigging was specifically on the Guaranteed Investment Contracts that
were used as investments from the bond proceeds and not bid rigging on
the interest rates paid on the bonds.
COMMITTEE ACTION: Receive report.
*b. Outstanding Expenditure Questions
The outstanding questions from the prior Committee meeting were
reviewed. The attached outstanding question regarding work done by
Expert Tree Service was brought to the meeting as it was not available at
the time the agenda was delivered.
...
'" Recycled Paper
Budget and Finance Committee
November 17, 2008
Page 2
COMMITTEE ACTION: The Expert Tree Service invoice appears
high. Member Nejedly asked for additional review and would like to
make a site visit to assess the number of hours that were required to
get the job done. Staff will follow up and report back on the
appropriateness of the charges.
4. CLAIMS MANAGEMENT
a. Review Outstanding Claims
The District may receive two small claims from last fiscal year. A new
general liability claim was filed by Joann Ariff who ran over a pressure
valve and received minor damage ($155). The valve has been repaired.
There is one outstanding auto claim where an employee knocked over a
post box, the claim has not been received yet. A new accident involved a
temporary employee who backed into a pillar, damaging the District
vehicle's taillight and rear section.
COMMITTEE ACTION: Received report.
5. REPORTS/ANNOUNCEMENTS
a. GASB 45 Trust
The Committee discussed the volatility of the market and decided to start
depositing GASB 45 monies into the Trust per the Board Initial Investment
Policy.
COMMITTEE ACTION: The Committee directed staff to invest the
first monthly installment to the Trust upon its establishment. The
documents should be signed by the Controller this week and the first
deposit will be made no later than the end of next week.
b. Review draft CAFR and related position paper
The Committee reviewed the draft CAFR.
COMMITTEE ACTION: Recommend approval to submit the CAFR to
the GFOA.
Budget and Finance Committee
November 17, 2008
Page 3
c. Update on AIG
Staff indicated that AIG continues to be a safe provider of insurance and
will continue to monitor the situation.
COMMITTEE ACTION: Received the report.
6. REVIEW EXPENDITURES
COMMITTEE ACTION: Recommended Board approval of expenditures.
7. ADJOURNMENT - at 3:35 p.m.
Central Contra Costa Sanitary District
November 17, 2008
TO:
FROM:
BOARD BUDGET AND FINANCE COMMITTEE
RANDALL MUSGRA VES
DEBBIE RATCLIFF
SUBJECT:
November 3, 2008 Finance Committee Meeting
There was one additional question from the last Board Budget and Finance Committee
meeting which required additional staff research. The question and answer is provided
below:
1. 173022- Expert Tree Service- What work was done for $9,6201
In the fall of 2006, a main sewer extension was constructed in a difficult
easement location in Orinda (66 La Encinal). During the violent storm of late
January 2008, a large tree (40" diameter Monterey Pine) adjacent to the
easement toppled. Staff determined that the sewer installation work may have
contributed to the loss of the tree as pruning some of the roots had been
necessary during construction. Expert Tree Service, which has a blanket contract
with CCCSD for tree work, was engaged in February 2008 to remove all of the
debris (limbs, etc) except for the trunk, and to cut the trunk into "rounds." The
rounds were left on site. Last summer, the Moraga-Orinda Fire Protection District
contacted the property owner and CCCSD and informed us that the rounds had
to be removed from the site as they posed an imminent fire hazard. Expert Tree
was again engaged to cut the rounds into manageable pieces, remove them from
the site and dispose of them properly. The work was very challenging as it
required all of the material to be hand carried up a steep slope to La Encinal. A
total of 18.5 person-days @ $520 per person-day ($9,620) was required to
complete the work. The work was monitored by the CCCSD inspector assigned
to Lamorinda.